Project Management – Chapter 7 – Flashcards
Unlock all answers in this set
Unlock answersquestion
Actual cost (AC)
answer
The total of direct and indirect costs incurred in accomplishing work on an activity during a given period; formerly called the actual cost of work performed (ACWP).
question
Analogous estimate
answer
A cost-estimating technique that uses the actual cost of a previous, similar project as the basis for estimating the cost of the current project; also called top-down estimate.
question
Baseline
answer
The original project plan plus approved changes.
question
Bottom-up estimate
answer
A cost-estimating technique based on estimating individual work items and summing them to get a project total.
question
Budget at completion (BAC)
answer
The original total budget for a project.
question
Budgetary estimate
answer
A cost estimate used to allocate money into an organization's budget.
question
Cash flow analysis
answer
A method for determining the estimated annual costs and benefits for a project.
question
COCOMO II
answer
A newer, computerized cost-estimating tool based on Barry Boehm's original model that allows one to estimate the cost, effort, and schedule when planning a new software development activity.
question
Computerized tools
answer
Cost-estimating tools that use computer software, such as spreadsheets and project management software.
question
Constructive Cost Model (COCOMO)
answer
A parametric model developed by Barry Boehm for estimating software development costs.
question
Contingency reserves
answer
Dollars included in a cost estimate to allow for future situations that may be partially planned for (sometimes called known unknowns) and are included in the project cost baseline.
question
Cost baseline
answer
A time-phased budget that project managers use to measure and monitor cost performance.
question
Cost budgeting
answer
Allocating the overall cost estimate to individual work items to establish a baseline for measuring performance.
question
Cost control
answer
Controlling changes to the project budget.
question
Cost estimating
answer
Developing an approximation or estimate of the costs of the resources needed to complete the project.
question
Cost management plan
answer
A document that describes how cost variances will be managed on the project.
question
Cost performance index (CPI)
answer
The ratio of earned value to actual cost; can be used to estimate the projected cost to complete the project.
question
Cost variance (CV)
answer
The earned value minus the actual cost.
question
Definitive estimate
answer
A cost estimate that provides an accurate estimate of project costs.
question
Direct costs
answer
Costs that can be directly related to producing the products and services of the project.
question
Earned value (EV)
answer
The percentage of work actually completed multiplied by the planned cost; formerly called the budgeted cost of work performed (BCWP).
question
Earned value management (EVM)
answer
A project performance measurement technique that integrates scope, time, and cost data.
question
Estimate at completion (EAC)
answer
An estimate of what it will cost to complete the project based on performance to date.
question
Function points
answer
Technology-independent assessments of the functions involved in developing a system.
question
Indirect costs
answer
Costs that are not directly related to the products or services of the project, but are indirectly related to performing the project.
question
Intangible costs or benefits
answer
Costs or benefits that are difficult to measure in monetary terms.
question
Learning curve theory
answer
A theory that states that when many items are produced repetitively, the unit cost of those items normally decreases in a regular pattern as more units are produced.
question
Life cycle costing
answer
Considers the total cost of ownership, or development plus support costs, for a project.
question
Management reserves
answer
Dollars included in a cost estimate to allow for future situations that are unpredictable (sometimes called unknown unknowns).
question
Overrun
answer
The additional percentage or dollar amount by which actual costs exceed estimates.
question
Parametric modeling
answer
A cost-estimating technique that uses project characteristics (parameters) in a mathematical model to estimate project costs.
question
Planned value (PV)
answer
The portion of the approved total cost estimate planned to be spent on an activity during a given period; formerly called the budgeted cost of work scheduled (BCWS).
question
Profit margin
answer
The ratio between revenues and profits.
question
Profits
answer
Revenues minus expenses.
question
Project cost management
answer
The processes required to ensure that the project is completed within the approved budget.
question
Rate of performance (RP)
answer
The ratio of actual work completed to the percentage of work planned to have been completed at any given time during the life of the project or activity.
question
Reserves
answer
Dollars included in a cost estimate to mitigate cost risk by allowing for future situations that are difficult to predict.
question
Rough order of magnitude (ROM) estimate
answer
A cost estimate prepared very early in the life of a project to provide a rough idea of what a project will cost.
question
Schedule performance index (SPI)
answer
The ratio of earned value to planned value; can be used to estimate the projected time to complete a project.
question
Schedule variance (SV)
answer
The earned value minus the planned value.
question
Source Lines of Code (SLOC)
answer
A human-written line of code that is not a blank line or comment.
question
Sunk cost
answer
Money that has been spent in the past.
question
Tangible costs or benefits
answer
Costs or benefits that can be easily measured in dollars
question
3 Project Management Processes
answer
1 - Estimating the cost 2 - Determining the budget 3 - Controlling costs
question
Outputs of estimating costs
answer
activity cost estimates basis of estimates project document updates
question
Outputs of determining the budget
answer
cost performance baseline project funding requirements project document updates
question
Outputs of controlling costs
answer
work performance measurements budget forecasts organizational process asset updates change requests project management plan updates project document updates
question
Why do many projects never finish?
answer
Cost management problems cause many problems to never finish.
question
What are most executives concerned with more than other issues?
answer
profits
question
When do organizations have a history of not spending enough money and what does it impact?
answer
They have a history of not spending enough money in the early phases of projects and it impacts the total cost of ownership.
question
Why is cash flow important?
answer
If top management selects too many projects that have high cash flow needs in the same year, the company will not be able to support all of its projects and maintain profitability.
question
Why is it important to define clearly the year on which the company bases its dollar amounts?
answer
If a company bases all costs on a previous years estimates it would need to account for inflation and other factors when projecting costs and benefits in future-year dollars.
question
3 basic types of estimates
answer
1 - Rough order of magnitude (ROM) 2 - Budgetary estimate 3 - Definitive estimate
question
Tom DiMarco's 4 reasons for project cost estimate inaccuracies.
answer
1 - Estimates often are done too quickly before clear system requirements have been produced. 2 - The person doing the estimating often has a lack of estimating experience. 3 - People have a tendency to underestimate. An experienced person may estimate based on how he/she would do the task, but the task may be performed by an inexperienced worker. 4 - Management desires accuracy. They are not looking for ballpark figures and often that is what they are given.
question
Earned value management involves calculating which three values for each activity or summary activity from a project's WBS?
answer
1 - Planned Value 2 - Actual Cost 3 - Earned Value
question
Earned value formula
answer
EV = PV to date * RP
question
Cost variance formula
answer
CV = EV - AC
question
Schedule variance formula
answer
SV = EV - PV
question
Cost performance index (CPI) formula
answer
CPI = EV / AC
question
Schedule performance index (SPI) formula
answer
SPI = EV / PV
question
Estimate at completion (EAC) formula
answer
EAC = BAC / CPI
question
Estimated time to complete formula
answer
Original time estimate / SPI
question
Five levels of project portfolio management from simplest to most complex
answer
1 - Put all your projects in one database 2 - Prioritize the projects in your database 3 - Divide your projects into two or three budgets based on type of investment, such as utilities or required systems to keep things running, incremental upgrades, and strategic investments. 4 - Automate the repository 5 - Apply modern portfolio theory, including risk-return tools that map project risk on a curve.
question
_______ is a resource sacrificed or foregone to achieve a specific objective or something given up in exchange.
answer
Cost
question
What is the main goal of project cost management?
answer
to complete a project within an approved budget.
question
Which of the following is not a key output of project cost management? a - activity cost estimates b - a cost management plan c - updates to the project management plan d - a cost performance baseline
answer
b - a cost management plan
question
If a company loses $5 for every $100 in revenue for a certain product, what is the profit margin for that product?
answer
-5%
question
______ reserves allow for future situations that are unpredictable.
answer
Management
question
You are preparing a cost estimate for a building based on its location, purpose, number of square feet, and other characteristics. What cost estimating technique are you using?
answer
parametric
question
______ involves allocating the project cost estimate to individual work items over time.
answer
Project cost budgeting
question
_____ is a project performance measurement technique that integrates scope, time, and cost data.
answer
Earned value analysis
question
If the actual cost for a WBS item is over $1500 and its earned value was $2000, what is its cost variance, and is it under or over budget?
answer
The cost variance is $500, which is under budget
question
If a project is halfway completed and its schedule performance index is 110 percent and its cost performance index is 95 percent, how is it progressing?
answer
It is ahead of schedule and over budget.
question
The ________ is the additional percentage or dollar amount by which actual costs exceed estimates.
answer
cost overrun
question
Which of the following processes of project cost management involves allocating the overall cost estimate to individual work items to establish a baseline for measuring performance?
answer
cost budgeting
question
Which of the following processes of project cost management involves developing an approximation of the costs of the resources needed to complete a project?
answer
cost estimating
question
The main outputs of the ________ process are work performance measurements, budget forecasts, organizational process asset updates, change requests, project management plan updates, and project document updates.
answer
cost control
question
To increase ________, a company can increase revenues, decrease expenses, or try to do both.
answer
profits
question
A company might complete a project to develop and implement a new customer service system in one or two years, but the new system could be in place for ten years. Project managers should create estimates of the costs and benefits of the project for ten years. This is an example of ________.
answer
life cycle costing
question
Avoid ________ when deciding what project to invest in or continue.
answer
sunk costs
question
________ for projects often include items like goodwill, prestige, and general statements of improved productivity that an organization cannot easily translate into dollar amounts.
answer
Intangible costs
question
________ are used for making many purchasing decisions for which accurate estimates are required and for estimating final project costs.
answer
Definitive estimates
question
Which type of estimate is done very early in a project or even before a project is officially started?
answer
rough order of magnitude (ROM) estimate
question
The drawback with ________ is that they are usually time-intensive and therefore expensive to develop.
answer
bottom-up estimates
question
A ________ might provide an estimate of $50 per line of code for a software development project based on the programming language the project is using, the level of expertise of the programmers, the size and complexity of the data involved, and so on.
answer
parametric model
question
Which type of estimate uses the actual cost of a previous, similar project as the basis for estimating the cost of the current project?
answer
top-down estimate
question
A(n) ________ is a time-phased budget that project managers use to measure and monitor cost performance.
answer
cost baseline
question
The ________ is an estimate of the value of the physical work actually completed.
answer
earned value (EV)
question
Suppose a project included a summary activity of purchasing and installing a new Web server. Suppose further that, according to the plan, it would take one week and cost a total of $10,000 for the labor hours, hardware, and software involved. The ________ for that activity that week is, therefore, $10,000.
answer
planned value (PV)
question
Which of the following is the earned value minus the actual cost?
answer
cost variance (CV)
question
Which of the following is the ratio of earned value to planned value and can be used to estimate the projected time to complete the project?
answer
schedule performance index (SPI)
question
Which of the following is the earned value minus the planned value?
answer
schedule variance (SV)
question
Which of the following is the ratio of earned value to actual cost and can be used to estimate the projected cost of completing the project?
answer
cost of performance index (CPI)