ARE 5.0 Project Management – Flashcards

Unlock all answers in this set

Unlock answers
question
Project Management
answer
Includes project planning, scheduling, monitoring, coordinating and directing, updating documentation, closing out the job, and following up with clients.
question
Partnering
answer
Various stakeholders in a project (such as the architect, owner, contractor and vendors) all participate in the decision-making process.
question
Bar Chart
answer
Method commonly used for scheduling design and construction projects. Tasks are listed in chronological order on vertical access and time period is listed on horizontal axis. (Aka Gantt Chart)
question
Dependency
answer
The relationship between a task that must be completed before another can start.
question
Critical Path Method (CPM)
answer
Common scheduling tool that graphically depicts all the tasks needed to complete a project, the sequence in which tasks must occur, and each task's duration.
question
Float
answer
The maximum length of time a noncritical task can be delayed or extended before it causes a delay.
question
Work Plan
answer
A detailed project schedule, breaking the project down into its component tasks and assigning staff members and other resources to each task. (Aka Fee projection)
question
Pro Forma
answer
Statement listing the expected income that the project will generate and the expected costs to build the project.
question
Value Engineering
answer
Reviewing individual systems and materials to see if the same function can be accomplished in a less expensive way.
question
Building Cost
answer
The money needed to construct the building, including structure, exterior cladding, finishes, and electrical and mechanical systems, as well as the contractor's overhead and profit.
question
Site Development Costs
answer
Cost of parking, drives, fences, landscaping, exterior lighting, and irrigation systems.
question
Furniture, Fixtures, and Equipment (FF&E)
answer
Costs of movable equipment, furnishings, accessories, and window coverings.
question
Professional Services
answer
Architectural and engineering fees as well as costs for services such as topographic surveys, soil tests, special consultants, appraisals, and legal consultation.
question
Financing
answer
Includes the long-term interest paid on permanent financing as well as the immediate costs of loan origination fees, construction loan interest, and other administrative costs.
question
Debt Service
answer
The cost to pay off the construction loan for a project and is generally considered an ongoing cost over many years, not part of the original cost of the project.
question
Top-Down Approach
answer
An approach for estimating fees where the PM begins by estimating the total fee needed to complete the project using a combination of rules of thumb and historical data.
question
Bottom-Up Approach
answer
An approach for estimating fees where the PM begins by breaking the project down into individual tasks and estimating how much time will be needed to complete each one.
question
Total Working Fee
answer
The fee available to pay people to do the job after subtracting fees for proffit, consultants and other expenses.
question
Project Monitoring Chart
answer
Used to monitor employees' time sheets weekly in order to compare the actual hours expended to the budgeted time and take corrective action if the actual time exceeds the budgeted time.
question
Communication
answer
The most important aspect of project management that includes 4 basic kinds known as work assignments, instructions, reward and punishment and social interaction.
question
Consultant
answer
An expert who is not part of the firm's regular staff but is employed to work on one or more specific projects.
question
Structural Engineer
answer
Designs and produces the drawings and specs for any new structure or structural modifications, including the building foundation, frame, floors, and load-bearing walls.
question
Mechanical Engineer
answer
Designs and produces the drawings and specs for the heating, ventilating, and air conditioning (HVAC) systems on a project, as well as any plumbing systems needed.
question
Project Notebook
answer
Gives the PM immediate access to information for planning, coordinating and monitoring the job. One of the most useful PM tools.
question
Project Perfection Syndrome
answer
The desire to continue to pursue perfection.
question
Meeting Minutes
answer
Documentation of all meetings and serve as the formal record of the proceedings and may have legal implications later on.
question
Contract Documents
answer
The formalized form of mutual understanding about what the architect will do and what the client will give in return for services rendered.
question
Basic Services
answer
Include the five traditional phases of a design-bid-build project: schematic design, design development, construction documents, bidding, and construction administration.
question
Additional Services
answer
Other services not apart of basic services which can include programming, building information modeling, LEED certification, and post occupancy evaluation.
question
Cost of the Work
answer
The cost of labor and materials furnished by the owner and the cost of items specified or designed by the architect, plus a reasonable allowance for overhead and profit.
question
Mediation
answer
A process in which a neutral third party helps the disputing parties negotiate a settlement, using rules established by the American Arbitration Association (AAA)
question
Arbitration
answer
A formal, legally binding process for resolving disputes without litigation
question
Reimbursable Expenses
answer
Expenses paid by the architect that are directly related to the project.
question
Cost Plus Fee
answer
The architect is compensated for the actual expenses of doing the job plus a reasonable fee for profit.
question
Percentage of Construction Cost
answer
The professional fee is a fixed percentage of the cost of construction.
question
Unit Cost
answer
Fees are based on a definable unit, such as Sq Ft, for such work as tenant planning in a leased building, or on a per-house basis in a large residential project.
question
Sustainability Workshop
answer
Team members confirm the sustainability objective, establish the goals and expectations for the project, and discuss possible sustainable measures.
question
Sustainable Measure
answer
A specific design or construction element, or a post-occupancy use, operation, maintenance or monitoring requirement, that must be completed in order to achieve the sustainable objective.
question
Sustainability Plan
answer
A contract document that identifies and describes the objective, measures to achieve the objective, strategies to implement sustainable measures, responsibilities of the owner, architect and contractor, details about design reviews, testing required to verify achievement and documentation required for the project.
question
Sustainability Certification
answer
Certification of sustainable design, construction, environmental performance, or energy performance.
question
Substantial Completion
answer
The stage at which the work, or a designated portion of it, is sufficiently complete that the owner can occupy it or use it for its intended purpose.
question
Liquidated Damages
answer
Fees paid by the contractor to the owner for every day the project is late.
question
Retainage
answer
A percentage of each payment is withheld until final completion of the work.
question
Stipulated Sum
answer
A fixed price that the owner agrees to pay the contractor for the work as shown in the contract documents.
question
Guaranteed Maximum Price (GMP)
answer
The contractor or construction manager guarantees the owner a fixed, maximum price.
question
Instruments of Service
answer
Any representations of the tangible and intangible creative work of the architect and the architect's consultants. Includes studies, surveys, models, sketches, drawings, specs, etc.
question
Change Order
answer
An order written by the architect and signed by the owner, contractor, and architect
question
Construction Change Directive
answer
Instructs the contractor to proceed with the stated changes in the work, even if the contractor does not agree with the basis for adjustment in contract sum or contract time.
question
Contract Time
answer
The period from the starting date established in the agreement to the time of substantial completion, including any authorized adjustments.
question
Mechanic's Lien
answer
A claim by one party against the property of another party for the satisfaction of a debt.
question
Surety Bond
answer
Protection for the owner against default by the contractor (Aka contract bond)
question
Claim
answer
An assertion, made by one of the parties to the contract, that he or she is owed payment or some other form of relief from under the contract's terms.
question
Direct damages
answer
The cost of repairing defective work or completing unfinished work.
question
Consequential damages
answer
Damages that are not caused directly and immediately by the other party's actions, but from the consequences of those actions. (Aka Indirect Damages)
question
Scope Creep
answer
Happens when the client or the architect makes uncontrolled changes to the original list of services set forth in the owner-architect agreement.
question
Parameter Method
answer
Method of budgeting that involves an expanded itemization of construction quantities and assignment of unit costs to these quantities.
question
Matrix Costing
answer
Method of budgeting where a matrix is drawn showing the various alternatives along one side and the individual elements that combine to produce the total cost of the alternatives on the other side.
question
Unit Cost Method
answer
Method of budgeting where the project is broken down into its individual building components and the labor needed to install them.
question
Life-Cycle Cost Analysis (LCCA)
answer
A method for determining the total cost of a building, building component, or system over the expected life of the building.
question
Quality Control (QC)
answer
An organized set of procedures, systems, and tools established by an office that aid in meeting the expectations of the client, maintaining a high level of professional service, and reducing risks and liability.
question
Achieving Quality through Process
answer
Achieving quality by making sure tasks are performed correctly the first time so that there is no need to redo them later.
question
Achieving Quality through Checking
answer
Achieving quality by making sure a finished product is correct before it is delivered to the end user.
question
Checklist
answer
A list of things that need to be considered or accomplished in order to complete a particular task.
question
Process-Based System
answer
Automates a procedure so that a task can be performed accurately and consistently with little or no human intervention.
question
Quality Circle
answer
A small group of employees who meet regularly to identify, analyze, and solve problems related to their particular sphere of work.
question
Steering Committee
answer
Guide the quality circle program, set goals and objectives, monitor progress, and, in general, see that the program is consistent with the overall goals of the firm.
question
Corporate Knowledge
answer
The documentation of information that an Architectural firm has gained through the work it has done and that can be applied to new projects.
question
Project Files
answer
A record of how the entire job progressed, from initial marketing to project closeout and follow-up.
question
Contemporaneous Documentation
answer
The recording of communications, decisions, and other actions that are not normally relegated to a standard form or whose occurrence cannot be predicted to take place at a given time or circumstance, such as within a regularly scheduled project meeting.
question
Hearsay
answer
A written or oral statement that was made outside of the court, usually by another person than the witness. Usually not allowed as evidence in court.
question
Business Entry Rule
answer
An exception to hearsay where a project record must have been made during the normal course of business, it must have been made at or shortly after the act, event, or transaction being recorded, and it must be the regular course of business for such a record to be made.
question
Directed Acceleration
answer
The owner instructs the contractor to speed up the schedule and agrees to pay the additional costs associated with the changes, which is directed through a change order.
question
Voluntary Acceleration
answer
The contractor may decide to speed up the work because the work has fallen behind the original schedule, the construction company is trying to finish early to collect a bonus, or they want to move personnel to another job.
question
Constructive Acceleration
answer
A contractor may opt to speed up a project due to an excusable or unavoidable delay caused by weather, deliveries or change orders. The contractor may choose to file a claim for damages if the extra time is warranted but not given and the contractor had to incur extra expenses to complete the work on time.
question
Addendum
answer
A written or graphic document issued by the architect during the bid period prior to the execution of the contract, that modifies or interprets the bidding documents by addition, deletion, clarification, or correction.
question
Minor change in the work
answer
A written order by the architect directing the contractor to make a minor change that does not involve modification to the contract sum or time and is consistent with the contract documents.
question
Request For Information (RFI)
answer
A standard form that the owner, architect and contractor may use to request further information from one another during construction.
question
Architects Supplemental Instructions (ASI)
answer
A means for the architect to address minor changes to the extent that AIA Document A201 authorizes, and may include both written instructions and drawings.
question
Submittals
answer
Shop drawings, samples, product data and documents related to sustainability issues (where applicable) that the contractor is responsible for providing after the contract is awarded.
question
Shop Drawings
answer
Detailed drawings, diagrams, schedules and other data prepared to show how a subcontractor or supplier proposes to supply and install work to conform to the requirements for this specific project.
question
Sample
answer
A physical example of a portion of the work, intended to show exactly how a material, finish, or piece of equipment will look in the completed job.
question
Product Data
answer
Brochures, charts, instructions, performance data, catalog pages and other information that illustrate some portion of the work.
question
Cut Sheet
answer
A short-format summary of a material or product's properties and characteristics and is often included in the product data submission.
question
Earned Value Management Method
answer
A technique used to predict both the time and money that is required to complete certain tasks.
question
Cost-Plus-Fee
answer
The contractor is compensated for the actual expenses of labor, materials, and subcontractors in addition to a fixed fee.
question
Work
answer
Consists of the contractor's obligations to provide improvements to the project.
question
Project
answer
Consists of the work of the contractor plus construction by other contractors or the owners own forces.
question
Substitutions
answer
Can be made by the contractor so long as he or she receives consent from the owner, after evaluation from the architect and in accordance with a change order.
question
Warranty
answer
The contractor guarantees that the materials and workmanship furnished under the contract are of good quality, free of defects and conform to the requirements of the contract documents.
question
Allowance
answer
The architect's estimated cost of a particular material or piece of equipment when the actual cost cannot be precisely determined at the time of the bid or negotiated proposal.
question
Record Documents
answer
Copies of all construction drawings, specifications, and other contract documents, marked to record exactly how the project was built, noting any changes or deviations from the original documents.
question
Design Delegation
answer
Allows the use of performance specifications for products and building assemblies. It can also let the contractor select the best approach to completing the work.
question
Indemnification
answer
The contractor will indemnify and hold harmless the owner, architect, architects consultants, and agents against claims, damages, and expenses arising from performance of the work.
question
Indemnify
answer
To secure against loss or damage.
question
Special Conditions
answer
Provisions that are completely unique to a particular project or project site.
question
Competitive Bidding
answer
Must be conducted within clearly defined guidelines that protect the owner from disreputable contractors and unethical bidding practices.
question
Value-Based Selection (VBS)
answer
Process that considers more than just the lowest bid cost, but also factors such as quality, schedule, and contractor personnel.
question
Negotiation
answer
The process in which the owner, with the assistance of the architect, works out a final contract price with one contractor.
question
Advertisement for Bids
answer
Published in one or more newspapers, trade journals or online publications when any contractor is permitted to submit a bid.
question
Invitation to Bid
answer
Only sent to prospective, prequalified contractors to submit a bid.
question
Instructions to Bidders
answer
Outline the procedures and requirements that the bidders must follow in submitting bids, how the bids will be considered, and submittals required of the successful bidder.
question
Bid security
answer
Required to ensure that the successful bidder will enter into a contract with the owner.
question
Performance Bond
answer
A statement by a surety company that obligates complete construction of the project in the event that the contractor defaults on his or her obligations.
question
Labor and Material Payment Bond
answer
Guarantees payment for labor and materials to suppliers, employees, or subcontractors by the defaulting contractor.
question
Agency Review
answer
Includes the standard building code check by the authority having jurisdiction (AHJ) as well as any other reviews by permitting agencies.
question
Buyout
answer
The process of selecting suppliers and finalizing prices from any remaining subcontractors and vendors that are not part of the IPD process.
question
Alternate
answer
A request included in the bidding documents asking the contractor to supply a price for some type of variation from the base bid.
question
Add Alternate
answer
An alternate that adds to the base bid.
question
Deduct Alternate
answer
An alternate that reduces the base bid.
question
Unit Price
answer
In bid documents: set costs for certain portions of work, based on an individual quantity.
question
Fire Resistance Rating
answer
The length of time that a construction material or assembly can withstand a standardized fire resistance test.
question
Fire Damper
answer
A listed device installed in ducts and air transfer openings that is designed to close automatically on detection of heat, to resist the passage of flame.
question
Smoke Damper
answer
A listed device installed in ducts and air transfer openings that is designed to resist the passage of smoke.
question
Fire Partition
answer
A wall assembly with a 1-hr fire resistance rating.
question
Fire Barrier
answer
A vertical or horizontal assembly that is fire-resistance rated and that is designed to restrict the spread of fire, confine it to limited areas, and/or afford safe passage for protected egress.
question
Fire Wall
answer
A fire-resistance rated wall that is used to separate a single structure into separate construction types or to provide for allowable area increases by creating what amounts to separate buildings.
question
Smoke Barrier
answer
A continuous vertical or horizontal membrane with a minimum fire-resistance rating of 1-hr that is designed and constructed to restrict the movement of smoke.
question
Occupancy
answer
The classification of the use of a building or interior space, such as an office, restaurant, residence, school, etc.
question
Mixed Occupancy
answer
When a building or area of a building contains two or more occupancies.
question
Accessory Occupancy
answer
A space or room that is ancillary to a main occupancy but that does not exceed 10% of the floor area of the story in which it is located.
question
Incidental Use
answer
Ancillary to a main occupancy and has the same classification as the nearest main occupancy, but poses a greater level of risk than that occupancy.
question
Fire Zone
answer
The division of a city in representation of the degree of fire hazard.
question
Fire Hazard
answer
Based on factors such as density, access to fire fighting equipment, existing building heights, and so forth.
question
Means of Egress
answer
A continuous and unobstructed path of vertical and horizontal egress travel from any point in a building or structure to a public way. Consists of the exit access, the exit and the exit discharge.
question
Public Way
answer
Any street, alley, or similar parcel of land essentially unobstructed from the ground to the sky that is permanently appropriated to the public for public use and has a clear width of not less than 10ft.
question
Exit Access
answer
The portion of the means of egress that leads to an exit.
question
Exit
answer
The portion of the egress system that provides a protected path of egress between the exit access and the exit discharge.
question
Exit Discharge
answer
The portion of the egress system between the termination of an exit and a public way.
question
Occupant Load
answer
The number of people that a building code assumes will occupy a given building or portion of a building.
question
Occupant Load Factor
answer
The amount of floor area presumed to be occupied by one person.
question
Gross Floor Area
answer
Includes stairs, corridors, toilet rooms, mechanical rooms, closets, and interior partition thickness when calculating occupant load.
question
Net Floor Area
answer
Includes only the space actually used by the occupant when calculating occupant load.
question
Common Path of Egress Travel
answer
The portion of the exit access travel distance measured from the most remote point within a story to the point where the occupants have separate access to two exits or exit access doorways and can make a choice about which direction to go.
question
Exit Access Travel Distance
answer
The distance that an occupant would have to travel to get from the most remote point in the occupied portion of the exit access area, along the natural and unobstructed path of horizontal and vertical travel, to the entrance to the nearest exit.
question
Corridor
answer
A fully enclosed portion of an exit access that defines and provides a path of egress travel to an exit.
question
Dead End
answer
Exists when a person in any part of a building required to have two means of egress has only one choice of direction that leads to an exit access doorway or an exit.
question
Stair
answer
A change in elevation accomplished by one or more risers.
question
Stairway
answer
One or more flights of stairs with the necessary landings and platforms connecting them to form a continuous passage from one level to another.
question
Interior Exit Stairway
answer
A stairway that is an exit component that meets one or more means of egress requirements
question
Exit Access Stairway
answer
An interior stairway that is not a required interior exit stairway.
question
High-Rise Building
answer
A building with occupied floors more than 75ft above the lowest level of fire department vehicle access.
question
Guardrail
answer
A component whose function is to prevent falls from an elevated area.
question
Chimney
answer
A primarily vertical structure containing one or more flues to carry gaseous products of combustion and air from a fuel-burning appliance to the outdoors.
question
Vent
answer
A pipe or factory-made component that contains a passageway for carrying combustion products and air to the atmosphere.
question
Floor Area Ratio (FAR)
answer
The ratio of the gross floor area within a structure to the area of the lot on which the structure is situated.
question
Setback
answer
The minimum distance a building must be placed from a property line.
question
Front Setback
answer
The distance from the property line facing the street or the primary front of the property.
question
Rear Setback
answer
The distance from the back of the lot.
question
Side setback
answer
The distance from the side property line.
question
Bulk Plane Restriction
answer
A zoning technique that establishes an imaginary inclined plane beginning at the lot line or the center of the street at a given elevation and slopes at a prescribed angle toward and over the lot. The building cannot extend beyond this plane.
question
Variance
answer
Permission to deviate from the zoning regulations.
question
Conditional Use Permit
answer
Allows a nonconforming use or other use in the zoning ordinance if the property owner meets certain conditions.
question
Proprietary Specification
answer
Specifies a particular product by brand name and allows no substitutions.
question
Decriptive Specification
answer
A specification that defines the type of outcome desired but does not list specific products.
question
Base Bid with Alternates
answer
Calls for a specific product but allows substitutions of other materials.
question
Base Bid with "approved equal" language
answer
Similar to Base Bid with Alternates except alternates require the architect's approval.
question
Milestone Chart
answer
Consists of a list of deadlines and assignment of responsibility for each task. Best for scheduling small projects with few participants.
question
General Obligation Bonds
answer
Typically used to fund a specific project, such as a library or fire station.
question
Developer Impact Fees
answer
Generally used to fund infrastructure improvements made necessary by new development.
question
Business Improvement Disticts
answer
Used to fund public space improvements to enhance an areas appeal and, indirectly, it's property values.
question
Tax Increment Financing
answer
A method of financing cities use to issue bonds to pay for improvements within a specified district. Improvements are intended to stimulate private development within the district by providing better infrastructure and city services.
question
Subrogation
answer
The legal technique whereby an insurer "steps into the shoes" of a party to whom it has made payment.
question
Davis Bacon Act
answer
Requires workers to be paid local prevailing wages when public funds are used.
question
Clinger-Cohen Act
answer
Allows the use of design-build contracting on federally funded projects.
question
Miller Act
answer
Requires contractors to post performance and payment bonds.
question
Brooks Act
answer
Requires federal agencies to award projects to architecture and engineering firms based on qualifications-based selection processes.
question
Utilization Ratio
answer
The ratio of time that a person spends working on billable tasks to the total amount of time worked.
question
Employee Time Sheet
answer
A record of time worked and the tasks accomplished, which the PM can use as a tool to track project progress.
question
Work Breakdown Structure
answer
The projects to-do list or the list of tasks that must be performed to complete the project.
question
Responsibility Matrix
answer
A document that the PM prepares that assigns tasks to specific team members.
question
Statute of Limitations
answer
Establishes the amount of time that a party has to take legal action upon discovery of a design or construction defect.
question
Statute of Repose
answer
Establishes the time to take legal action once construction has completed.
question
Parameter Method
answer
Calculates an estimated cost per Sq Ft for many types of materials so that the designer can understand the cost implications of each, as well as mix and match materials or systems to arrive at a design that complies with the project bidget.
question
Conditional Covenant
answer
States that if the restrictions prescribed in the deed are not followed, the title to the land will revert to the original grantor or his/her heirs.
question
Conditional Use Permit
answer
Provides permission from a zoning board to use a property for a special purpose.
question
Affirmative Covenant
answer
Commits a buyer of a piece of property to performing a specific duty in the future.
question
Eminent Domain
answer
Granted by the 5th Ammendment to the US Constitution, it is the right of a government to aquire private property for a use that is determined to be in the public interest.
question
Hard Costs
answer
Expenses directly associated with construction, including materials, labor and contractors overhead and profit.
question
Soft Costs
answer
Other project expenses such as design fees, legal fees, cost of financing the project, insurance, administrative costs incurred by the owner and moving expenses.
Get an explanation on any task
Get unstuck with the help of our AI assistant in seconds
New