POM Chapter 3: Project Management – Flashcards

Unlock all answers in this set

Unlock answers
question
The 3 phases the management of a project
answer
1. planning 2. scheduling 3. controlling
question
project organization
answer
an organization formed to ensure that programs receive the proper management and attention
question
project organization is most helpful when
answer
1. tasks can be defined with a goal and deadline 2. job is unique or unfamiliar to the organization 3. work requires specialized skills 4. project is temporary but critical 5. project cuts across organizational lines
question
the 4 responsibilities of a project manager
answer
1.on time 2. within budget 3. meets quality goals 4. people assigned receive the motivation, direction, and information needed for jobs
question
the for ethical issues project managers face
answer
1. offer of gifts form contractor 2. pressure to alter status reports to mask the reality of delays 3. false reports for charges of time and expenses 4. pressures to compromise quality to meet bonuses or avoid penalties related to schedules
question
work breakdown structure (WBS)
answer
a hierarchical description of a project into more and more detailed components
question
Gantt Charts
answer
planning charts used to schedule resources and allocate time and require 4 things 1. activities are planned 2. order of performance is documented 3. activity time estimates are recorded 4. overall project time is developed
question
the downside to Gantt charts
answer
they do not adequately illustrate the interrelationships between the activities and the resources
question
the 4 things project scheduling serves
answer
1. shows the relationship of activities to others and the whole project 2. identifies the precedence relationships 3. encourages setting of realistic time and cost estimates 4. helps make better use of people, money, and material resources
question
Program evaluation and review technique (PERT)
answer
a project management technique that employs three times estimates for each activity
question
Critical path
answer
the coupled longest time paths throughout a network
question
critical path method (CPM)
answer
a project management technique that uses only time factor per activity
question
the 6 basic steps of PERT and CPM
answer
1. define the project and prepare the work breakdown structure 2. develop the relationship among the activities. decide which activities must precede and which must follow others 3. draw the network connecting all the activities 4. assign time and/or cost estimates to each activity 5. compute the longest time path through that network. this is call the critical path 6. use the network to help plan, schedule, monitor, and control the project
question
activity on node (AON)
answer
a network diagram in which nodes designate activities
question
activity on narrow (AOA)
answer
a network diagram in which arrow designate activities
question
the 2 approaches for drawing a project network
answer
1. AON 2. AOA
question
critical path analysis
answer
a process that helps determine a project schedule
question
forward pass
answer
a process that identifies all the early times
question
earliest start time rule
answer
before an activity can start, all its immediate predecessor must be finished
question
earliest finish time rule
answer
the earliness finish time of an activity is the sum of its earliest start time and its activity time
question
backward pass
answer
an activity that finds all the late start and finish times
question
latest finish time rule
answer
this rule is again based on the fact that before an activity can start, all its immediate predecessors must be finished
question
lastest start time rule
answer
the difference of its latest finish time and its activity time
question
slack time
answer
free time for an activity. also referred to as free float or free attack
question
the 2 formulas for slack
answer
ls-es or lf-ef
question
the 3 time estimates in PERT
answer
1. optimistic time 2. pessimistic time 3. most likely time
question
optimistic time
answer
the best activity completion time that could be obtained in a PERT network
question
pessimistic time
answer
the worst activity time that could be expected in a PERT network
question
most likely time
answer
the most probable time to complete an activity
question
crashing
answer
shortening activity time in a network to reduce time on the critical path so total completion time is reduced
question
when we choose activities to crash we must consider the following
answer
1. the amount by which an activity is crashed is, in fact, permissible 2. taken together, the shortened activity durations will enable us to finish the project by the due date 3. the total cost of crashing is as small as possible
question
the four steps to crashing
answer
1. compute the crash cost per week 2. using the current activity times, find the critical path in the project network and identify the critical activities 3. select the activity on this critical path that can still be crashed and the smallest crash cost per period 4. update all activity times
question
the 7 advantages of PERT and CPM
answer
1. useful when scheduling and controlling large projects 2. straightforward 3. helps highlight relationships among project activities 4. critical path and slack time analyses help pinpoint activities that need to be watched 5. points out who is responsible for various activities 6. applicable to a wide variety of projects 7. useful in monitoring schedules but costs
question
the 4 limitations of PERT and CPM
answer
1. project activities must be defined, independent, and in stable relationships 2. relationships must be specific and networked together 3. time estimates tend to be subjective and are subject to fudging by managers 4. there is danger in placing too much emphasis on the critical path
Get an explanation on any task
Get unstuck with the help of our AI assistant in seconds
New