The primary output of the planning cost management process is a change request. - Q/A (Question and Answer)
The primary output of the planning cost management process is a change request.
Question
The primary output of the planning cost management process is a change request. – Q/A (Question and Answer)
Test Answer
Answer:
False
Recource IT Project Management Exam 3 Review Ch 7-8