Project Management Ch. 10-13 – Flashcards

Unlock all answers in this set

Unlock answers
question
Monitoring
answer
Collecting, recording, and reporting information concerning any and all aspects of project performance
question
Controlling
answer
Uses the data supplied by monitoring to bring actual performance into compliance with the plan
question
Evaluation
answer
Judgments regarding the quality and effectiveness of project performance
question
Data Involves
answer
Frequency counts Raw numbers Subjective numeric ratings Indicators Verbal measures
question
Routine
answer
Reports that are issued on a regular basis or each time the project reaches a milestone
question
Exception
answer
Reports that are generated when an unusual condition occurs or as an informational vehicle when an unusual decision is made
question
Special Analysis
answer
Reports that result from studies commissioned to look into unexpected problems
question
Planning-Monitoring-Controlling Cycle
answer
* We mainly want to monitor: Time (schedule) Cost (budget) Scope (project performance) * Closed-loop system Revised plans and schedules following corrective actions
question
Earned Value Analysis
answer
* Actual against baseline ignores the amount of work accomplished * Earned value incorporates work accomplished * Multiply the estimated percent work complete for each task by the planned cost * Only need percent complete estimate for tasks currently in progress
question
EVA- 50/50 Rule
answer
50% percent completion is assumed when the task is begun, and the remaining 50 percent when the work is complete. This seems to be the most popular rule, probably because it is relatively fair and doesn't require the effort of attempting to estimate task progress.
question
EVA- 0-100 Rule
answer
This rule allows no credit for work until the task is complete. With this highly conservative rule, the project always seems to be running late, until the very end of the project when it appears to suddenly catch up. Consequently, the earned value line will always lag the planned value line on the graph.
question
Cost Variance (CV)
answer
CV = EV - AC Negative variance indicates a cost overrun Magnitude depends on the costs
question
Schedule Variance (SV)
answer
SV = EV - PV Negative variance indicates you are behind schedule Measured using costs
question
Time Variance (TV)
answer
TV = ST - AT Negative variance indicates you are behind schedule
question
Cost Performance Index
answer
CPI = EV/AC
question
Schedule Performance Index
answer
SPI = EV/PV
question
Time Performance Index
answer
TPI = ST/AT
question
Cost Schedule Index
answer
CSI = EV2/(AC)(PV)
question
ETC (estimated time to complete)=
answer
(BAC+EV)/CPI BAC= Budget at completion EV= Earned Value CPI= Cost Performance Index
question
EAC (estimated cost at completion)=
answer
ETC + AC ETC= Estimated time to complete AC= Amount expended to date (actual cost)
question
Three Types of Control Processes
answer
Cybernetic Control Go/no-go Control Post Control
question
Cybernetic Control
answer
* A system that is constantly monitored * When a deviation is spotted, corrective action is taken * Cybernetic controls are not common in projects * Negative feedback loop
question
Go/no-go Control
answer
* Testing to see if some preset condition has been met * Most of project management is go/no-go controls * Use cannot be based on the calendar - Some will take place at milestones - Some will take place when work packages are completed - Others will be on-going
question
Post Control
answer
* These are controls that are applied after the fact * Their purpose is to mainly improve the performance on future projects * Often times, a final report is prepared comparing the plan with reality * Sometimes called "lessons learned"
question
Characteristics of Control System
answer
* Flexible * Cost effective * Useful * Ethical * Timely * Accurate * Simple * Easy to maintain * Fully documented
question
Critical Ratio Control Chart
answer
Control Ratio = (AP/SP) x (BC/AC)
question
Physical Asset Control
answer
...
question
Phase-Gate
answer
* Controls the project at various points throughout its life cycle * Most commonly used for new product/service development projects * Project must pass gate to continue funding
question
Project Audit
answer
* A formal review of any aspect of a project * Audits focus on whatever matters senior management desires - Another type of audit is an ethics audit * Evaluate means to set the value of or appraise * Project evaluation appraises progress and performance against standard
question
Purposes of Project Audit
answer
* The main purpose of an audit is to help achieve the goals of the project * All facets of the project are studied * A project audit is equivalent to the application of TQM to project management
question
Approach to Project Audit
answer
*All facets of the project are studied * The strengths and weaknesses are identified * Recommendations are prepared to help current and future projects
question
Types of Audits
answer
* General Audit * Detailed Audit * Technical Audit
question
Audit Information
answer
1. Introduction 2. Current status 3. Future project status 4. Critical management issues 5. Risk management 6. Caveats, limitations, and assumptions
question
Responsibilities of Project Auditor
answer
* Be honest and ethical * Be independent * Tell the whole truth * Seek help for technical issues
question
Project Audit Life Cycle
answer
* Project audit initiation * Project baseline definition * Establishing an audit database * Preliminary analysis of the project * Audit report preparation * Project audit termination
question
Project Evaluation
answer
* Efficiency in meeting both the budget and the schedule * Customer impact/satisfaction * Business/direct success * Future potential
question
Termination by Extinction
answer
* Extinction occurs in any scenario where the project goes away -Successful -Unsuccessful -Changes in environment -Take too long -Murder * When work on a project stops, some organizational work continues
question
Termination by Addition
answer
* Applies to an in-house project * When the project is successful, it is institutionalized * While the project goes away, project personnel and assets are transferred to the new business
question
Termination by Integration
answer
* The most common way to terminate a project * The project comes into the business - It is absorbed into the existing structure *That structure absorbs the assets of the project
question
Termination by Starvation
answer
* Termination by starvation involves greatly reducing the budget of a project * Used when it is politically dangerous to cancel a project * Bad manners to enquire the status of the project
Get an explanation on any task
Get unstuck with the help of our AI assistant in seconds
New