question
Project managers must take adequate time to identify, understand, and manage relationships with all project stakeholders.
answer
true
question
The Adaptive Software Development (ASD) life cycle model assumes that software development follows an adaptive approach because the requirements cannot be clearly expressed early in the life cycle.
answer
true
question
Corrective actions reduce the probability of negative consequences associated with project risks, while preventive actions should result in improvements in project performance.
answer
false
question
The DMAIC (Define, Measure, Analyze, Improve, and Control) methodology of the Six Sigma projects, is used to improve an existing business process.
answer
true
question
A Gantt chart is the same as a project management plan.
answer
false
question
Decisions and actions taken in one knowledge area at a certain time rarely affect other knowledge areas.
answer
false
question
Systems analysis addresses the business, technological, and organizational issues associated with creating, maintaining, and modifying a system.
answer
false
question
Project procurement management primarily involves identifying stakeholder needs while managing their engagement throughout the life of the project.
answer
false
question
In order to be realistic, a project manager should always set discrete goals instead of a range of objectives.
answer
false
question
Opponents of a project do not belong to the category of stakeholders.
answer
false
question
When you separate business and organizational issues from project management planning, you do a better job of ensuring project success.
answer
false
question
Maturity models, statistical methods, and test plans are examples of tools used in quality management.
answer
true
question
Project managers must have cooperation from people in other parts of the organization.
answer
true
question
Monitoring and controlling processes overlap all of the other project management process groups.
answer
true
question
As projects progress, the organization must reevaluate the need, funding, and will for each project to determine if the project should be continued, redefined, or terminated.
answer
true
question
Projects that arise as a result of problems and directives must be resolved quickly to avoid hurting an organization's business.
answer
true
question
The nature of hardware development projects is more diverse than software-oriented projects.
answer
false
question
Most colleges and universities have very strong functional organizations.
answer
true
question
Information systems can help an organization support a strategy of being a low-cost producer.
answer
true
question
It is mandatory for project managers working on large information technology projects to be experts in the field of information technology.
answer
false
question
An organization should consider only projects with a negative NPV if financial value is a key criterion for project selection.
answer
false
question
In project integration management, directing and managing project execution involves carrying out the project management plan by performing the activities included in it.
answer
true
question
An organizational culture with strong unit integration makes the project manager's job more difficult
answer
false
question
Earned value management is a tool primarily used in human resource management.
answer
false (Project budgets, net present value, return on investment, payback analysis, and earned value management are tools used in cost management.)
question
Until the 1980s, project management primarily focused on providing schedule and resource data to top management in the military, computer, and construction industries.
answer
true
question
It is much more expensive to make major changes to a project during the earlier phases.
answer
false
question
Good project managers assume that their definition of success is the same as the sponsors.
answer
false
question
Leadership style has no impact on the success of virtual teams.
answer
false
question
An annual discount factor is a multiplier for each year based on the discount rate and year.
answer
true
question
The pre-initiation phase of a project using the Scrum method does not involve project charters, stakeholder management strategy, and kick-off meetings.
answer
false
question
Agile methods comprise of 45 subprocesses which are organized into eight process groups.
answer
false ( All agile methods include an iterative workflow and incremental delivery of software in short iterations.)
question
Some organizations initiate projects using a contract in place of a project charter.
answer
true
question
The number of interfaces in a single project is limited, and does not depend on the number of people involved in the project.
answer
false
question
Effective program managers recognize that managing a project is much more complex than managing a program.
answer
false
question
Organizational process asset updates are an important output of the closing process of a project.
answer
true
question
Payback period is the amount of time it will take to recoup, in the form of net cash inflows, the total dollars invested in a project.
answer
true
question
The burndown chart is a Scrum created artifact that provides a list of features prioritized by business value.
answer
false
question
Project managers in matrix organizations have staff from various functional areas working on their projects.
answer
true
question
One of the main reasons why project management is challenging is because of the factor of uncertainty
answer
true
question
Project managers should lead projects in isolation in order to truly serve the needs of the organization.
answer
false
question
The only responsibility of a project manager is to meet the specific scope, time, and cost goals of a project.
answer
false
question
The same organization can have different subcultures
answer
true
question
Initiating and closing tasks are usually the longest and require the most amount of resources and time.
answer
false
question
The kick-off meeting is always held before the business case and project charter are completed.
answer
false
question
Identifying the project sponsor is a pre-initiation task.
answer
true
question
A SWOT analysis, being a linear process, cannot be performed using the nonlinear mind mapping technique.
answer
false
question
Every project should have a well-defined objective.
answer
true
question
The two main items for monitoring and controlling in the Scrum framework are the dailyScrum and the sprint retrospectives.
answer
true
question
Resources in a project should be used effectively because they are limited.
answer
true
question
Project human resource management is concerned with making effective use of the people involved with a project.
answer
true
question
Initiating processes are not required to end a project.
answer
false
question
The introduction of new software makes basic tools, such as Gantt charts and network diagrams, inexpensive and easy to create
answer
true
question
The WBS provides a basis for creating the project schedule and performing earned value management for measuring and forecasting project performance.
answer
true
question
Which of the following is true of a matrix organizational structure?
answer
In a strong matrix organizational structure, the project manager controls the project budget and has moderate to high authority.
question
The project stakeholder management knowledge area maps to the _____ process group by identifying stakeholders.
answer
initiating
question
In the _____ stage of selecting information technology projects, organizations select information technology projects.
answer
resource allocation
question
A project's internal rate of return can be determined by finding what discount rate results in an NPV of ____ for the project.
answer
zero
question
____ analysis is a method of calculating the expected net monetary gain or loss from a project by discounting all expected future cash inflows and outflows to the present point in time.
answer
Net present value
question
A _____ is a tool used in quality management.
answer
checklist
question
In the development phase of the project life cycle:
answer
the project team creates more detailed project plans, a more accurate cost estimate, and a more thorough WBS.
question
The _____ is the minimum acceptable rate of return on an investment.
answer
required rate of return
question
The _____ frame of an organization focuses on providing harmony between the needs of the organization and the needs of people.
answer
human resources
question
Grey's Infotech sells customized hardware and software solutions for businesses. The salespeople for Grey's have a strict dress code when meeting clients. They are required to wear dark business suits, in order to convey the company's dedication to quality. The meaning conveyed to the clients' through the salespeople's clothing is part of the _____ frame of the organization.
answer
symbolic
question
The project integration management knowledge area maps to the _____ process group through the activities of developing project charters.
answer
initiating
question
Joe is a project manager in an IT company and has over the years, gained substantial knowledge in his area of work. However, while managing his team, he often loses his temper. In addition, he fails to be an active listener when his team members approach him with work related challenges. In which of the following areas does Joe need to develop his skills in?
answer
Human relations skills
question
Fast tracking is an example of a tool used in _____ management.
answer
time
question
Which of the following project parameters would be compatible with the use of the agile approach?
answer
Projects that have more flexible scheduling
question
The _____ stage of information technology planning outlines business processes that are central to achieving strategic goals and helps determine which ones could most benefit from information technology.
answer
business area analysis
question
The project time management knowledge area maps to the _____ process group through the activity of schedule control.
answer
monitoring and controlling
question
Projects must operate in a broad organizational environment, and project managers need to consider projects within the greater organizational context. _____ describes this holistic view of carrying out projects within the context of the organization.
answer
Systems thinking
question
The outputs of the _____ process include change request status updates, project management plan updates, and project document updates.
answer
monitoring and controlling
question
Which of the following refers to a set of principles that guides decision making based on personal values of what is considered right and wrong?
answer
ethics
question
The improvement of the product and process in the Scrum method is discussed at the _____.
answer
sprint reflection meeting
question
The _____ model of a systems development life cycle assumes that requirements will remain stable after they are defined.
answer
waterfall life cycle
question
The first step in determining the NPV is to _____.
answer
...
question
Examples of _____ processes include acquiring and developing the project team, performing quality assurance, distributing information, managing stakeholder expectations, and conducting procurements.
answer
executing
question
Which of the following tools can best help in efficient communication management?
answer
Kick-off meetings
question
In organizational culture, control refers to _____.
answer
the degree to which rules, policies, and direct supervision are used to oversee employee behavior
question
In the _____ model, developers use a model to generate functional requirements and physical design specifications simultaneously.
answer
prototyping life cycle
question
management?
answer
Project management addresses specific, short-term goals whereas portfolio management focuses on long-term goals.
question
Which of the following types of tools is usually recommended for small projects and single users?
answer
Low-end
question
Organizational process assets update is the output of the closing process of _____.
answer
project integration management
question
The role of a _____ is to provide direction and funding for a project.
answer
project sponsor
question
Which of the following is a difference between projects and operations?
answer
Projects are temporary endeavors whereas an organization's operations are ongoing in nature.
question
The project schedule information section of the project management plan includes ____.
answer
an elaborate timetable
question
____ is a planning process that is within the Project Scope Management knowledge area.
answer
Creation of a WBS
question
Which of the following best describes outsourcing?
answer
An organization's acquisition of goods and services from an outside source
question
_____ processes include defining and authorizing a project or project phase.
answer
Initiating