Operations Management – Project Management – Flashcards
16 test answers
Unlock all answers in this set
Unlock answers 16question
A code of ethics especially for project? managers: A. does not exist at this time. B. has been established by the Project Management Institute. C. has been formulated by the World Trade Organization. D. has been formulated by the Federal government. E. is? inappropriate, since everyone should use the same guidance on ethical issues.
answer
B.
Unlock the answer
question
WBS stands for which of the following project management? tools? A. work breakdown schedule B. work break schedule C. work breakdown structure D. work breakdown status E. work break status
answer
C.
Unlock the answer
question
The main difference between PERT and CPM is? that: A. PERT employs three time estimates for each activity. B. PERT ignores activity costs. C. CPM assumes activity durations can vary. D. PERT is more accurate than CPM. E. PERT assumes that activity durations are known.
answer
A.
Unlock the answer
question
Which of the following statements regarding CPM networks is? true? A. The late start of an activity is its late finish plus its duration. B. The early finish of an activity is the latest early start of all preceding activities. C. If a specific project has multiple critical? paths, all of them will have the same duration. D. There can be multiple critical paths on the same? project, all with different durations. E. None of the above are true.
answer
C.
Unlock the answer
question
Every network has at least one critical path.
answer
True
Unlock the answer
question
A project organization that becomes permanent is often referred to as? a: A. fixed project organization. B. matrix organization. C. standard organization. D. normal organization. E. permanent project organization.
answer
B.
Unlock the answer
question
Project crashing
answer
You use the time taken for the project reducing the budget time taken and costs incurred
Unlock the answer
question
Disadvantages of a Gantt chart
answer
- still difficult to see which tasks are done concurrently/sequentially when there are many tasks to he completed - you can't see how to reallocate resources if one task is taking longer than expected, how to reduce time to complete a task, or what would happen if you have lower staff than expected
Unlock the answer
question
Advantages of a Gantt chart
answer
Tells you which tasks can be completed simultaneously and how long each task takes
Unlock the answer
question
Who created CPM?
answer
DuPont created CPM for chemical plants (1957)
Unlock the answer
question
Who created PERT?
answer
Good, Allen, and Hamilton with the U.S. Navy for Polaris missile (1958)
Unlock the answer
question
Difference between CPM and PERT
answer
They use a different estimate of activity times. CPM is deterministic (20 days). PERT gives 3 potential outcomes: optimistic (if everything goes right, 16 days), most likely (maybe 21 days), pessimistic (Murphy's law, 30 days)
Unlock the answer