Project Management 2.1 – Flashcards
Unlock all answers in this set
Unlock answersquestion
Risk Management Contingencies
answer
1. Contingency plans are predefined actions that the project team will take if an identified risk event occurs. 2. Fallback plans are developed for risks that have a high impact on meeting project objectives, and are put into effect if attempts to reduce the risk do not work. 3. Contingency reserves or contingency allowances are provisions held by the project sponsor or organization to reduce the risk of cost or schedule over-runs to an acceptable level. Could also include management reserves for unknown risks.
question
Common Source of Risks
answer
Do I have the right users? Did I involve the users early and often? Do I have a quality relationship with the users? Do I make involvement easy? Did I find out what the users need?
question
Broad Categories of Risk
answer
Market Risk - will the product be useful tot he organization or marketable for others? Financial Risk - can the organization afford to undertake the project? Technology Risk - is the project technically feasible? People Risk - does the organization have people with the appropriate skills to complete the project successfully? Structure/process Risk - What degree of change will the new project introduce into user areas and business procedures?
question
Risk Breakdown Structure
answer
A hierarchy of potential risks categories for a project. The highest level categories are typically business, technical, organizational and project management.
question
Brainstorming
answer
A technique by which a group attempts to generate ideas or find a solution for a specific problem by amassing ideas spontaneously and without judgement.
question
Probability / Impact Matrix or Chart
answer
Lists the relative probability of a risk occurring and the relative impact of the risk occurring.
question
Watch List
answer
A list of risks that have low priority but are still identified as potential risks.
question
Expected Monetary Value (EMV)
answer
The product of a risk event probability and the risk event's monetary value.
question
Sensitivity Analysis
answer
Used to see the effects of changing one or more variables on an outcome.
question
Response Strategies for Negative Risks
answer
1. Risk Avoidance - eliminate a specific threat 2. Risk Acceptance - accept the consequence if the risk occurs 3. Risk Transference - shift the consequences or responsibility to a t
question
Response Strategies for Positive Risks
answer
1. Risk Exploitation - do whatever you can to make sure the positive risk happens. 2. Risk Sharing - allocating ownership of the risk to another party. 3. Risk Enhancement - changing the size of the opportunity by identifying and maximizing key drivers of potential risk. 4.
question
Workarounds
answer
Unplanned responses to risk events when they do not have contingency plans in place.
question
Bid
answer
A document prepared by sellers to provide pricing for standard items that the buyer has clearly defined; also called a tender or quote.
question
Constructive Change Orders
answer
Oral or written acts or omissions by someone with actual or apparent authority that can be construed to have the same effect as a written change order.
question
Contract
answer
A mutually agreement that obligates the seller to provide specified products or services and obligates the buyer to pay for them.
question
Cost Plus Award Fee (CPAF) Contract
answer
A contract in which the buyer pays the supplier for allowable performance costs plus an award fee based on the satisfaction of subjective performance criteria.
question
Cost Plus Fixed Fee (CPFF) Contract
answer
A contract in which the buyer pays the supplier for allowable performance costs plus a fixed fee payment that is usually based on a percentage of estimated costs.
question
Cost Plus Incentive Fee (CPIF) Contract
answer
A contract in which the buyer pays the supplier for allowable performance costs along with a predetermined fee and an incentive bonus.
question
Cost Plus Percentage of Costs (CPPC) Contract
answer
A contract in which the buyers pays the supplier for allowable performance costs along with a predetermined percentage based on total costs.
question
Cost-Reimbursable Contracts
answer
Contracts that involve payment to the supplier for direct and indirect actual costs.
question
Fixed-Price Contract
answer
A contract with a fixed total price for a well-defined product or service; also called a lump-sum contract.
question
Lump-Sum Contract
answer
A contract with a fixed total price for a well-defined product or service; also called a fixed-price contract.
question
Make-or-Buy Decision
answer
An organization's decision to make certain products and perform certain services inside the organization or to buy them from an outside organization.
question
Point of Total Assumption (PTA)
answer
The cost at which the contractor assumes total responsibility for each additional dollar of contract cost in a fixed-price incentive fee contract.
question
Procurement
answer
Acquiring goods and services from an outside source.
question
Project Procurement Management
answer
The processes required to acquire goods and services for a project from outside the performing organization.
question
Proposal
answer
A document prepared by sellers when there are different approaches for meeting buyer needs.
question
Request for Proposal (RFP)
answer
A document used to solicit proposals from prospective suppliers.
question
Request for Quote (RFQ)
answer
A document used to solicit quotes or bids from prospective suppliers.
question
Sellers
answer
Contractors, suppliers, or providers who provide goods and services to other organizations.
question
Statement of Work (SOW)
answer
A description of the work required for procurement.
question
Termination Clause
answer
A contract clause that allows the buyer or supplier to end the contract.
question
Time and Material (T&M) Contracts
answer
A hybrid of fixed-prices and cost-reimbursable contracts.
question
Unit Pricing
answer
An approach in which the buyers pays the supplier a predetermined amount per unit of service, and the total value of the contract is a function of the quantities needed to complete the work.
question
Contingency Allowances
answer
Provisions held by the project sponsor or organization to reduce the risk of cost or schedule overruns to an acceptable level; also called contingency reserves.
question
Contingency Plans
answer
Predefined actions that the project team will take if an identified risk event occurs.
question
Contingency Reserves
answer
Provisions held by the project sponsor or organization to reduce the risk of cost or schedule overruns to an acceptable level; also called contingency allowances.
question
Decision Tree
answer
A diagramming analysis technique used to help select the best course of action when future outcomes are uncertain.
question
Delphi Technique
answer
An approach to derive a consensus among a panel of experts to make predictions about future developments.
question
Fallback Plans
answer
Plans developed for risks that have a high impact on meeting project objectives, and implemented if attempts to reduce the risk are not effective.
question
Flowcharts
answer
Diagrams that show how various elements of a system relate to each other.
question
Influence Diagram
answer
A diagram that represents decision problems by displaying essential elements, including decisions, uncertainties, and objectives, and how they influence each other.
question
Interviewing
answer
A fact-finding technique that is normally done face to face, but can also occur through phone calls, e-mail, or instant messaging.
question
Known Risks
answer
Risks that the project team has identified and analyzed and that can be managed proactively.
question
Management Reserves
answer
Funds held for unknown risks.
question
Monte Carlo Analysis
answer
A risk quantification technique that simulates a model's outcome many times to provide a statistical distribution of the calculated results.
question
Probability/Impact Matrix or Chart
answer
A matrix or chart that shows the relative probability of a risk occurring and the relative impact of the risk.
question
Residual Risks
answer
Risks that remain after all of the response strategies have been implemented.
question
Risk
answer
An uncertainty that can have a negative or positive effect on meeting project objectives.
question
Risk Acceptance
answer
Accepting the consequences if a risk occurs.
question
Risk Appetite
answer
The degree of uncertainty an entity is willing to take on in anticipation of a reward.
question
Risk-Averse
answer
Have a low tolerance for risk.
question
Risk Avoidance
answer
Eliminating a specific threat or risk, usually by eliminating its causes.
question
Risk Enhancement
answer
Changing the size of an opportunity by identifying and maximizing key drivers of the positive risk.
question
Risk Events
answer
Specific uncertain events that may occur to the detriment or enhancement of the project.
question
Risk Exploitation
answer
Doing whatever you can to make sure a positive risk happens.
question
Risk Factors
answer
Numbers that represent the overall risk of specific events, given their probability of occurring and the consequence to the project if they do occur.
question
Risk Management Plan
answer
A plan that documents the procedures for managing risk throughout a project.
question
Risk Mitigation
answer
Reducing the impact of a risk event by reducing the probability of its occurrence.
question
Risk-Neutral
answer
A balance between risk and payoff.
question
Risk Owner
answer
The person who will take responsibility for a risk and its associated response strategies and tasks.
question
Risk Register
answer
A document that contains results of various risk management processes, often displayed in a table or spreadsheet format.
question
Risk-Seeking
answer
Having a high tolerance for risk.
question
Risk Sharing
answer
Allocating ownership of a risk to another party.
question
Risk Tolerance
answer
The maximum acceptable deviation an entity is willing to accept on a project or business objectives as the potential impact.
question
Risk Transference
answer
Shifting the consequence of a risk and responsibility for its management to a third party.
question
Risk Utility
answer
The amount of satisfaction or pleasure received from a potential payoff.
question
Runaway Projects
answer
Projects that have significant cost or schedule overruns.
question
Secondary Risks
answer
Risks that are a direct result of implementing a risk response.
question
Top Ten Risk Item Tracking
answer
A qualitative risk analysis tool for identifying risks and maintaining an awareness of risks throughout the life of a project.
question
Triggers
answer
Indications for actual risk events.
question
Unknown Risks
answer
Risks that cannot be managed proactively because they have not been identified and analyzed.
question
Blogs
answer
Journals on the Web that allow users to write entries, create links, and upload pictures, while readers can post comments to journal entries.
question
Communications Management Plan
answer
A document that guides project communications. 1. Stakeholder communications requirements. 2. Information to be communicated, including format, content, and level of detail. 3. Who will receive the information and who will produce it. 4. Suggested methods or technologies for conveying the information. 5. Frequency of communication. 6. Escalation procedures for resolving issues. 7. Revision procedures for updating the communications management plan. 8. A glossary of common terminology.
question
Google Docs
answer
Online applications offered by Google that allow users to create, share, and edit documents, spreadsheets, and presentations online.
question
Lessons-Learned Report
answer
Reflective statements written by project managers and their team members to document important information they have learned from working on a project.
question
Progress Reports
answer
Reports that describe what the project team has accomplished during a certain period of time.
question
Project Archives
answer
A complete set of organized project records that provide an accurate history of the project.
question
SharePoint Portal
answer
A tool that allows users to create custom Web sites to access documents and applications stored on shared devices.
question
Status Reports
answer
Reports that describe where a project stands at a specific point in time.
question
Wiki
answer
A Web site that enables anyone who accesses it to contribute or modify content.
question
Processes for Project Management Communication
answer
1. Planning communications management - determining the information and communications needs of the stakeholders. 2. Management communications - involves crating, distributing, storing, retrieving, and disposing of project communications based on the communications management plan. 3. Controlling communications involves monitoring and controlling project communications based on the communications management plan.
question
Misc
answer
Short face-to-face meeting are often more effective than electronic communications, particularly for sensitive information.
question
Misc.
answer
People also have a tendency to avoid reporting bad news.
question
Misc.
answer
Oral Communication via meetings and informal talks helps bring important information positive or negative into the open.
question
Determining the number of Communications Channels
answer
n(n-1)/2
question
Misc.
answer
Information about the content of essential project communications comes from the work breakdown structure (WBS).
question
Broad Classification for Communications Methods
answer
1. Interactive Communication: Two or more people interact to exchange information via meetings, phone calls, or video conferencing. 2. Push Communication: Information is sent or pushed to recipients without their request via reports, e-mails, faxes, voice mails, and other means. 3. Pull Communication: Information is sent to recipients at their request via Web sites, bulleting boards, e-learning, knowledge repositories like blogs, and other means.
question
Forecasts
answer
Predict future project status and progress based on past information and trends.
question
Running Effective Meetings
answer
1. Determine if a meeting can be avoided 2. Define the purpose and intended outcome of the meeting 3. Determine who should attend the meeting 4. Provide an agenda to participants 5. Prepare handouts and visual aids, and make logistical arrangements ahead of time 6. Run the meeting professionally 7. Set the ground rules for the meeting 8. Build relationships
question
Misc.
answer
Post installation audit should be part of the project archives.
question
Misc.
answer
Risk management can have a positive impact on selecting projects, determining their scope, and developing realistic schedules and cost estimates.
question
Risk Management Processes
answer
1. Planning risk management involves deciding how to approach and plan risk management activities. 2. Identifying risks involves determining which risks are likely to affect a project and documenting the characteristic of each. 3. Performing qualitative risk analysis involves prioritizing risks based on their probability and impact of occurrence. 4. Performing quantitative risk analysis involves numerically estimating the effects of risks on project objectives. 5. Planning risk responses involves taking steps to enhance opportunities and reduce threats to meeting project objectives. 6.controlling risk involves monitoring identified and residual risks, identifying new risks, carrying out risk response plans, and evaluating the effectiveness of risk strategies.
question
Broad Categories of Risk
answer
1. Market Risk: will the project be useful to the organization or others? 2. Financial Risk: can the organization afford to undertake the project? 3. Technology Risk: is the project technically feasible? 4. People Risk: does the organization have people with the appropriate skills to complete the project successfully? 5. Structure/process Risk: What degree of change will the new project introduce into user areas and business procedures?
question
Response Strategies for Negative Risks
answer
1. Risk avoidance 2. Risk acceptance 3. Risk transference 4. Risk mitigation
question
Response Strategies for Positive Risks
answer
1. Risk exploitation 2. Risk sharing 3. Risk enhancement 4. Risk acceptance
question
Outsourcing Accomplishments
answer
1. Access skills and technologies 2. Reduce both fixed and recurrent costs 3. Allow the client organization to focus on its core business 4. Provide flexibility 5. Increase accountability
question
Project Procurement Management Processes
answer
1. Planning procurement management involves determining what to procure and when and how to do it. 2. Conducting procurements involves obtaining seller responses, selecting sellers, and awarding contracts. 3. Controlling procurements involves managing relationships with sellers, monitoring contract performance, and making changes as needed. 4. Closing procurements involves completion and settlement of each contract or agreement, including resolution of any open items.
question
Project Procurement Best Practices
answer
1. Changes to any part of the project need to be reviewed, approved, and documented by the same people in the same way they approved the original part of the plan. 2. Evaluation of any change should include an impact analysis. 3. Changes must be documented in writing. 4. When procuring complex information systems, project managers and their teams must stay closely involved to make sure the new system will meet business needs and work in an operational environment. 5. Have backup plans in case the new system does not work as planned. 6. Several tools and techniques can help in contract administration, such as formal contract change control system, buyer-conducted procurement performance reviews, inspections and audits, performance reporting, payment systems, claims administrations, and records management systems.
question
Stakeholder Management Processes
answer
1. Identifying stakeholders involves identifying everyone involved in the project or affected by it, and determining the best ways to manage relationships with them. 2. Planning stakeholder management involves determining strategies to effectively engage stakeholders in project decisions and activities based on their needs, interests, and potential impact. 3. Managing stakeholder engagement involves communicating and working with project stakeholders to satisfy their needs and expectations, resolving issues, and fostering engagement in project decisions and activities. 4. Controlling stakeholder engagement involves monitoring stakeholder relationships and adjusting plans and strategies for engaging stakeholders as needed.