Wastewater Treatment Systems
Unlock all answers in this set
Unlock answersquestion
            What is a Class 4 Sewage System?
answer
        Septic Tank
question
            What are the classes of effluent?
answer
        Level 2: 30-25, Level 3: 15-15, Level 4: 10-10
question
            A treatment unit with a leaching bed must not exceed what class of concentrations?
answer
        Level 4
question
            Is it true that all units must be fitted with alarms?
answer
        Yes
question
            For a leaching bed as a shallow buried trench, the total length of distribution pipe must not be less than:
answer
        30 meters
question
            This formula is used to calculate length for any other leaching bed:
answer
        L=QT/300
question
            What are the daily flow limits for filter beds?
answer
        5000L w/ septic tank OR 10,000L where unit is a level 2, 3, or 4
question
            When used in conjunction with a filter bed, loading on surface should not exceed:
answer
        100L/m2/day
question
            Treatment unit with dispersal bed should not exceed level _____ unit
answer
        4
question
            Type A dispersel bed must be backfilled with _____ to avoid ______
answer
        leaching bed fill, depressions
question
            In a type A dispersal bed, the combined thickness of sand and stone layer must not be less than:
answer
        500mm
question
            Sand in a type A diserpsal bed must have a percolation time of:
answer
        not less than 6 but not more than 10
question
            Sand in type A dispersal bed must not have more than ____ fines passing through a ____ sieve
answer
        5%, No. 200
question
            Sand in type A dispersal bed must have an area not less than:
answer
        A=QT/850
question
            The stone layer in a Type A dispersal bed must not be less than ____ thick
answer
        200mm
question
            The bottom layer of stone in a Type A dispersal bed must be at least ____ above the groundwater table
answer
        600mm
question
            The minimum area of the stone layer in a Type A dispersal bed must not be less than this formula:
answer
        A=Q/B
question
            The slope of a Type B dispersal bed must not exceed this many units:
answer
        1 unit horizontally to 7 units vertically
question
            Type B dispersal bed must not be more than ____in depth with a percolation time of:
answer
        1000mm, P>15 minutes
question
            Type B dispersal bed must be backfilled with:
answer
        leaching bed
question
            Type B dispersal bed must be this high above water table:
answer
        600mm
question
            (Type B Bed) Self-draining distribution pipes must be at least ____ in diameter
answer
        3mm
question
            (Type B Bed) Stone layer must not be ____ below or ___ above the pipe
answer
        250mm, 50mm
question
            (Type B Bed) pipes must not be more than _____ apart or _____ from the edge of the bed
answer
        1.2mm, >600mm
question
            Area of a Type B bed determined by:
answer
        A=QT/400
question
            (Type B Bed) Linear loading rates must not be greater than:
answer
        40L/m if P > 24 min  50L/m if P < 24 min
question
            width of Type B bed must not exceed:
answer
        4 meters
question
            A Class 5 Sewage system is:
answer
        a holding tank designed to accept sewage until the tank capacity is reached, it is then pumped away to an offsite
question
            Class 5 system usually has _____ chambers
answer
        1
question
            (Class 5) Working capacity must be no less than:
answer
        9,000L
question
            (class 5) All tanks in residual dwellings must have a minimum of ____ day carrying capacity
answer
        7
question
            Scenarios in which a Class 5 sytem is used:
answer
        -temporary, 12 months or less  -remedy to an unsafe system  -an upgrade, if class 4 is not possible  -municipal systems not yet available
question
            Do class 5 systems require an alarm?
answer
        Yes, for capacity
question
            Vents on a class 5 system must be no less than:
answer
        3 inch trade size
question
            A class 5 system must terminate _____ above finished grade, or _____ if the area is flood prone
answer
        300mm, 600mm
question
            (class 5 system) must terminate at least _____ away from any air inlet
answer
        3.5 meters
question
            Class 5 System Clearances
answer
        1.5m from structures  15m from all wells  15m from springs  3m from the property line
question
            (CP) plans and specifications should include:
answer
        -cross sectional drawing  -site plan  -list of materials
question
            (CP) Treatment and holding tanks must conform to:
answer
        CSA-CAN3-B66
question
            (CP) distribution piping must not be less than ____ for gravity flow and ____ for pressurized sytems
answer
        3 inches, 1 inch
question
            (CP) fill stone for trenches must be covered with:
answer
        untreated building paper or permeable geo-textile
question
            (CP) Unacceptable fill material includes:
answer
        -material where PT>20min/cm   -too much silt or clay
question
            (CP) important installation factors include:
answer
        -depth of installation  -debris removal  -leveling and backfilling  -uplift prevention  -backfill compaction
question
            (CP) a pump is required when:
answer
        -effluent must be delivered to higher elevation, if lenth of pipe is more than 150m a Type B diserpsal system is used
question
            (CP) pumps must have capacity large enough to deliver dosage of effluent within:
answer
        15 minutes
question
            (Trenching) trenches must be at least ____ and not more than _____ wide, centres no closer than ____apart
answer
        500mm, 1000mm, 1.6m
question
            (trenching) not less than _____ and not more than ____ in depth, providing a minimum of ____ of stone beneath.
answer
        600mm, 900mm, 15cm
question
            The bottoms and sidewalls of a trench must be:
answer
        Scarified
question
            (trenching) stone fill at least ____ thick placed at bottom layer
answer
        15cm
question
            (Trenching) layer of washed stone at least ____ deep on top of pipes
answer
        50mm
question
            (trenching) after pipe and stone installation, what installed to block fine soil particles?
answer
        filter interface of building paper or geo-textile fabric
question
            (trenching) backfill must be composed of:
answer
        porous soil
question
            (trenching) topsoil layer of at least _____ to allow for grass
answer
        15cm
question
            What is the purpose of a raised leaching bed?
answer
        -to fix poor soil conditions  -to fix inadequate soil depth or bedrock  -to deal with a high groundwater table
question
            (trenching) an area must be graded ____ below natural grading
answer
        25cm
question
            (trenching) what are the 2 purposes of the fill material?
answer
        leaching bed and mantle
question
            leaching bed fill layer must be ____ from the water table:
answer
        900mm
question
            The mantle fill layer must extend ____ beyond the distribution pipes in any horizontal direction
answer
        15m
question
            Raised bed and mantle cannot have slope sides exceeding:
answer
        1 unit horizontally to 4 units vertically
question
            What are four main signs of a malfunctioning system?
answer
        -foul odour   -sewage backup  -breakout to surface  -water contamination
question
            How can a sump pit be involved in malfunction?
answer
        efflunt is picked up by weeping tile and being drained into building's sump pit, indicating break in pipe from building to treatment unit
question
            What is usually the cause of a breakout to surface?
answer
        hydraulic capacity of soil/fill beneath leaching bed being exceeded
question
            What is an important measure of groundwater contamination?
answer
        presence of faecal coliform
question
            What is one of the main causes of groundwater contamination?
answer
        installation less than 900mm above the groundwater table
question
            What building factors can reduce the performance of a sewage system?
answer
        -added bedrooms  -exceeds 15% of finished area of dwelling unit  -installation of new plumbing fixtures
question
            What are the main infrastructural factors of Durham's sewage system?
answer
        -12 wastewater treatment systems  -42 pumping stations  -2055kms of sewer pipe
question
            What is the simplest sewage treatment method in Durham?
answer
        waste stabilization pond
question
            What was the average flow for Durham in 2010?
answer
        41,392m3/day
question
            What are the two main factors of primary treatment in Durham?
answer
        -screening to remove solids  -primary clarifier, which consists of two settling tanks
question
            What happens during secondary treatment in Durham?
answer
        2 bioreactor tanks use anoxic and aerobic zones, air is bubbled through the tank.  micro-organisms break down components to NO2, CO2, and H2O
question
            What are five bugs found in the basin in Durham?
answer
        -bacteria  -protozoa  -metazoa  -filamentous bacteria   -algae and fungi
question
            What are some facts about the secondary clarifier in Durham?
answer
        -a sedimentation process that takes 4-6 hours  -Return Activated Sludge is returned to head of aeration tank for further use  -Waste Activated Sludge is removed from system
question
            Explain the disenfection process in Durham:
answer
        -achieved using a sodium hypochloride solution  -200 organisms/m3/s  -before discharge to lake, effluent is dechlorinated
question
            Sampling and analysis is performed at Durham how often?
answer
        Daily
question
            Once sewage is stabilized, it is sent to one of these two places:
answer
        Dufferin Creek WPCP or Corbett Creek WPCP