Chpt 4 – Project Integration Management – Flashcards

question
Develop Project Charter process
answer
The process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
question
Key benefit of the Develop Project Charter process
answer
A well-defined project start and project boundaries, creation of a formal record of the project, and a direct way for senior management to formally accept and commit to the project.
question
Develop Project Management Plan process
answer
Develop Project Management Plan is the process of defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive project management plan.
question
Key benefit of the Develop Project Management Plan process
answer
A central document that defines the basis of all project work.
question
Direct and Manage Project Work process
answer
The process of leading and performing the work defined in the project management plan and implementing approved changes to achieve the project's objectives.
question
Key benefit of the Direct and Manage Project Work process
answer
It provides overall management of the project work.
question
Monitor and Control Project Work process
answer
The process of tracking, reviewing, and reporting the progress to meet the performance objectives defined in the project management plan.
question
Key benefit of the Monitor and Control Project Work process
answer
It allows stakeholders to understand the current state of the project, the steps taken, and budget, schedule, and scope forecasts.
question
Perform Integrated Change Control process
answer
The process of reviewing all change requests; approving changes and managing changes to deliverables, organizational process assets, project documents, and the project management plan; and communicating their disposition. It reviews all requests for changes or modifications to project documents, deliverables, baselines, or the project management plan and approves or rejects the changes.
question
Key benefit of the Perform Integrated Change Control process
answer
It allows for documented changes within the project to be considered in an integrated fashion while reducing project risk, which often arises from changes made without consideration to the overall project objectives or plans.
question
Close Project or Phase process
answer
The process of finalizing all activities across all of the Project Management Process Groups to formally complete the project or phase.
question
Key benefit of the Close Project or Phase process
answer
It provides lessons learned, the formal ending of project work, and the release of organization resources to pursue new endeavors.
question
Two key things about a Project Charter
answer
It formally initiates the project and it gives the PM authority to spend money and commit resources
question
When is a PM assigned
answer
As early in the project as feasible, preferably while the project charter is being is being developed, and always before planning
question
Who authors the project charter?
answer
The sponsoring entity
question
Inputs to Develop Project Charter process
answer
Project Statement of Work Business Case Agreements EEF OPA
question
What is a Project Statement of Work?
answer
Narrative description of products, services, or results to be delivered by a project.
question
Who provides the Statement of Work?
answer
For internal projects, the sponsor. For external projects, the customer.
question
What is a Business Case?
answer
Describes the necessary information from a business standpoint to determine whether or not the project is worth the required investment. Includes business need and the cost-benefit analysis.
question
Who usually conducts the analysis for the business case?
answer
The business analyst using stakeholder input
question
What are agreements?
answer
Typically for projects with an external customer. Used to define initial intentions for a project. Agreements may take the form of contracts, memorandums of understanding (MOUs), service level agreements (SLA), letter of agreements, letters of intent, verbal agreements, email, or other written agreements.
question
What may be included in a project charter?
answer
Project Purpose Project Objectives High-level requirements Assumptions and Constraints High-level project description and boundaries High-Level risks Milestone schedule Summary budget Stakeholder list Project approval requirements Assigned PM, responsibility, and authority level Name and authority of the sponsor
question
Who issues the project charter?
answer
The project sponsor
question
What does the Project Management Plan do?
answer
Defines how the project is executed, monitored and controlled, and closed.
question
How is the Project Management Plan developed?
answer
Through a series of integrated processes extending through project closure. It is progressively elaborated by updates and controlled and approved through the Perform Integrated Change Control process.
question
Inputs to the Develop Project Management Plan process
answer
Project Charter Outputs from other processes (other plans) EEF OPA
question
Name some Enterprise Environmental Factors
answer
Government standards PMBOK PMIS Org structure, culture, practices Infrastructure Personnel admin Stakeholder risk tolerance
question
Name some Organizational Process Assets
answer
Standardized guideline, instructions, or performance criteria Plan Template Procedures Historical Information and lessons learned knowledge base Files from previous projects
question
Tools and Techniques for Develop Project Charter
answer
Expert Judgment Facilitation Techniques
question
Tools and Techniques for Develop Project Management Plan
answer
Expert Judgment Facilitation Techniques
question
Output of Develop Project Management Plan
answer
The Project Management Plan
question
What is included in a Project Management Plan?
answer
Scope baseline Schedule baseline Cost baseline Subsidiary plans Type of life cycle selected
question
When may the Project Management Plan be changed
answer
Once the project management plan is baselined, it may only be changed when a change request is generated and approved through the Perform Integrated Change Control process.
question
Inputs to Direct and Manage Project Work process
answer
Project Management Plan Approved change requests EEF OPA
question
Tools and Techniques for Direct and Manage Project Work process
answer
Expert Judgment PMIS Meetings
question
Outputs of Direct and Manage Project Work process
answer
Deliverables Work performance data Change requests Project management plan updates Project documents updates
question
Name some Direct and Manage Project Work activities
answer
Perform activities to accomplish project objectives Create project deliverables to meet the planned project work Provide, train, and manage team members Obtain, manage, and use resources Implement the planned methods and standards Establish and manage project communication channels, external and internal Generate work performance data Issue CR and implement approved changes Manage risks and implement risk response Manage sellers and suppliers Manage stakeholders Collect and document lessons learned and implement approved process improvement activities
question
What are three types of project change requests?
answer
Corrective Action Preventive Action Defect Repair Updates
question
Define Corrective Action
answer
An intentional activity that realigns the performance of the project work with the project management plan.
question
Define Preventive Action
answer
An intentional activity that ensures the future performance of the project work is aligned with the project management plan.
question
Define Defect Repair
answer
An intentional activity to modify a nonconforming product or product component.
question
Define Updates
answer
Changes to formally controlled project documents, plans, etc., to reflect modified or additional ideas or content.
question
Name three common types of meetings
answer
Information exchange Brainstorming, open evaluation or design Decision making
question
Meeting best practices
answer
Don't mix meeting types Well-defined agenda, purpose, objective, time frame Meeting minutes and action items Each attendee should have a defined role to ensure appropriate participation
question
Define "Deliverable"
answer
Any unique and verifiable product, result or capability to perform a service that is required to be produced to complete a process, phase, or project.
question
Define "Work Performance Data"
answer
The raw observations and measurements identified during activities being performed to carry out the project work.
question
Define "Change Request"
answer
A formal proposal to modify any document, deliverable, or baseline.
question
Name some things that might be modified by an approved change request
answer
Project policies or procedures Project scope Project cost or budget Project schedule Project quality
question
Name some examples of Project Documents
answer
Requirements document Project logs (issues, assumptions, etc.) Risk register Stakeholder register
question
Inputs of Monitor and Control Project Work process
answer
Project management plan Schedule forecasts Cost forecasts Validated changes Work performance information EEF OPA
question
Tools and Techniques for Monitor and Control Project Work process
answer
Expert judgment Analytical tactics PMIS Meetings
question
Outputs of Monitor and Control Project Work process
answer
Change requests Work performance reports Project management plan updates Project documents updates
question
What is work performance information?
answer
The performance data collected from various controlling processes, analyzed in context, and integrated based on relationships across areas.
question
What are work performance reports?
answer
The physical and electronic representation of work performance information compiled into project documents, intended to generate decisions, actions, or awareness.
question
Inputs to Perform Integrated Change Control process
answer
Project management plan Work performance reports Change requests EEF OPA
question
Tools and Techniques for Perform Integrated Change Control process
answer
Expert judgment Meetings Change control tools
question
Outputs from Perform Integrated Change Control process
answer
Approved change requests Change log Project management plan updates Project document updates
question
Who is ultimately responsible for change control?
answer
The Project Manager
question
When is Perform Integrated Change Control conducted?
answer
From project inception through completion
question
Who may request a change?
answer
Any stakeholder involved with the project
question
Who approves change requests?
answer
A responsible individual, either the project sponsor or project manager
question
Where is the responsible individual identified?
answer
Project management plan or the by organizational procedures
question
What is a CCB?
answer
Change Control Board. A formally chartered group responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project. They also record and communicate these changes.
question
What are factors in choosing the level of change control?
answer
Application area Complexity of project Contract requirements Context Environment
question
Configuration control vs change control
answer
Configuration control is focused on the specification of both the deliverables and the processes (the product). Change control is focused on identifying, documenting and approving or rejecting changes to the project documents, deliverables, or baselines. •Configuration Management deals with changes in product specifications - An example of Configuration Management can be an extra feature added to the product •Change Management manages the changes in project baseline or process. - An example of Change Management system can be a change in budget, schedule, etc.
question
Name some configuration management activities
answer
Configuration identification Configuration status accounting Configuration verification and audit
question
What is configuration identification?
answer
Identification and selection of a configuration item to provide a basis for which the product configuration is defined and verified, products and documents are labeled, changes are managed, and accountability is maintain.
question
What is configuration status accounting?
answer
Information is recorded and reported as necessary. This info includes listing of approved configuration identification, status of proposed configuration changes, and implementation status of approved changes
question
What is configuration verification and audit?
answer
Ensures the composition of the project's configuration items is correct and that corresponding changes are registered, assess, approved, tracked, and correctly implemented. Functional requirements in the configuration documentation have been met
question
What happens when a CR is approved.
answer
The approved change request will be implemented through the Direct and Manage Project Work process.
question
What is the change log?
answer
Used to document change requests. Includes their impact to the project in terms of time, cost, and risk. And whether they are approved or not
question
Input to Close Project or Phase process
answer
Project management plan Accepted deliverables OPA
question
Tools and Techniques for Close Project or Phase process
answer
Expert judgment Analytical techniques Meetings
question
Outputs from Close Project or Phase process
answer
Final product, services, or result transition OPA
question
Closure Activities
answer
Actions and activities necessary to satisfy completion or exit criteria for the phase or project Actions and activities necessary to transfer the project's products, services, or results to the next phase or to production and/or operations Activities needed to collect project or phase records, audit project success or failure, gather lessons learned and archive project information for future use by the organization.
question
Name some examples of Accepted Deliverables
answer
Approved product specifications Delivery receipts Work performance documents For phased or cancelled projects these deliverables may be partial or interim
question
Describe "Final Product, Service, or Result Transition"
answer
Transition of the final product, service, or result that the project was authorized to product (for phase closure it is the intermediate not final)
question
Name some OPAs for Close Project or Phase process
answer
Project files - Documents resulting from the projects activities Project or phase closure documents - Formal doc to indicate completion and transfer. Includes reviewing customer acceptance doc or contract before finalizing closure. For terminated projects, this doc indicates why and formalizes transfer of finished and unfinished deliverables of cancelled project to others Historical information - This info and lessons learned are transferred to the knowledge db for use in future projects
1 of

Unlock all answers in this set

Unlock answers
question
Develop Project Charter process
answer
The process of developing a document that formally authorizes the existence of a project and provides the project manager with the authority to apply organizational resources to project activities.
question
Key benefit of the Develop Project Charter process
answer
A well-defined project start and project boundaries, creation of a formal record of the project, and a direct way for senior management to formally accept and commit to the project.
question
Develop Project Management Plan process
answer
Develop Project Management Plan is the process of defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive project management plan.
question
Key benefit of the Develop Project Management Plan process
answer
A central document that defines the basis of all project work.
question
Direct and Manage Project Work process
answer
The process of leading and performing the work defined in the project management plan and implementing approved changes to achieve the project's objectives.
question
Key benefit of the Direct and Manage Project Work process
answer
It provides overall management of the project work.
question
Monitor and Control Project Work process
answer
The process of tracking, reviewing, and reporting the progress to meet the performance objectives defined in the project management plan.
question
Key benefit of the Monitor and Control Project Work process
answer
It allows stakeholders to understand the current state of the project, the steps taken, and budget, schedule, and scope forecasts.
question
Perform Integrated Change Control process
answer
The process of reviewing all change requests; approving changes and managing changes to deliverables, organizational process assets, project documents, and the project management plan; and communicating their disposition. It reviews all requests for changes or modifications to project documents, deliverables, baselines, or the project management plan and approves or rejects the changes.
question
Key benefit of the Perform Integrated Change Control process
answer
It allows for documented changes within the project to be considered in an integrated fashion while reducing project risk, which often arises from changes made without consideration to the overall project objectives or plans.
question
Close Project or Phase process
answer
The process of finalizing all activities across all of the Project Management Process Groups to formally complete the project or phase.
question
Key benefit of the Close Project or Phase process
answer
It provides lessons learned, the formal ending of project work, and the release of organization resources to pursue new endeavors.
question
Two key things about a Project Charter
answer
It formally initiates the project and it gives the PM authority to spend money and commit resources
question
When is a PM assigned
answer
As early in the project as feasible, preferably while the project charter is being is being developed, and always before planning
question
Who authors the project charter?
answer
The sponsoring entity
question
Inputs to Develop Project Charter process
answer
Project Statement of Work Business Case Agreements EEF OPA
question
What is a Project Statement of Work?
answer
Narrative description of products, services, or results to be delivered by a project.
question
Who provides the Statement of Work?
answer
For internal projects, the sponsor. For external projects, the customer.
question
What is a Business Case?
answer
Describes the necessary information from a business standpoint to determine whether or not the project is worth the required investment. Includes business need and the cost-benefit analysis.
question
Who usually conducts the analysis for the business case?
answer
The business analyst using stakeholder input
question
What are agreements?
answer
Typically for projects with an external customer. Used to define initial intentions for a project. Agreements may take the form of contracts, memorandums of understanding (MOUs), service level agreements (SLA), letter of agreements, letters of intent, verbal agreements, email, or other written agreements.
question
What may be included in a project charter?
answer
Project Purpose Project Objectives High-level requirements Assumptions and Constraints High-level project description and boundaries High-Level risks Milestone schedule Summary budget Stakeholder list Project approval requirements Assigned PM, responsibility, and authority level Name and authority of the sponsor
question
Who issues the project charter?
answer
The project sponsor
question
What does the Project Management Plan do?
answer
Defines how the project is executed, monitored and controlled, and closed.
question
How is the Project Management Plan developed?
answer
Through a series of integrated processes extending through project closure. It is progressively elaborated by updates and controlled and approved through the Perform Integrated Change Control process.
question
Inputs to the Develop Project Management Plan process
answer
Project Charter Outputs from other processes (other plans) EEF OPA
question
Name some Enterprise Environmental Factors
answer
Government standards PMBOK PMIS Org structure, culture, practices Infrastructure Personnel admin Stakeholder risk tolerance
question
Name some Organizational Process Assets
answer
Standardized guideline, instructions, or performance criteria Plan Template Procedures Historical Information and lessons learned knowledge base Files from previous projects
question
Tools and Techniques for Develop Project Charter
answer
Expert Judgment Facilitation Techniques
question
Tools and Techniques for Develop Project Management Plan
answer
Expert Judgment Facilitation Techniques
question
Output of Develop Project Management Plan
answer
The Project Management Plan
question
What is included in a Project Management Plan?
answer
Scope baseline Schedule baseline Cost baseline Subsidiary plans Type of life cycle selected
question
When may the Project Management Plan be changed
answer
Once the project management plan is baselined, it may only be changed when a change request is generated and approved through the Perform Integrated Change Control process.
question
Inputs to Direct and Manage Project Work process
answer
Project Management Plan Approved change requests EEF OPA
question
Tools and Techniques for Direct and Manage Project Work process
answer
Expert Judgment PMIS Meetings
question
Outputs of Direct and Manage Project Work process
answer
Deliverables Work performance data Change requests Project management plan updates Project documents updates
question
Name some Direct and Manage Project Work activities
answer
Perform activities to accomplish project objectives Create project deliverables to meet the planned project work Provide, train, and manage team members Obtain, manage, and use resources Implement the planned methods and standards Establish and manage project communication channels, external and internal Generate work performance data Issue CR and implement approved changes Manage risks and implement risk response Manage sellers and suppliers Manage stakeholders Collect and document lessons learned and implement approved process improvement activities
question
What are three types of project change requests?
answer
Corrective Action Preventive Action Defect Repair Updates
question
Define Corrective Action
answer
An intentional activity that realigns the performance of the project work with the project management plan.
question
Define Preventive Action
answer
An intentional activity that ensures the future performance of the project work is aligned with the project management plan.
question
Define Defect Repair
answer
An intentional activity to modify a nonconforming product or product component.
question
Define Updates
answer
Changes to formally controlled project documents, plans, etc., to reflect modified or additional ideas or content.
question
Name three common types of meetings
answer
Information exchange Brainstorming, open evaluation or design Decision making
question
Meeting best practices
answer
Don't mix meeting types Well-defined agenda, purpose, objective, time frame Meeting minutes and action items Each attendee should have a defined role to ensure appropriate participation
question
Define "Deliverable"
answer
Any unique and verifiable product, result or capability to perform a service that is required to be produced to complete a process, phase, or project.
question
Define "Work Performance Data"
answer
The raw observations and measurements identified during activities being performed to carry out the project work.
question
Define "Change Request"
answer
A formal proposal to modify any document, deliverable, or baseline.
question
Name some things that might be modified by an approved change request
answer
Project policies or procedures Project scope Project cost or budget Project schedule Project quality
question
Name some examples of Project Documents
answer
Requirements document Project logs (issues, assumptions, etc.) Risk register Stakeholder register
question
Inputs of Monitor and Control Project Work process
answer
Project management plan Schedule forecasts Cost forecasts Validated changes Work performance information EEF OPA
question
Tools and Techniques for Monitor and Control Project Work process
answer
Expert judgment Analytical tactics PMIS Meetings
question
Outputs of Monitor and Control Project Work process
answer
Change requests Work performance reports Project management plan updates Project documents updates
question
What is work performance information?
answer
The performance data collected from various controlling processes, analyzed in context, and integrated based on relationships across areas.
question
What are work performance reports?
answer
The physical and electronic representation of work performance information compiled into project documents, intended to generate decisions, actions, or awareness.
question
Inputs to Perform Integrated Change Control process
answer
Project management plan Work performance reports Change requests EEF OPA
question
Tools and Techniques for Perform Integrated Change Control process
answer
Expert judgment Meetings Change control tools
question
Outputs from Perform Integrated Change Control process
answer
Approved change requests Change log Project management plan updates Project document updates
question
Who is ultimately responsible for change control?
answer
The Project Manager
question
When is Perform Integrated Change Control conducted?
answer
From project inception through completion
question
Who may request a change?
answer
Any stakeholder involved with the project
question
Who approves change requests?
answer
A responsible individual, either the project sponsor or project manager
question
Where is the responsible individual identified?
answer
Project management plan or the by organizational procedures
question
What is a CCB?
answer
Change Control Board. A formally chartered group responsible for reviewing, evaluating, approving, delaying, or rejecting changes to the project. They also record and communicate these changes.
question
What are factors in choosing the level of change control?
answer
Application area Complexity of project Contract requirements Context Environment
question
Configuration control vs change control
answer
Configuration control is focused on the specification of both the deliverables and the processes (the product). Change control is focused on identifying, documenting and approving or rejecting changes to the project documents, deliverables, or baselines. •Configuration Management deals with changes in product specifications - An example of Configuration Management can be an extra feature added to the product •Change Management manages the changes in project baseline or process. - An example of Change Management system can be a change in budget, schedule, etc.
question
Name some configuration management activities
answer
Configuration identification Configuration status accounting Configuration verification and audit
question
What is configuration identification?
answer
Identification and selection of a configuration item to provide a basis for which the product configuration is defined and verified, products and documents are labeled, changes are managed, and accountability is maintain.
question
What is configuration status accounting?
answer
Information is recorded and reported as necessary. This info includes listing of approved configuration identification, status of proposed configuration changes, and implementation status of approved changes
question
What is configuration verification and audit?
answer
Ensures the composition of the project's configuration items is correct and that corresponding changes are registered, assess, approved, tracked, and correctly implemented. Functional requirements in the configuration documentation have been met
question
What happens when a CR is approved.
answer
The approved change request will be implemented through the Direct and Manage Project Work process.
question
What is the change log?
answer
Used to document change requests. Includes their impact to the project in terms of time, cost, and risk. And whether they are approved or not
question
Input to Close Project or Phase process
answer
Project management plan Accepted deliverables OPA
question
Tools and Techniques for Close Project or Phase process
answer
Expert judgment Analytical techniques Meetings
question
Outputs from Close Project or Phase process
answer
Final product, services, or result transition OPA
question
Closure Activities
answer
Actions and activities necessary to satisfy completion or exit criteria for the phase or project Actions and activities necessary to transfer the project's products, services, or results to the next phase or to production and/or operations Activities needed to collect project or phase records, audit project success or failure, gather lessons learned and archive project information for future use by the organization.
question
Name some examples of Accepted Deliverables
answer
Approved product specifications Delivery receipts Work performance documents For phased or cancelled projects these deliverables may be partial or interim
question
Describe "Final Product, Service, or Result Transition"
answer
Transition of the final product, service, or result that the project was authorized to product (for phase closure it is the intermediate not final)
question
Name some OPAs for Close Project or Phase process
answer
Project files - Documents resulting from the projects activities Project or phase closure documents - Formal doc to indicate completion and transfer. Includes reviewing customer acceptance doc or contract before finalizing closure. For terminated projects, this doc indicates why and formalizes transfer of finished and unfinished deliverables of cancelled project to others Historical information - This info and lessons learned are transferred to the knowledge db for use in future projects
Get an explanation on any task
Get unstuck with the help of our AI assistant in seconds
New