PMstudy Process Chart – Flashcards

Unlock all answers in this set

Unlock answers
question
Name the 10 Knowledge Areas
answer
1. Integration 2. Scope 3. Time 4. Cost 5. Quality 6. Human Resource 7. Communications 8. Risk 9. Procurement 10. Stakeholder I-S-T-C-Q-H-C-R-P-S I See Tigers Chomp Quality Hairy Chimps Resting Pool-Side
question
Name the Process Groups
answer
1. Initiating 2. Planning 3. Executing 4. Monitoring & Controlling 5. Closing I-P-E-M-C I Pee Exotic Multi Colors
question
All ______ are written in boxes.
answer
Processes
question
Processes in the Integration Area
answer
1. Initiating: Develop Project Charter 2. Planning: Develop Project Management Plan 3. Executing: Direct and Manage Project Work 4. Monitoring & Controlling: Monitor and Control Project Work 5. Monitoring & Controlling: Perform Integrated Change Control 6. Closing: Close Project or Phase
question
Processes in Scope Area
answer
1. Planning: Plan Scope Management 2. Planning: Collect Requirements 3. Planning: Define Scope 4. Planning: Create WBS 5. Monitoring & Controlling: Validate Scope 6. Monitoring & Controlling: Control Scope
question
Processes in Time Area
answer
Planning: Plan Schedule Management Planning: Define Activities Planning: Sequence Activities Planning: Estimate Activity Resources Planning: Estimate Activity Durations Planning: Develop Schedule Monitoring & Controlling: Control Schedule
question
Processes in Cost Area
answer
Planning: Plan Cost Management Planning: Estimate Costs Planning: Determine Budget Monitoring & Controlling: Control Costs
question
Processes in Quality
answer
Planning: Plan Quality Management Executing: Perform Quality Assurance Monitoring & Controlling: Control Quality
question
Processes in Human Resources
answer
Planning: Plan Human Resource Management Executing: Acquire Project Team Executing: Develop Project Team Executing: Manage Project Team
question
Processes in Communications
answer
Planning: Plan Communications Management Executing: Manage Communications Monitoring & Controlling: Control Communications
question
Processes in Risk
answer
Planning: Plan Risk Management Planning: Identify Risks Planning: Perform Qualitative Risk Analysis Planning: Perform Quantitative Risk Analysis Planning: Plan Risk Responses Monitoring & Controlling: Control Risks
question
Processes in Procurement
answer
Planning: Plan Procurement Management Executing: Conduct Procurement Monitoring & Controlling: Control Procurements Closing: Close Procurements
question
Processes in Stakeholder
answer
Initiating: Identify Stakeholders Planning: Plan Stakeholder Management Executing: Manage Stakeholder Engagement Monitoring & Controlling: Control Stakeholder Engagement
question
Acronym: PV
answer
Planned Value
question
Acronym: EV
answer
Earned Value
question
Acronym: AC
answer
Actual Cost
question
Acronym: BAC
answer
Budget At Completion
question
Acronym: SV Earned Value Formula:
answer
Scheduled Variance EV - PV
question
Acronym: CV Earned Value Formula:
answer
Cost Variance EV - AC
question
Acronym: SPI Earned Value Formula:
answer
Schedule Performance Index EV / PV
question
Acronym: CPI Earned Value Formula:
answer
Cost Performance Index EV / AC
question
Acronym: % Complete Earned Value Formula:
answer
Percent Complete (EV / BAC) * 100
question
Acronym: EAC Earned Value Formula(s):
answer
1. Estimating Assumptions not valid AC + ETC 2. Current Variances are atypical AC + BAC - EV 3. Current Variances are typical (DEFAULT) BAC / CPI
question
Acronym: ETC Earned Value Formula:
answer
Estimate to Complete EAC - AC
question
Acronym: VAC Earned Value Formula:
answer
Variance at Completion BAC - EAC
question
Acronym: TCPI Earned Value Formula(s):
answer
To-Complete Performance Index (Based on BAC) (BAC - EV) / (BAC - AC) To-Complete Performance Index (Based on EAC) (BAC - EV) / EAC - AC)
question
Acronym: AF Procurement Formula:
answer
AF = Actual Fee; TC = Target Cost; AC = Actual Cost; TF = Target Fee; SSR = Seller's Share Ratio { (TC - AC) SSR } + TF
question
Float
answer
LF - EF OR LS - ES
question
PERT
answer
(P + 4M + O) / 6 Std. Deviation = (P - O) / 6 Variance = { (P - O)/6 } sqr or SD sqr
question
Communication Channels
answer
N (N - 1) /2
question
EMV
answer
Probability * Impact
question
Present Value
answer
Future Value / (1 + r) raised t