Operations Management – Project Management – Flashcards

Unlock all answers in this set

Unlock answers
question
Gantt charts give a timeline for each of a? project's activities, but they do not adequately illustrate the interrelationships between the activities and the resources.
answer
True
question
The shortest of all paths through the network is the critical path.
answer
False - the critical path is the longest path
question
Slack is the amount of time an activity can be delayed without delaying the entire project.
answer
True
question
The phases of project management? are: A. ?planning, programming, and budgeting. B. different for manufacturing projects than for service projects. C. ?GANTT, CPM, and PERT. D. ?planning, scheduling, and controlling. E. ?planning, organizing,? staffing, leading, and controlling.
answer
D.
question
A code of ethics especially for project? managers: A. does not exist at this time. B. has been established by the Project Management Institute. C. has been formulated by the World Trade Organization. D. has been formulated by the Federal government. E. is? inappropriate, since everyone should use the same guidance on ethical issues.
answer
B.
question
WBS stands for which of the following project management? tools? A. work breakdown schedule B. work break schedule C. work breakdown structure D. work breakdown status E. work break status
answer
C.
question
The main difference between PERT and CPM is? that: A. PERT employs three time estimates for each activity. B. PERT ignores activity costs. C. CPM assumes activity durations can vary. D. PERT is more accurate than CPM. E. PERT assumes that activity durations are known.
answer
A.
question
Which of the following statements regarding CPM networks is? true? A. The late start of an activity is its late finish plus its duration. B. The early finish of an activity is the latest early start of all preceding activities. C. If a specific project has multiple critical? paths, all of them will have the same duration. D. There can be multiple critical paths on the same? project, all with different durations. E. None of the above are true.
answer
C.
question
Every network has at least one critical path.
answer
True
question
A project organization that becomes permanent is often referred to as? a: A. fixed project organization. B. matrix organization. C. standard organization. D. normal organization. E. permanent project organization.
answer
B.
question
Project crashing
answer
You use the time taken for the project reducing the budget time taken and costs incurred
question
Disadvantages of a Gantt chart
answer
- still difficult to see which tasks are done concurrently/sequentially when there are many tasks to he completed - you can't see how to reallocate resources if one task is taking longer than expected, how to reduce time to complete a task, or what would happen if you have lower staff than expected
question
Advantages of a Gantt chart
answer
Tells you which tasks can be completed simultaneously and how long each task takes
question
Who created CPM?
answer
DuPont created CPM for chemical plants (1957)
question
Who created PERT?
answer
Good, Allen, and Hamilton with the U.S. Navy for Polaris missile (1958)
question
Difference between CPM and PERT
answer
They use a different estimate of activity times. CPM is deterministic (20 days). PERT gives 3 potential outcomes: optimistic (if everything goes right, 16 days), most likely (maybe 21 days), pessimistic (Murphy's law, 30 days)