MGT 461 Exam 2 – Flashcards

Unlock all answers in this set

Unlock answers
question
"Unknown unknowns" is a term used to describe events which occur that are totally unexpecteD) All of the following accurately describe an implication associated with unknown unknowns EXCEPT:
answer
They are usually discovered during risk identification
question
There is often terrific pressure to complete a project as quickly as possible. To confront this pressure, a project manager should quickly promise to meet the deadlines requested by the sponsor and then assemble a team to create the corresponding schedule.
answer
FALSE
question
Since activities represent work that needs to be performed, it doesn't matter how the verb-noun is listed.
answer
FALSE
question
Faced with significant schedule challenges, the project manager has several responsibilities. All of the following are among the project manager's responsibilities EXCEPT:
answer
willingly accept end dates dictated by customers or sponsors
question
While the lowest level of decomposition in a Work Breakdown Structure is the work package, work packages can still be decomposed further into project activities.
answer
TRUE
question
For activities to be useful as schedule building blocks, they should have what characteristic(s)?
answer
All of these
question
The critical path is the sequence of activities that form the shortest path through the project network and determine the duration of the project.
answer
FALSE
question
Estimates of the likely amount a project will cost should always include an indication of accuracy.
answer
TRUE
question
The length of time to perform an activity is often dependent upon who will do that work.
answer
TRUE
question
Milestones are important points in a project schedule that can serve as check points for project managers and sponsors. All of the following reasons might justify the decision to establish a milestone EXCEPT:
answer
updating status reports
question
Estimating the number of work periods that will be needed to complete individual schedule activities characterizes which of the following time management processes?
answer
Estimate activity duration
question
A successor activity follows a predecessor activity based on their logical relationship.
answer
TRUE
question
The process of estimating the types and quantities of resources required to perform each scheduled activity is called a "project staffing analysis."
answer
FALSE
question
The staffing management plan addresses all of the following except:
answer
how to create project organization charts
question
A milestone is a typical measuring point used when establishing cost control. Which of the following accurately describes the use of cost control milestones?
answer
all of these
question
When estimating resource needs, project teams should consider all the following EXCEPT:
answer
scoring models
question
When determining resource availability, project managers need only consider full-time, internal resources.
answer
FALSE
question
When identifying people to work on the project, it is helpful to consider their professional disciplines, skill levels and their physical location.
answer
TRUE
question
Project managers often confront the challenge of reducing excessive time commitments and overloads among project resources. All of the following methods represent a potentially viable strategy to reduce work overloads EXCEPT:
answer
Require all project resources to work overtime
question
In order to avoid project delays, project managers confronted with resource overloads will naturally seek to exploit the slack associated with non-critical activities.
answer
TRUE
question
Resource leveling is a network scheduling technique that seeks to assign nearly equivalent work units to each member of the project team.
answer
FALSE
question
When resource overloads are extreme, project managers may need to consider the acquisition of additional resources, reductions in scope or extensions to the project schedule.
answer
TRUE
question
The critical chain method is a schedule network analysis technique that modifies the project schedule to account for limited resources.
answer
TRUE
question
There are many causes of variation in project costs. Which of the following accurately describes the nature of this variation?
answer
Variation occurs in all work processes and the novelty associated with most projects creates many opportunities for variation.
question
The document that establishes the activities and criteria for planning, structuring and controlling the project costs is the project financial plan.
answer
FALSE
question
Recurring costs tend to occur during project planning and closing while nonrecurring costs tend to occur during project execution.
answer
FALSE
question
Project managers are encouraged to avoid overly conservative cost estimates because the resulting estimate may be too high to approve.
answer
TRUE
question
The cost management plan establishes the format and criteria for planning and controlling the project costs.
answer
TRUE
question
Fixed costs remain constant over time, whereas variable costs may change directly as a function of time.
answer
FALSE
question
A project manager needs to ensure that the cumulative amount of cash coming into the project either from internal budgeting or from customer payments meets or exceeds the demands for paying cash out.
answer
TRUE
question
Except in rare circumstances, project teams should not attempt to decompose work packages into project activities because work packages provide sufficient detail to develop a project schedule.
answer
False
question
All of the following items describe an aspect of life cycle costing EXCEPT:
answer
Life cycle cost only includes the project cost from initiating through closing
question
Cost estimating is linked very closely with scope, schedule and resource planning.
answer
True
question
If a project manager delays the start of an activity on the critical path, than the expected completion date of the project will occur at a later date than originally planned.
answer
True
question
While a "RACI"chart may be very useful for assigning activities to core team members and project managers, the sheer number of subject matter experts on many projects renders the RACI chart impractical for large projects.
answer
False
question
Consider the programmers resource histogram presented in Figure 8-3. How many programmers are required during the fifth week of this project?
answer
7 programmers
question
Activity based costing allocates indirect costs based on different types of cost drivers. Which of the following cost drivers serve as a basis of allocation when activity based costing is used?
answer
number of units produced
question
One approach to identify which activities contribute to work overload for a particular resource is to compare the resource histogram to the Gantt chart.
answer
True
question
Typically, expedited costs are preferred over regular costs.
answer
False
question
The first process in developing a project schedule is to identify all the resources available to work on the project.
answer
False
question
The sequencing of activities is often based upon dependencies between the activities. The dependencies that should guide activity sequencing can be either
answer
Mandatory or discretionary
question
Even when a project team does not identify individual activities, it will still need to determine how many resources are needed to complete the project
answer
True
question
When recruiting resources to support a project, it is always best to bring team members and experts on board as soon as possible.
answer
True
question
On small projects, the cost management plan may simply address the accuracy of estimating, the source of funding and cost reporting procedures.
answer
True
question
In order for activities to be useful as schedule building blocks, they should have tangible output that can be verified.
answer
True
question
Creating a realistic schedule is often an iterative process because several factors can limit how fast a project can be completed. All of the following factors can limit how fast a project can be scheduled and completed EXCEPT
answer
quality control
question
The first draft of the project schedule can be drafted once the WBS has been constructed.
answer
True
question
Consider the time-phased budget presented in Figure 9-1. What is the cumulative project budget through the end of April?
answer
$46,000
question
Monte Carlo Analysis is a technique that computes activity durations based on three time estimates: one optimistic, one pessimistic and one most likely.
answer
False
question
One precondition that must be met for a project kick-off meeting is that the project manager needs to set clear directions during the planning phase and does not need to collaborate with the sponsor before doing so.
answer
FALSE
question
Risk is often considered in terms of impact to project success. Which of the following is a valid measure of project success?
answer
all of these
question
It is impossible to remove all sources of risk on a project.
answer
TRUE
question
All of the following are benefits that can be attributed to the effective use of a risk management plan EXCEPT:
answer
It enables the project manager to identify and eliminate all risks
question
The risk management plan is the document that describes how project risk management will be structured and performed on a project.
answer
TRUE
question
All of the following items are valid reasons to conduct a project kick-off meeting EXCEPT:
answer
to emphasize that all decisions will be made exclusively by the project manager
question
A risk is anything that may impact the project team's ability to achieve the general project success measures and the specific project stakeholder priorities.
answer
TRUE
question
Which of the following describes the effective use of a risk register?
answer
Items such as the probability of occurrence and impact are typically added to the risk register subsequent to risk identification.
question
Project teams can often identify risks by conducting any of several types of reviews. Which of the following illustrates a valuable type of risk review?
answer
review the communication plan to determine where poor communications could cause a problem
question
The risk register is a living document and new risks can be added as they are identified.
answer
TRUE
question
The formality of a kick-off meeting can vary considerably depending on the size and type of project.
answer
TRUE
question
All of the following criteria can be used to categorize project risks EXCEPT:
answer
whether the risk is a known known
question
All of the following methods have proven to be useful techniques to help project teams identify the risks that might impact the project EXCEPT:
answer
deriving lessons learned
question
Generally, once risks have been identified and analyzed, the project team decides how to handle each risk.
answer
TRUE
question
All of the following are among the classic risk response strategies EXCEPT:
answer
share a threat
question
When an overall plan becomes or appears impractical, the key stakeholders often will determine their priorities and tradeoffs prior to proceeding.
answer
TRUE
question
In some cases, project teams will elect to reduce a threat rather than eliminate it because the effort to completely eliminate a threat is unjustified.
answer
TRUE
question
Sometimes the risks posed by a project are so great that an appropriate risk response is to not perform the project at all.
answer
TRUE
question
Which of the following describes the appropriate use of a cause and effect diagram to support project risk analysis?
answer
It is often easier to alter the effect by changing the underlying cause.
question
Project stakeholders will judge the quality of project work processes as well as project deliverables.
answer
TRUE
question
It is important that there is an atmosphere of trust and relationship building prior to kicking off the project amongst all parties involved.
answer
TRUE
question
All of the following reasons explain why it is better to design quality into processes than to find problems through inspections EXCEPT:
answer
The best inspectors should find every variation and defect
question
DMAIC is typically used as a method of implementing continuous improvement and can thus be practiced repeatedly within a single process to further improve process performance.
answer
TRUE
question
The decision process for developing relevant quality standards on a project includes all of the following activities EXCEPT:
answer
design work systems
question
The four core project quality concepts include which of the following?
answer
stakeholder satisfaction
question
The quality policy on a specific project should defer the quality policies of the parent organization when major customer needs and policies create a conflict
answer
FALSE
question
Which of the following documents describes how the project management team will implement the performing organization's quality policy?
answer
the quality management plan
question
The project manager is responsible for selecting appropriate quality standards for the project. Typically, these standards apply to all of the following EXCEPT:
answer
team selection criteria
question
Project quality tools such as a histogram, Pareto chart, and Failure Mode and Effect Analysis (FMEA) are generally used in support of which of the following DMAIC phases?
answer
Analyze
question
The quality management plan describes how the project management team will implement the performing organization's quality policy.
answer
TRUE
question
Which of the following activities illustrates a risk response strategy designed to mitigate a threat?
answer
train a team member to cover for a potentially unavailable key resource.
question
The International Organization for Standardization developed a quality management standard that relies upon several quality management areas including management, resources and realization.
answer
True
question
The primary questions project teams use in qualitative risk analysis are "What is the nature of this risk?" and "Who will be responsible for addressing it?"
answer
False
question
The cost per risk for risks discovered early in the project is often more than the cost per risk for risks discovered late because there is more opportunity for the risk to impact several dimensions of the project.
answer
False
question
All of the following activities are appropriate upon completion of risk response planning EXCEPT:
answer
The risk register should be baselined after planning is completed, and should not be updated once the project is in flight.
question
A risk management plan should define who has responsibility for causing each risk and hold the responsible party directly accountable for developing an appropriate solution.
answer
False
question
Project managers can identify risks by learning and understanding the cause and effect relationships that bear on risk events. All of the following approaches rely upon an understanding of cause and effect relationships to identify risks EXCEPT:
answer
list all in a risk register
question
Identifying risk involves a process of determining which risk might affect the project without having to having to document the nature or characteristics of the risk.
answer
False
question
On many small, simple projects the quality planning is performed concurrently with other planning and the quality plan is seamlessly incorporated into the project plan.
answer
True
question
All of the following describe the appropriate application of Perform Quantitative Risk Analysis in project management EXCEPT:
answer
Brainstorming techniques are used by the team and other stakeholders to identify as many project risks as possible.
question
After completing detailed planning for a project, it is often helpful for the project manager and team to apply a sanity test to the project plan. Which of the following accurately describes the application of a sanity test?
answer
It should include questions to ensure budgets, schedules and resource plans are reasonable and achievable.
question
All of the following actions play constructive roles in an organization when project managers are considering process improvements EXCEPT:
answer
Organizations focus exclusively on short term results.
question
Which of the following activities are typically included in a project kick-off meeting?
answer
The project manager outlines the project goals.
question
The process of deciding how to approach, plan and execute risk management activities for a project is known as Project Risk Absorption Methodology (PRAM).
answer
False
question
When the impact of an event is negative, it is considered a risk; when the impact is positive, the event is considered an opportunity.
answer
True
question
Risk response strategies such as acceptance and conducting further research apply to both threats and opportunities.
answer
True
question
The primary output of risk identification is the Risk Identification Matrix (RIM)
answer
False
question
The primary output of risk identification is the Risk Identification Matrix (RIM)
answer
False