Project Management TPV1 and C176 WGU Test Answers – Flashcards

Unlock all answers in this set

Unlock answers
question
Acceptance criteria
answer
Requirements and conditions that must be met before the project deliverables are formally accepted.
question
Acceptance test
answer
A group of end-users work with the final product to test it for unidentified issues that may appear during routine use. Also known as User Acceptance Testing (UAT).
question
Actual duration
answer
The number of hours or days expanded to complete a project activity.
question
Actual effort
answer
The actual number of person hours or days expended to complete an activity.
question
Activity
answer
A specified piece of work that needs to be completed. An activity typically has an expected duration, cost and requires certain resources. Also known as task.
question
Activity list
answer
A list of the defined activities that need to be completed for a project.
question
Activity sequencing
answer
Identifying activity dependency relationships (how activities affect each other) and determining the best order to perform the activities to complete the project.
question
Actual cost (AC)
answer
The actual cost expanded to complete a project activity or work package.
question
Assignment
answer
The activities team members are responsible to complete.
question
Assumptions
answer
Factors that are believed to be true and affect project planning. Assumptions may impact risk and should always be documented and validated.
question
Baseline
answer
Represents the original approved plan for schedules, costs, etc. and is used to monitor and control ongoing project performance.
question
Budget
answer
The amount of money allocated for a project.
question
Budget at completion (BAC)
answer
The budget estimate determined in the planning phase for a work package or entire project to be completed.
question
Business value
answer
The positive impact for the business that will be achieved with completion of the project (e.g. generate revenue, customer satisfaction, etc.).
question
Change control board
answer
A group of stakeholders responsible for reviewing and accepting or rejecting changes to the project.
question
Change control process
answer
A process that ensures changes to the project are identified, evaluated, approved, documented and managed.
question
Change management plan
answer
A plan that documents the process for managing changes to the project.
question
Change request
answer
A document that is submitted to request a change to any part of the project management plan after the plan was approved.
question
Communications
answer
Relaying information so that all concerned parties have an equal understanding.
question
Communications management plan
answer
A plan that documents who will receive information about the project, what information they will receive, when they will receive it and how the information will be communicated. It also identifies the person who is responsible for providing the information.
question
Consensus
answer
A decision that a group agrees to support. It is usually achieved by discussing the relevant issues and options.
question
Constraint
answer
A financial, schedule, risk or resource-based limitation on a project.
question
Contingency reserve
answer
Allocation of resources to address possible adverse events.
question
Contract
answer
A legal, mutually-binding document between buyer and seller covering the terms and conditions by which the work must be completed.
question
Contract administration
answer
Managing the relationship with the seller and overseeing that all elements of the contract are met.
question
Contract closeout
answer
The process of determining whether the work as outlined in the contract was completed accurately and settling the terms of the contract.
question
Corrective action
answer
Actions taken to bring expected performance in line with the project plan.
question
Cost-benefit analysis
answer
A benefit measurement method that weighs expected project costs against expected project benefits.
question
Cost control
answer
Managing and controlling changes to the cost baseline.
question
Cost estimating
answer
Estimating the cost of resources that will be required to complete each project activity.
question
Cost variance (CV)
answer
The difference between the budgeted cost and actual cost. CV = EV - AC
question
Cost of quality
answer
The costs incurred to ensure the quality of the project.
question
Critical path
answer
The longest path through all project activities (as represented in a network diagram) that determines the duration of the project. The activities on the critical path usually have zero float.
question
Critical path method (CPM)
answer
A technique used to determine the duration of a project by looking at the sequence of activities and their flexibility in scheduling.
question
Customer
answer
The recipient of service or product that the project created. Also known as client in some organizations.
question
Decomposition
answer
Breaking the project deliverables into smaller, more manageable components.
question
Deliverable
answer
Outcome or product that is produced to complete a work package or project.
question
Dependency
answer
The relationship between project activities.
question
Early finish date
answer
The earliest date that an activity may be completed in the activity sequence.
question
Early start date
answer
The earliest date that an activity can be started in the activity sequence.
question
Earned value (EV)
answer
A measurement used to determine a project's progress and represents the value of the work completed to date. Also known as budgeted cost of work performed (BCWP).
question
Baseline
answer
Represents the original approved plan for schedules, costs, etc. and is used to monitor and control ongoing project performance.
question
Top-down estimating
answer
An estimating technique that uses historical project information to estimate the project duration of a similar project. Also known as analogous estimating.
question
Backward pass
answer
...Calculation of the late start and the late finish dates for uncompleted activities by working backwards through the network diagram from the project's end date. Part of critical path method (CPM).
question
End user
answer
The person or group who will use the product produced by the project.
question
Estimate at completion (EAC)
answer
The estimated total cost of the completed project at a particular time, using current project performance and work that still needs to be completed. EAC = AC + ETC
question
Estimate to complete (ETC)
answer
The estimated amount of the work that still needs to be completed.
question
Expert judgment
answer
Using subject matter experts to assist in decision making.
question
External dependency
answer
A relationship between a project activity and a factor outside the scope of the project that influences the completion of that activity.
question
Finish-to-finish dependency
answer
When the completion of an activity is dependent on the completion of the preceding activity.
question
Finish-to-start dependency
answer
When the start of an activity is dependent on the completion of the previous activity.
question
Fixed cost
answer
A cost that remains constant regardless of a change in production.
question
Float
answer
The amount of time that the early start of an activity can be delayed without affecting the completion date of the project. Also known as slack time.
question
Flowchart
answer
A diagram showing the steps in a process or system from beginning to end.
question
Formal acceptance
answer
When the authorized stakeholder provides sign-off, indicating the product has been received and is acceptable.
question
Functional manager
answer
The person responsible for the activities of a specific functional department.
question
Functional organization
answer
An organizational structure that groups staff hierarchically by area of specialty.
question
Gantt chart
answer
A schedule that shows project activities with associated start and completion dates. Also known as bar chart.
question
Kickoff meeting
answer
A meeting held at the end of major planning activities for all stakeholders to provide an overview of the project and outline expectations, ensure a common understanding of the project and to build consensus and excitement about the project.
question
Initiation
answer
Formal definition and authorization of a new project or continuation of an ongoing project.
question
Issue
answer
An identified element or event that may have a negative impact on the project and needs to be avoided or resolved.
question
Integrated change control
answer
Coordinating and managing change across the entire project scope, schedule and budget.
question
Integration management plan
answer
A plan that documents how elements of the project will be integrated and outlines how changes will be managed across the project.
question
Issue log
answer
A document that outlines each project issue, along with the person responsible for resolving it, status and expected resolution date.
question
Late finish date
answer
The latest date an activity can be completed without delaying the completion of the entire project.
question
Late start date
answer
The latest date an activity can begin without affecting the completion of the entire project.
question
Lessons learned
answer
The learning that takes place during the project and is documented to provide information on what went well and which aspects could have been improved. Lessons learned serve as references for future projects.
question
Matrix organization
answer
An organization where project team members answer to both a functional manager and a project manager.
question
Milestone
answer
The completion of a significant event or major deliverable used to measure project progress.
question
Negative variance
answer
The negative number that results from comparing planned project results with actual project results. A negative variance in the project schedule indicates the project is behind schedule. A negative variance in the budget indicates the project is over budget.
question
Network diagram
answer
A method of determining the sequence of activities, including dependencies for a project. Types include the activity-on-node (AON), arrow diagramming method (ADM) and precedence diagramming method (PDM).
question
Opportunity
answer
A chance to increase project benefits.
question
Operations and maintenance
answer
The turnover of a project to the operational staff of an organization for ongoing support and maintenance.
question
Opportunity
answer
A chance to increase project benefits.
question
Opportunity cost
answer
The opportunity given up by choosing to do one project over another one.
question
Positive variance
answer
The positive number that results from comparing planned project results with actual project results. A positive variance in the project schedule indicates the project is ahead of schedule. A positive variance in the budget schedule indicates the project is under budget.
question
Predecessor
answer
An activity that is on the same network diagram path and occurs before another activity.
question
Probability impact matrix
answer
A method of determining the severity of risk by looking at the probability of occurrence and impact on project objectives.
question
Procurement planning
answer
The process of determining which goods and services should be purchased or performed outside of the organization and outlines the details of what, how and when the goods should be acquired
question
Product life cycle
answer
The required phases to develop the product. For example, creation of a software product may follow a software development lifecycle that consists of requirements-gathering, design, development, testing and roll-out phases.
question
Program evaluation and review techniques (PERT)
answer
A weighted average time estimate of project duration using optimistic (O), pessimistic (P) and most likely (ML) estimates of project duration. Also known as three-point estimating. PERT = O + (4)ML + P
question
Project
answer
A temporary endeavor with defined start and end dates that creates a unique product or service.
question
Project charter
answer
A document that is created in the initiation phase that provides direction about the project's objectives and management and authorizes the project to begin. Also known as a project initiation document.
question
Project life cycle
answer
The management phases of a project which includes: initiation and scope definition; planning; execution, control and coordination; closure, acceptance and support
question
Project management
answer
The process of initiating, planning, executing, monitoring, controlling and closing out a project by applying skills, knowledge, tools and techniques to fulfill requirements.
question
Project management plan
answer
An overall project plan that contains all of the project management-related documents created during the phases of initiation and scope definition and planning.
question
Project performance indicators
answer
Measures to determine whether the project is on track.
question
Project scope
answer
The work required to produce the product of the project.
question
Qualitative risk analysisble for providing the information.
answer
Uses a subjective approach to determine the likelihood that risks will occur and the impact that risks will have on the project. This information enables the risk to be prioritized.
question
Quality assurance
answer
The evaluation of overall project performance on a regular basis to ensure quality management processes are followed
question
Quality control
answer
The process of measuring specific results to determine compliance with quality standards and taking corrective action if necessary.
question
Quality management plan
answer
A plan that documents the quality activities and outlines the processes, procedures, responsibilities and resources required for maintaining project quality.
question
Quantitative risk analysis
answer
Uses a mathematical approach to analyze the probability that risks will occur and the impact that risks have on the project. This information enables the risks to be prioritized. Techniques used for computing quantitative risk analysis include sensitivity analysis, decision tree analysis and Monte Carlo.
question
Remote team
answer
Individuals in different locations working on the same project and collaborating electronically or by telephone.
question
Request for proposal (RFP)
answer
A document provided to a prospective vendor requesting a proposal for work and or products to be provided. Also known as Invitation for Bid (IFB).
question
Resource
answer
Anything needed to complete the project. May be people, equipment, facilities or money.
question
Resource leveling
answer
Scheduling resource usage to be the same for each time period (e.g. monthly).
question
Return on investment (ROI)
answer
Determining whether the project outcomes will benefit the organization based on the resources used to complete the project.
question
Risk
answer
A potential event, occurrence or result that can have positive or negative consequences.
question
Risk assessment
answer
Identifying risks to the project and determining the affect the risks will have on the project.
question
Risk management plan
answer
A plan that documents the process for identifying and quantifying project risks and outlines how risks will be addressed or controlled.
question
Risk monitoring and control
answer
Uses the risk management plan to identify risks, respond to risks and monitor the effectiveness of the risk response.
question
Risk register
answer
A formal document that outlines identified project risks
question
Risk response
answer
The procedures that are implemented if an identified risk occurs.
question
Risk trigger
answer
An event that tells a risk is about to occur or has occurred.
question
Schedule management plan
answer
A plan that documents the process to manage project schedules and any changes made to the schedules.
question
Schedule variance (SV)
answer
The difference between scheduled activity completion and actual activity completion. SV = EV - PV; SV = Planned Date - Actual Date
question
Scope
answer
The amount of work involved to complete the project. Includes identifying the problem to be addressed by the project including the goals and objectives, measures of success and risks, and obstacles and assumptions that may affect the project outcome. Also known as project scope of work.
question
Scope creep
answer
The addition of new features or requirements while the project is in process.
question
Scope document
answer
A document that contains the project requirements and overall project direction. It should contain the goals, deliverables, budget, success criteria and important milestones.
question
Scope change control
answer
Controlling changes to the project scope
question
Scope change request
answer
A form submitted to request a change to the project scope.
question
Scope statement
answer
Documents the project objectives, business justification and goals. It outlines the deliverables that are to be included in the project along with the functional, business and technical requirements.
question
Sponsor
answer
An executive in the organization who can assign resources and can make final decisions on the project.
question
Staff acquisition
answer
The process of getting people assigned to and working on the project.
question
Stakeholder
answer
An individual or organization that affects or is affected by the project
question
Start-to-finish dependency
answer
The completion of an activity is dependent on the start of the previous activity.
question
Start-to-start dependency
answer
The beginning of an activity is dependent on the start of the previous activity.
question
Statement of work (SOW)
answer
A document that outlines the details and requirements of the product or service being procured.
question
Successor
answer
An activity that is on the same network diagram path and occurs after another activity
question
Technical requirements
answer
The product characteristics that are required for the product to perform the functional requirements.
question
Time and material contract
answer
A contract based on a unit rate such as an hourly wage plus reimbursement for materials or other expenses incurred
question
Triple constraint
answer
The link between the project constraints of time, cost and quality.
question
Variance
answer
The difference between actual and planned values.
question
Variance analysis
answer
The process of comparing planned project results against actual project results, determining the impact of the variance and implementing corrective actions if needed.
question
Virtual team
answer
Individuals in different reporting structures, departments, locations or organizations working together on the same project.
question
Workaround
answer
A response to deal with an unforeseen risk. A workaround is not planned in advance of the risk occurrence
question
Work breakdown structure (WBS)
answer
A deliverable-oriented hierarchy that depicts the entire project work.
question
WBS dictionary
answer
A document describing each work package in the WBS.
question
Work package
answer
The lowest level of the WBS. Includes activities required to fulfill a project deliverable or other project work.
question
Cost performance index (CPI)
answer
A performance tracking method that compares budgeted cost to the actual cost. CPI = EV / AC
question
Crashing
answer
Adding resources to activities on the critical path to reduce project duration.
question
Earned value analysis
answer
Shortening the project completion time without changing the scope of the project.
question
Fast tracking
answer
A method of schedule compression where activities that would typically be performed sequentially are performed in parallel to decrease schedule duration.
question
Feasibility study
answer
A study undertaken to determine whether a project is viable.
question
Free float
answer
The amount of time that an activity can be delayed without affecting the early start of the next activity.
question
Ishikawa diagram or Fishbone Diangram
answer
A graphical diagram that shows how causes or potential causes relate to create potential problems. Also known as Ishikawa diagram.
question
Pareto chart
answer
A graph that is used to rank the importance of a problem by the frequency with which it occurs.
question
Planned value (PV)
answer
The budgeted cost of work during a specified time period. Also known as budgeted cost of work scheduled (BCWS).
question
Risk acceptance
answer
A risk response that chooses to accept the consequences of the identified risk or the inability to identify another response strategy.
question
Risk avoidance
answer
A risk response that eliminates the identified risk or protects the project from the risk.
question
Schedule performance index (SPI)
answer
Ratio of work completed to work planned. SPI = EV/PV
question
Scope definition
answer
The process of breaking down deliverables into smaller components in order to provide better control.
question
Scope verification
answer
Formal acceptance by the stakeholders that deliverables and work results are completed to their satisfaction.
question
Threat.
answer
A negative risk that may or may not occur (as opposed to an opportunity, which is a positive risk).
question
To-complete performance index (TCPI)
answer
The performance that must be achieved during the remaining project to meet stated goals.
question
Work authorization system
answer
A formal process to ensure work is done in the right sequence and at the right time.
Get an explanation on any task
Get unstuck with the help of our AI assistant in seconds
New