A simple CPM network has five activities, A, B, C, D, and E.

Question
A simple CPM network has five activities, A, B, C, D, and E. A is an immediate predecessor of C and of D. B is also an immediate predecessor of C and of D. C and D are both immediate predecessors of E. Given the above scenario, which of the following is correct? – Q/A (Question and Answer)

Test Answer

Answer:

There are four paths in this network