Chapter 9: Project Management Answers – Flashcards

Unlock all answers in this set

Unlock answers
question
projects
answer
unique nonroutine activities intended to accomplish some objective within a limited amount of time ex: building construction, movie production
question
project management
answer
planning, scheduling and controlling
question
project management parts
answer
project team matrix organization project manager scope statement statement of work work breakdown structure (WBS)
question
project team
answer
made up of individuals from various areas and departments within a company (group from editing, casting, directors)
question
matrix organization
answer
a team structure with members from functional areas, depending on skills required (select people from project teams)
question
project manager
answer
most important member to a project team
question
scope statement
answer
a document that provides an understanding, justification, and expected result of a project
question
statement of work
answer
written description of objectives of a project
question
work breakdown structure
answer
breaks a project into components, subcomponents, activities and tasks
question
project scheduling
answer
based off of a gantt chart allows us to see how things work and operations overlap
question
Early Start
answer
absolute earliest an activity can start equal to latest early finish times
question
early finish
answer
absolute earliest any activity can be finished given the order of the overall project
question
late start
answer
absolute latest any activity can begin without delaying the overall project
question
late finish
answer
absolute latest any activity can be finished without slowing down the project
question
critical path
answer
the absolute longest path for completion of the project (with a given time) having no slack
question
Start and finish time rules
answer
to determine the critical path we will analyze the program diagram twice using: forward pass - early start early finish backwards pass - late start and late finish
question
early start rules
answer
if an activity has one immediate predecessor, its ES is on the EF of its predecessor if has several, its ES is the max
question
Early finish time rules
answer
the early finish time of an activity is the sum of its ES time and its activity time
question
late finish time rule
answer
if an activity is an immediate predecessor, its LF equals the LS of the immediately following activity if an activity is an immediate predecessor for several activities, its LF equals the minimum of all LS values of the activities that immediately follow
question
late start time rule
answer
if the LS time of an activity is the difference of it LF time and its activity time
question
slack
answer
allowable slippage for any path LS-ES or LF-EF
question
for activities on the critical path (slack)
answer
delaying these activities will delay the entire project
question
move through the activity node chart in
answer
vertical slices
question
crashing a project
answer
sometimes projects need to be sped up in order to meet a specified date possibly because the project is behind schedule or a date has been changes
question
we generally crash projects on the critical path on the following guidelines
answer
amt by which an activity can be crashes is allowed taken together, the shortened activity durations will allow us to finish the project by the due date total cost of crashing is as small as possible
question
crashing costs tend to increase
answer
as project duration decreases meaning generally more expensive to crash projects that are already pretty short indirect costs increase as project time does we should aim to reduce the projects length so long as crashing costs are less than indirect costs
question
CPM, critical path management
answer
assumes that activity times are fixed with no variation if activity times vary, we use PERT analysis
question
time estimates for pert analysis
answer
optimistic time pessimistic time most likely time
question
optimistic time (a)
answer
shortest time activity should take if all goes according to plan
question
pessimistic time (b)
answer
longest time activity should take place if shit hits the fan
question
most likely time (m)
answer
most realistic estimate of activity time
question
estimates of our activity times are assumed to follow
answer
a beta distribution
question
using beta distribution
answer
we can calculate mean and variance of INDIVIDUAL activity times
question
in beta distribution
answer
we are only concerned with the expected times and variances on the critical path
question
we assume that the distribution of project times follows a
answer
normal distribution so we can use z scores and the standard normal table to compute possibilities
Get an explanation on any task
Get unstuck with the help of our AI assistant in seconds
New