In the basic EOQ model, if lead time increases from five to 10 days, the EOQ will: – Q/A (Question and Answer)
Question
In the basic EOQ model, if lead time increases from five to 10 days, the EOQ will: – Q/A (Question and Answer)
Test Answer
Answer:
remain the same; The EOQ is independent of lead time.
Recource ch.13 OP MGMT