Project MGMT 7-12 – Flashcards

Unlock all answers in this set

Unlock answers
question
A rule of thumb for moderate-to high-techonology firms is that a six-month delay in bringing a product to market can result in a loss of about 35 Percent of the Market Share.
answer
True
question
Efforts to shorten a project's duration can occur before the project begins or while it is in progress.
answer
True
question
Indirect costs generally represent overhead costs such as supervision administration,consultants, and interests.
answer
True
question
The total cost for each possible duration of a project is the sum of labor, materials, and equipment
answer
False
question
Direct Costs are so named because they can be assigned directly to a work package and activity.
answer
True
question
To reduce the duration of a project by reducing activity duration the first criteria is that the activity to be reduced must be on the critical path.
answer
True
question
Shortening an activity's duration si termed crashing
answer
True
question
Crashing a critical activity as soon as a problem is detected is the best strategy to take.
answer
True
question
Sometimes an activity that is more expensive to crash should be crashed because it is less risky to crash than the cheaper one.
answer
True
question
One of the advantages of using a Project Cost-Duration Graph is that it keeps the importance of indirect cost in forefront of decision making.
answer
True
question
Intense global competition and rapid technological advances create pressure on developing projects rapidly. This is an example if reducing project duration caused by:
answer
the market
question
A contracter finished a bridge across a lake 18 months early and received more then $6 million for the early completion. This is an example of reducing project duration caused by.
answer
Incentive Contracts
question
The shortest possible time an activity can be completed realistically is called_time.
answer
Crash
question
The less steep the cost slope of an activity, the
answer
less it costs to shorten one time period.
question
Which of the following correctly calculates an activity's cost slope?
answer
(crash cost-normal cost)/(normal time-crash time)
question
The optimum duration for a project is at the point where
answer
total project costs are the lowest
question
If a network has several critical or near-creatical paths it is deemed to be:
answer
sensitive
question
A common method for shortening the project time is to
answer
A, B, and C are all correct
question
The most common method for shortening project time is to
answer
add additional staff and equipment
question
According to Brook's Law, adding more people to a late project is most likely to have which of the following impact?
answer
make the project slip further
question
An uncertain even or condition that, if it occurs, has a positive or negative effect on a project objectives is termed.
answer
risk
question
The chances of a risk event occurring as a project proceeds through its life cycle tends to
answer
slowly drop
question
The cost impact of a risk event occurring as a project proceeds through its life cycle tends to
answer
slowly rise
question
The attempt to recognize and manage potential and unforeseen trouble spots that may occur when a project is implemented is known as
answer
risk management
question
The initial step in the risk management process is to
answer
identify the risks
question
Which of the following would not be considered a threat?
answer
meeting the project schedule
question
All of the following are included in the risk identification process except
answer
competitors
question
One of the keys to success in risk identification is
answer
critical thinking
question
The easiest and most commonly used technique for analyzing risk is ___ analysis
answer
Scenario
question
The risk assessment form contains all of the following except
answer
who will detect the occurrence of the risk event
question
This risk assessment tool is a variation of the risk severity matrix that includes the ease of detection for each of the identified risks
answer
FMEA analysis
question
Which of the following is not one of the potential responses to a specific risk event?
answer
ignoring
question
A Risk Response Matrix contains all of the following except
answer
all of these are included in the matrix
question
Due to the impact over a long period of time, risk events that occur in the early stages of a project will have a greater costs impact than those that occur in later stages.
answer
False
question
During risk identification the smaller risks should be identified first because they will naturally lead to identifying the larger risks.
answer
False
question
The first step in the risk management process is Risk Assessment.
answer
False
question
Since the goal is to find problems before they happen, the project manager should encourage critical thinking when it comes to risk identification.
answer
True
question
Developing a scenario analysis includes the probability of the event and the impact of the event.
answer
True
question
Fixed price contracts are an example of transferring risk from an owner to a contractor
answer
True
question
Scheduling outdoor work in the summer, investing in up front safety training, and choosing high quality materials are examples of retaining a risk.
answer
False
question
Control is one of the most neglected areas of project management.
answer
True
question
Earned value is defined as the budgeted costs of the work performed
answer
True
question
The baseline is derived from merging information from the work packages with the project network.q
answer
True
question
If the actual costs for the first six months of a project are 1.5 million and the planned budget cost for the first six months are $1.2, then the project is automatically in trouble.
answer
False
question
Earned value is calculated by taking the percent complete times the original budget.
answer
True
question
The key to managing scope creep is change management
answer
True
question
A CPI index of 0.97 indicates that the project has spent less money than budgeted.
answer
False
question
The major reasons for creating a baseline are to monitor and report progress and to estimate cash flow.
answer
True
question
Adequate project controls have the advantage(s) of:
answer
A, B, and C are all correct
question
A typical project progress report would contain all of the following sections except:
answer
all of these are typical sections
question
The first step in the project control process of the measurement and evaluation of project performance is to
answer
set a baseline plan
question
The second step in the project control process of the measurement and evaluation of project performance is to:
answer
measure progress and performance
question
The third step in the project control process of the measurement and evaluation of project performance is to:
answer
compare the plan against actual performance
question
The last step in the project control process of the measurement and evaluation of project performance is to:
answer
take appropriate action
question
A typical tool used to communicate project status is a:
answer
Gantt Chart
question
A tool used to monitor past project schedule performance, current performance, and to estimate future schedule rends is a simple line chart known as a:
answer
project schedule control chart
question
The earned value of a project is the
answer
percent of the original budget that has been earned by the actual work
question
The cost variance for a project is calculated by
answer
EV-AC
question
Small refinements that eventually build to be major changes are known as:
answer
scope creep
question
Of the following costs, which is not included in the baseline?
answer
all of these are usually included
question
The storming stage of team development is completed once members begin to think of themselves as part of a group
answer
False
question
The norming stage of team development is complete when the group establishes a common set of expectation about how members should work together.
answer
True
question
Co-location of team members, team names, and team rituals are common vehicles for establishing a team identity.
answer
True
question
A project vision is an image a project team holds in common about how the project will look upon completion, how they will work together, and how customers will accept the project.
answer
True
question
Everyone on the project team should have identically the same vision of the project.
answer
False
question
Letters of commendation, public recognition for outstanding work, and desirable job assignments are types of individual rewards.
answer
True
question
Group decision making should be used when strong commitment to the decision is needed and there is low probability of acceptance if only one person make the decision.
answer
True
question
"Going native" is the ability that some project teams have to bypass the normal policies and procedures that everyone in the organization is supposed to follow.
answer
False
question
Groupthink refers to the tendency of members in highly cohesive groups to lose their critical evaluative capabilities resulting in quick decision making with little consideration of alternatives.
answer
True
question
Team members can be upset and dissatisfied with conflict, but as long as the disagreement furthers the objectives of the project, then the conflict is functional.
answer
True
question
During which stage of development is the team fully functional and accepted.
answer
Performing
question
Sam is the coach of a high school soccer team and has noticed that some close relationships have formed as well as feelings of camaraderie and shared responsibilities for the team's success. Which stage of development is the team in?
answer
Norming
question
Roger is new-product project manager for retail company. Recently the team has exhibited a high degree of conflict
answer
Storming
question
Which of the following is an objective of the first project team meeting?
answer
A, B, and C are all correct
question
Researchers have found that high performance teams will have which of the following norms?
answer
A, B, and C are all correct
question
All of the following have been found to be good for running effective project meeting except:
answer
all of these are good for effective meetings
question
Establishing a team identity is facilitated by
answer
A, B, and C are all correct
question
Individual rewards for outstanding work would not include:
answer
all of these can be used for individual rewards
question
The first step in facilitating group decision making is to:
answer
identify the problem
question
Strategies to manage dysfunctional conflict do not include__ the conflict.
answer
encourage
question
A 360-degree performance evaluation includes feedback from peers, project managers, subordinates, and even customers
answer
True
question
A project closure where the project is completed early with some parts of project eliminated would be classified as project failure
answer
False
question
The most common circumstance for project closure is simply a completed project such as building a new facility or creating a customized information system.
answer
True
question
The review of the response to hurricane Katrina is an example of a project closure.
answer
True
question
A goal of the retrospectives is to improve the way future projects are managed.
answer
True
question
Performance appraisals, in general, should focus only on the past performance and not on any future development plans for improving performance.
answer
False
question
The facilitator for the retrospective review should be independent and have authority to review results without recrimination
answer
True
question
A project can be closed because the priorities have changed.
answer
True
question
Wrapping up a project does not include acceptance by the customer
answer
False
question
Individual performance reviews should include the individuals self evaluation of his/her contributions
answer
True
question
Which of the following is not part of an effective project closure?
answer
all of these are included in an effective project closure
question
Project auditing includes performance evaluations of
answer
A, B, and C are all correct
question
The project closure process includes all of the following except
answer
conduct an audit
question
More and more companies are discarding the traditional superior-subordinate performance feedback process and replacing it with
answer
the 360-degree feedback
question
Project closures can fall into all of the following categories except
answer
all of these are categories for project closure
question
Highlighting major improvements actions that should be taken would typically appear in the _____ section of the final report.
answer
Recommendations
question
Project mission and objectives, procedures and systems used, and organization resources used typically appear in the___section of the final report.
answer
Analysis
question
Which of the following is not one of the recommended sections of the final report
answer
Strategic objectives
question
When archiving retrospectives the following can be used as classifications
answer
All of the above
question
The Final Report for a Project should include all of the following except:
answer
Selection of the next project
question
The environmental factor labeled security involves the capacity of a country's military and police forces to prevent and respond to attacks.
answer
True
question
The example of one project in Africa being paid in goat skins is an example of the environmental factor of infrastructure.
answer
False
question
Americans tend to underestimate the importance that relationship building plays in conducting business in other countries.
answer
True
question
Mexicans tend to perceive Americans as being cold and that most Americans look down upon them.
answer
True
question
In dealing with the French, a lot of what gets done is a result of going through administrative channels, which involves a lot of red tape and efforts to sidestep this can be regarded as disrespect for legal and governmental institutions.
answer
False
question
Many outsiders consider the Chinese system of guanxi to be like nepotism where decisions are made based on family ties instead of an objective assessment of ability.
answer
True
question
If the length of stay in another culture is to be in the range of 2 to 12 months, the experiential approach to training is advisable.
answer
False
question
Saudis attach little importance to status and rank with the bypassing of legal channels and red tape a common occurrence.
answer
False
question
Which of the following is not one of the potential results for the international project manager?
answer
all fo these are potential results
question
The major issues dealing with international project management include all of the following except:
answer
foreign currency exchange rates
question
Concern about the local restrictions on toxic waste is classified as which of the following environmental factor?
answer
Legal/Political
question
As a response to the events of September 11, 2001 the moving of personnel, materials, and equipment across international borders has created border congestion with increased costs and time. This is an example of which of the following environmental factors?
answer
Security
question
An information systems specialist reported that his performance on a project in Northern Sweden declined due to sleep deprivation during the summer months in which there was 20 hours of daylight each day. This is an example of which of the following environmental factors?
answer
Geographic
question
Inflation rates, import quotas and tariffs, and education level of workforce are examples of which of the following environmental factors?
answer
Economic
question
Needs for a project could include telecommunications, transportation, power, and availability of technically skilled talent. This is an example of which of the following environmental factors?
answer
Infrastructure
question
Communications difficulties because of different languages, social standards, and religious views are examples of which of the following environmental factors?
answer
Cultural
question
Culture is a concept that encompasses all of the following except
answer
economic level
question
The stages of culture shock include all of the following except
answer
Repatriation
question
When you recover from your sense of psychological disorientation and begin to function and communicate, you are in which of the following stages of culture shock?
answer
Adaptation
question
When you begin to lose confidence in your abilities to communicate and work effectively in the different culture, you are in which of the following stages of culture shock?