A simple CPM network has five activities, A, B, C, D, and E.
Question
A simple CPM network has five activities, A, B, C, D, and E. A is an immediate predecessor of C and of D. B is also an immediate predecessor of C and of D. C and D are both immediate predecessors of E. Given the above scenario, which of the following is correct? – Q/A (Question and Answer)
Test Answer
Answer:
There are four paths in this network
Recource SCMA 331 DSM 3 Chapter 3 (Project Management)
Unlock this answer
Join StudyHippo to unlock
unlock