Chapter 9: Project Management Answers

question

projects
answer

unique nonroutine activities intended to accomplish some objective within a limited amount of time ex: building construction, movie production
question

project management
answer

planning, scheduling and controlling
question

project management parts
answer

project team matrix organization project manager scope statement statement of work work breakdown structure (WBS)
question

project team
answer

made up of individuals from various areas and departments within a company (group from editing, casting, directors)
question

matrix organization
answer

a team structure with members from functional areas, depending on skills required (select people from project teams)
question

project manager
answer

most important member to a project team
question

scope statement
answer

a document that provides an understanding, justification, and expected result of a project
question

statement of work
answer

written description of objectives of a project
question

work breakdown structure
answer

breaks a project into components, subcomponents, activities and tasks
question

project scheduling
answer

based off of a gantt chart allows us to see how things work and operations overlap
question

Early Start
answer

absolute earliest an activity can start equal to latest early finish times
question

early finish
answer

absolute earliest any activity can be finished given the order of the overall project
question

late start
answer

absolute latest any activity can begin without delaying the overall project
question

late finish
answer

absolute latest any activity can be finished without slowing down the project
question

critical path
answer

the absolute longest path for completion of the project (with a given time) having no slack
question

Start and finish time rules
answer

to determine the critical path we will analyze the program diagram twice using: forward pass – early start early finish backwards pass – late start and late finish
question

early start rules
answer

if an activity has one immediate predecessor, its ES is on the EF of its predecessor if has several, its ES is the max
question

Early finish time rules
answer

the early finish time of an activity is the sum of its ES time and its activity time
question

late finish time rule
answer

if an activity is an immediate predecessor, its LF equals the LS of the immediately following activity if an activity is an immediate predecessor for several activities, its LF equals the minimum of all LS values of the activities that immediately follow
question

late start time rule
answer

if the LS time of an activity is the difference of it LF time and its activity time
question

slack
answer

allowable slippage for any path LS-ES or LF-EF
question

for activities on the critical path (slack)
answer

delaying these activities will delay the entire project
question

move through the activity node chart in
answer

vertical slices
question

crashing a project
answer

sometimes projects need to be sped up in order to meet a specified date possibly because the project is behind schedule or a date has been changes
question

we generally crash projects on the critical path on the following guidelines
answer

amt by which an activity can be crashes is allowed taken together, the shortened activity durations will allow us to finish the project by the due date total cost of crashing is as small as possible
question

crashing costs tend to increase
answer

as project duration decreases meaning generally more expensive to crash projects that are already pretty short indirect costs increase as project time does we should aim to reduce the projects length so long as crashing costs are less than indirect costs
question

CPM, critical path management
answer

assumes that activity times are fixed with no variation if activity times vary, we use PERT analysis
question

time estimates for pert analysis
answer

optimistic time pessimistic time most likely time
question

optimistic time (a)
answer

shortest time activity should take if all goes according to plan
question

pessimistic time (b)
answer

longest time activity should take place if shit hits the fan
question

most likely time (m)
answer

most realistic estimate of activity time
question

estimates of our activity times are assumed to follow
answer

a beta distribution
question

using beta distribution
answer

we can calculate mean and variance of INDIVIDUAL activity times
question

in beta distribution
answer

we are only concerned with the expected times and variances on the critical path
question

we assume that the distribution of project times follows a
answer

normal distribution so we can use z scores and the standard normal table to compute possibilities