Processes (Primary Outputs, order, knowledge area, process group) – Flashcards

141 test answers

Unlock all answers in this set

Unlock answers 141
question
Integration Management - #1
answer
Initiate - Develop Project Charter
question
Integration Management - #2
answer
Plan - Develop Project Management Plan
question
Integration Management - #3
answer
Execute - Direct & Manage Project Work
question
Integration Management - #4
answer
Monitor - Monitor & Control Project Work
question
Integration Management - #5
answer
Monitor - Perform Integrated Change Control
Unlock the answer
question
Integration Management - #6
answer
Closing - Close Project of Phase
Unlock the answer
question
Scope Management - #1
answer
Plan - Plan Scope Management
Unlock the answer
question
Scope Management - #2
answer
Plan - Collect Requirements
Unlock the answer
question
Scope Management - #3
answer
Plan - Define Scope
Unlock the answer
question
Scope Management - #4
answer
Plan - Create WBS
Unlock the answer
question
Scope Management - #5
answer
Monitor - Validate Scope
Unlock the answer
question
Scope Management - #6
answer
Monitor - Control Scope
Unlock the answer
question
Time Management - #1
answer
Plan - Plan Schedule Management
Unlock the answer
question
Time Management - #2
answer
Plan - Define Activities
Unlock the answer
question
Time Management - #3
answer
Plan - Sequence Activities
Unlock the answer
question
Time Management - #4
answer
Plan - Estimate Activity Resources
Unlock the answer
question
Time Management - #5
answer
Plan - Estimate Activity Durations
Unlock the answer
question
Time Management - #6
answer
Plan - Develop Schedule
Unlock the answer
question
Time Management - #7
answer
Monitor - Control Schedule
Unlock the answer
question
Cost Management - #1
answer
Plan - Plan Cost Management
Unlock the answer
question
Cost Management - #2
answer
Plan - Estimate Costs
Unlock the answer
question
Cost Management - #3
answer
Plan - Determine Budget
Unlock the answer
question
Cost Management - #4
answer
Monitor - Control Costs
Unlock the answer
question
Quality Management - #1
answer
Plan - Plan Quality Management
Unlock the answer
question
Quality Management - #2
answer
Execute - Perform Quality Assurance
Unlock the answer
question
Quality Management - #3
answer
Monitor - Control Quality
Unlock the answer
question
Human Resource Management - #1
answer
Plan - Plan Human Resource Management
Unlock the answer
question
Human Resource Management - #2
answer
Execute - Acquire Project Team
Unlock the answer
question
Human Resource Management - #3
answer
Execute - Develop Project Team
Unlock the answer
question
Human Resource Management - #4
answer
Execute - Manage Project Team
Unlock the answer
question
Communication Management - #1
answer
Plan - Plan Communications Management
Unlock the answer
question
Communication Management - #2
answer
Execute - Manage Communications
Unlock the answer
question
Communication Management - #3
answer
Monitor - Control Communications
Unlock the answer
question
Risk Management - #1
answer
Plan - Plan Risk Management
Unlock the answer
question
Risk Management - #2
answer
Plan - Identify Risks
Unlock the answer
question
Risk Management - #3
answer
Plan - Perform Qualitative Risk Analysis
Unlock the answer
question
Risk Management - #4
answer
Plan - Perform Quantitative Risk Analysis
Unlock the answer
question
Risk Management - #5
answer
Plan - Plan Risk Responses
Unlock the answer
question
Risk Management - #6
answer
Monitor - Monitoring and Control Risks
Unlock the answer
question
Procurement Management - #1
answer
Execute - Plan Procurement Management
Unlock the answer
question
Procurement Management - #2
answer
Monitor - Conduct Procurements
Unlock the answer
question
Procurement Management - #3
answer
Monitor - Control Procurements
Unlock the answer
question
Procurement Management - #4
answer
Closing - Close Procurements
Unlock the answer
question
Stakeholder Management - #1
answer
Plan - Identify Stakeholders
Unlock the answer
question
Stakeholder Management - #2
answer
Execute - Plan Stakeholder Management
Unlock the answer
question
Stakeholder Management - #3
answer
Monitor - Manage Stakeholder Engagements
Unlock the answer
question
Stakeholder Management - #4
answer
Monitor - Control Stakeholder Engagements
Unlock the answer
question
Develop Project Charter - Primary Output(s)
answer
Project Charter
Unlock the answer
question
Develop Project Management Plan - Primary Output(s)
answer
Project Management Plan
Unlock the answer
question
Direct & Manage Project Work - Primary Output(s)
answer
Deliverables, Work Performance Information, Change Requests
Unlock the answer
question
Monitor & Control Project Work - Primary Output(s)
answer
Change Requests
Unlock the answer
question
Perform Integrated Change Control - Primary Output(s)
answer
Approved Change Requests, Change Log
Unlock the answer
question
Close Project of Phase - Primary Output(s)
answer
Final Product, Service, or Result Transition
Unlock the answer
question
Plan Scope Management - Primary Output(s)
answer
Scope Management Plan, Requirements Management Plan
Unlock the answer
question
Collect Requirements - Primary Output(s)
answer
Requirements Documentation, Requirements Traceability Matrix
Unlock the answer
question
Define Scope - Primary Output(s)
answer
Project Scope Statement
Unlock the answer
question
Create WBS - Primary Output(s)
answer
Scope Baseline (Project Scope Statement, WBS, WBS Dictionary)
Unlock the answer
question
Validate Scope - Primary Output(s)
answer
Accepted Deliverables
Unlock the answer
question
Control Scope - Primary Output(s)
answer
(Scope) Change Requests
Unlock the answer
question
Plan Schedule Management - Primary Output(s)
answer
Schedule Management Plan
Unlock the answer
question
Define Activities - Primary Output(s)
answer
Activity List
Unlock the answer
question
Sequence Activities - Primary Output(s)
answer
Project Schedule Network Diagrams
Unlock the answer
question
Estimate Activity Resources - Primary Output(s)
answer
Activity Resource Requirements, Resource Breakdown Structure
Unlock the answer
question
Estimate Activity Durations - Primary Output(s)
answer
Activity Duration Estimates
Unlock the answer
question
Develop Schedule - Primary Output(s)
answer
Project Schedule, Schedule Baseline
Unlock the answer
question
Control Schedule - Primary Output(s)
answer
Work Performance Measurements, Change Requests
Unlock the answer
question
Plan Cost Management - Primary Output(s)
answer
Cost Management Plan
Unlock the answer
question
Estimate Costs - Primary Output(s)
answer
Activity Cost Estimates, Basis of Estimates
Unlock the answer
question
Determine Budget - Primary Output(s)
answer
Cost Baseline, Project Funding Requirements
Unlock the answer
question
Control Costs - Primary Output(s)
answer
Work Performance Information, Cost Forecasts, Change Requests, Project Management Plan updates,
Unlock the answer
question
Plan Quality Management - Primary Output(s)
answer
Quality management plan, quality checklist, quality metrics
Unlock the answer
question
Perform Quality Assurance - Primary Output(s)
answer
Change requests
Unlock the answer
question
Control Quality - Primary Output(s)
answer
Change requests, quality control measurements, validated changes, validated deliverables, work performance information
Unlock the answer
question
Plan Human Resource Management - Primary Output(s)
answer
Human Resource Plan
Unlock the answer
question
Acquire Project Team - Primary Output(s)
answer
Project Staff Assignment, Resource Calendars
Unlock the answer
question
Develop Project Team - Primary Output(s)
answer
Team Performance Assessments
Unlock the answer
question
Manage Project Team - Primary Output(s)
answer
Change Requests
Unlock the answer
question
Plan Communications Management - Primary Output(s)
answer
Communication Management Plan
Unlock the answer
question
Manage Communications - Primary Output(s)
answer
Project Communications
Unlock the answer
question
Control Communications - Primary Output(s)
answer
Work Performance Information, Change Requests
Unlock the answer
question
Plan Risk Management - Primary Output(s)
answer
Risk Management Plan
Unlock the answer
question
Identify Risks - Primary Output(s)
answer
Risk Register
Unlock the answer
question
Perform Qualitative Risk Analysis - Primary Output(s)
answer
Risk Register Updates, Assumption Log updates
Unlock the answer
question
Perform Quantitative Risk Analysis - Primary Output(s)
answer
Risk Register Updates
Unlock the answer
question
Plan Risk Responses - Primary Output(s)
answer
Project Management Plan Updates, Project Document Updates
Unlock the answer
question
Monitoring and Control Risks - Primary Output(s)
answer
Work Performance Information, Change Requests, Project Management Plan Updates, Project Document Updates
Unlock the answer
question
Plan Procurement Management - Primary Output(s)
answer
Procurement Management Plan, Procurement Statement of Work, Source Selection Criteria, Make-or-Buy Decisions
Unlock the answer
question
Conduct Procurements - Primary Output(s)
answer
Selected Sellers, Agreements, Resource Calendars,
Unlock the answer
question
Control Procurements - Primary Output(s)
answer
Work Performance Information, Change Requests
Unlock the answer
question
Close Procurements - Primary Output(s)
answer
Closed Procurements, Organizational Process Assets Updates
Unlock the answer
question
Identify Stakeholders - Primary Output(s)
answer
Stakeholder register
Unlock the answer
question
Plan Stakeholder Management - Primary Output(s)
answer
Stakeholder management plan
Unlock the answer
question
Manage Stakeholder Engagements - Primary Output(s)
answer
Issue log, Change requests
Unlock the answer
question
Control Stakeholder Engagements - Primary Output(s)
answer
Work performance information, Change requests
Unlock the answer
question
Knowledge Area and Process Group for - Develop Project Charter
answer
Integration Management - #1 - Initiate
Unlock the answer
question
Knowledge Area and Process Group for - Develop Project Management Plan
answer
Integration Management - #2 - Plan
Unlock the answer
question
Knowledge Area and Process Group for - Direct & Manage Project Work
answer
Integration Management - #3 - Execute
Unlock the answer
question
Knowledge Area and Process Group for - Monitor & Control Project Work
answer
Integration Management - #4 - Monitor
Unlock the answer
question
Knowledge Area and Process Group for - Perform Integrated Change Control
answer
Integration Management - #5 - Monitor
Unlock the answer
question
Knowledge Area and Process Group for - Close Project of Phase
answer
Integration Management - #6 - Closing
Unlock the answer
question
Knowledge Area and Process Group for - Plan Scope Management
answer
Scope Management - #1 - Plan
Unlock the answer
question
Knowledge Area and Process Group for - Collect Requirements
answer
Scope Management - #2 - Plan
Unlock the answer
question
Knowledge Area and Process Group for - Define Scope
answer
Scope Management - #3 - Plan
Unlock the answer
question
Knowledge Area and Process Group for - Create WBS
answer
Scope Management - #4 - Plan
Unlock the answer
question
Knowledge Area and Process Group for - Validate Scope
answer
Scope Management - #5 - Monitor
Unlock the answer
question
Knowledge Area and Process Group for - Control Scope
answer
Scope Management - #6 - Monitor
Unlock the answer
question
Knowledge Area and Process Group for - Plan Schedule Management
answer
Time Management - #1 - Plan
Unlock the answer
question
Knowledge Area and Process Group for - Define Activities
answer
Time Management - #2 - Plan
Unlock the answer
question
Knowledge Area and Process Group for - Sequence Activities
answer
Time Management - #3 - Plan
Unlock the answer
question
Knowledge Area and Process Group for - Estimate Activity Resources
answer
Time Management - #4 - Plan
Unlock the answer
question
Knowledge Area and Process Group for - Estimate Activity Durations
answer
Time Management - #5 - Plan
Unlock the answer
question
Knowledge Area and Process Group for - Develop Schedule
answer
Time Management - #6 - Plan
Unlock the answer
question
Knowledge Area and Process Group for - Control Schedule
answer
Time Management - #7 - Monitor
Unlock the answer
question
Knowledge Area and Process Group for - Plan Cost Management
answer
Cost Management - #1 - Plan
Unlock the answer
question
Knowledge Area and Process Group for - Estimate Costs
answer
Cost Management - #2 - Plan
Unlock the answer
question
Knowledge Area and Process Group for - Determine Budget
answer
Cost Management - #3 - Plan
Unlock the answer
question
Knowledge Area and Process Group for - Control Costs
answer
Cost Management - #4 - Monitor
Unlock the answer
question
Knowledge Area and Process Group for - Plan Quality Management
answer
Quality Management - #1 - Plan
Unlock the answer
question
Knowledge Area and Process Group for - Perform Quality Assurance
answer
Quality Management - #2 - Execute
Unlock the answer
question
Knowledge Area and Process Group for - Control Quality
answer
Quality Management - #3 - Monitor
Unlock the answer
question
Knowledge Area and Process Group for - Plan Human Resource Management
answer
Human Resource Management - #1 - Plan
Unlock the answer
question
Knowledge Area and Process Group for - Acquire Project Team
answer
Human Resource Management - #2 - Execute
Unlock the answer
question
Knowledge Area and Process Group for - Develop Project Team
answer
Human Resource Management - #3 - Execute
Unlock the answer
question
Knowledge Area and Process Group for - Manage Project Team
answer
Human Resource Management - #4 - Execute
Unlock the answer
question
Knowledge Area and Process Group for - Plan Communications Management
answer
Communication Management - #1 - Plan
Unlock the answer
question
Knowledge Area and Process Group for - Manage Communications
answer
Communication Management - #2 - Execute
Unlock the answer
question
Knowledge Area and Process Group for - Control Communications
answer
Communication Management - #3 - Monitor
Unlock the answer
question
Knowledge Area and Process Group for - Plan Risk Management
answer
Risk Management - #1 - Plan
Unlock the answer
question
Knowledge Area and Process Group for - Identify Risks
answer
Risk Management - #2 - Plan
Unlock the answer
question
Knowledge Area and Process Group for - Perform Qualitative Risk Analysis
answer
Risk Management - #3 - Plan
Unlock the answer
question
Knowledge Area and Process Group for - Perform Quantitative Risk Analysis
answer
Risk Management - #4 - Plan
Unlock the answer
question
Knowledge Area and Process Group for - Plan Risk Responses
answer
Risk Management - #5 - Plan
Unlock the answer
question
Knowledge Area and Process Group for - Monitoring and Control Risks
answer
Risk Management - #6 - Monitor
Unlock the answer
question
Knowledge Area and Process Group for - Plan Procurement Management
answer
Procurement Management - #1 - Execute
Unlock the answer
question
Knowledge Area and Process Group for - Conduct Procurements
answer
Procurement Management - #2 - Monitor
Unlock the answer
question
Knowledge Area and Process Group for - Control Procurements
answer
Procurement Management - #3 - Monitor
Unlock the answer
question
Knowledge Area and Process Group for - Close Procurements
answer
Procurement Management - #4 - Closing
Unlock the answer
question
Knowledge Area and Process Group for - Identify Stakeholders
answer
Stakeholder Management - #1 - Plan
Unlock the answer
question
Knowledge Area and Process Group for - Plan Stakeholder Management
answer
Stakeholder Management - #2 - Execute
Unlock the answer
question
Knowledge Area and Process Group for - Manage Stakeholder Engagements
answer
Stakeholder Management - #3 - Monitor
Unlock the answer
question
Knowledge Area and Process Group for - Control Stakeholder Engagements
answer
Stakeholder Management - #4 - Monitor
Unlock the answer
Get an explanation on any task
Get unstuck with the help of our AI assistant in seconds
New