In a PERT network, non-critical activities that have little slack need to be monitored closely – Q/A (Question and Answer)
Question
In a PERT network, non-critical activities that have little slack need to be monitored closely – Q/A (Question and Answer)
Test Answer
Answer:
because near-critical paths could become critical paths with small delays in these activities