SCMA 331 DSM 3 Chapter 3 (Project Management) – Flashcards

Unlock all answers in this set

Unlock answers
question
__ is the amount of time an individual activity in a network can be delayed without delaying the entire project.
answer
Slack time
question
A project's critical path is composed of activities A (variance .33), B (variance .67), C (variance .33), and D (variance .17). What is the standard deviation on the critical path?
answer
1.22
question
WBS stands for which of the following project management tools?
answer
Work Breakdown Structure
question
A simple CPM network has five activities, A, B, C, D, and E. A is an immediate predecessor of C and of D. B is also an immediate predecessor of C and of D. C and D are both immediate predecessors of E. Given the above scenario, which of the following is correct?
answer
There are four paths in this network
question
An activity has an optimistic time of 11 days, a most likely time of 15 days, and a pessimistic time of 23 days. What is its variance?
answer
4
question
With respect to PERT and CPM, slack is the...
answer
amount of time a task may be delayed without changing the overall project completion time
question
An activity has an optimistic time of 15 days, a most likely time of 18 days, and a pessimistic time of 27 days. What is the expected time?
answer
19 days
question
Which of the following is determined during the forward pass?
answer
Early Start
question
In a PERT network, non-critical activities that have little slack need to be monitored closely
answer
because near-critical paths could become critical paths with small delays in these activities
question
The critical path for the network activities shown below is __ with duration __
answer
B-C-E; 12
question
An activity on a PERT network has these time estimates: optimistic = 2, most likely = 5, and pessimistic = 10. Its expected time is:
answer
5.33
question
The critical path of a network is the
answer
longest time path through the network.
question
PERT analysis computes the variance of the total project completion time as:
answer
The sum of the variances of all activities on the critical path.
question
Which of the following statements regarding PERT analysis is true?
answer
Only critical activities contribute to the project variances.
question
Dummy activities
answer
are used when two activities have identical starting and ending events.
question
Which of the following is a basic assumption of PERT?
answer
no activity in the network must be repeated
question
Which of the following statements regarding Gantt charts is true?
answer
Gantt charts are visual devices that show the duration of activities in a project.
question
Which of these statements regarding time-cost tradeoffs in CPM networks is true?
answer
Crashing shortens the project duration by assigning more resources to one or more of the critical tasks.
question
The EF of an activity is the:
answer
ES + Activity time
question
The three phases involved in the management of large projects are:
answer
planning, scheduling and controlling.
question
An activity on a PERT network has these time estimates: optimistic =2, most likely = 3, and pessimistic 8. Its expected time and variance (if it is a critical activity) are:
answer
3.67 and 1
question
The Beta distribution is used in project management to
answer
Calculate expected activity times