Manufacturing Planning and Control for Supply Chain Management – Flashcards

Unlock all answers in this set

Unlock answers
question
Supporting information for material requirements planning (MRP) systems includes which of the following I. Bills of material II. Routing File III. Inventory status data
answer
I and III only
question
Material requirements planning (MRP) takes place in the front-end systems of the manufacturing planning and control system
answer
False
question
Material requirements planning (MRP) systems perform which of these functions? I. Translating the overall production plan into detailed steps II Providing information for capacity planning III. Providing information for staffing plans
answer
I and II only
question
In a material requirements planning (MRP) system, gross requirements are
answer
Anticipated future usage or demand for the item during each period
question
In a material requirements planning (MRP) system, the scheduled receipts are
answer
Existing replenishment orders for the item due at the beginning of each period
question
In material requirements planning (MRP) system, the projected available balance is
answer
Current and projected inventory status for the item at the end of the period
question
In a material requirements planning (MRP) system, gross requirements are time phased, which means which of the following
answer
Requirements from all periods are stated on a period-by-period basis
question
The precedent relationship shows
answer
The order in which production steps must be accomplished
question
Front scheduling logic starts each step of the process as late as possible
answer
False
question
Back scheduling logic starts each step of the process as late as possible
answer
True
question
A lot-for-lot order policy generates orders for a fixed quantity; independent of actual requirements
answer
False
question
Processing all material requirements planning (MRP) records in a single computer run is called
answer
Regeneration
question
Safety stock is an inventory buffer of stock over and above requirements
answer
True
question
Safety lead time involves inflating lead times to ensure stock availability
answer
False
question
In a system where timing of reduction is uncertain; it would be more appropriate to utilize
answer
Safety lead time
question
Information concerning the specific source of demand is called
answer
Pegging information
question
A firm planned order (FPO) can be changed by the material requirements planing (MRP) system without human involvement
answer
False
question
A commitment to an eternal supplier (e.g. a purchase order) is represented in the material requirements planning (MRP) system by a
answer
Scheduled receipt
question
Which of the following is not and action commonly taken by an MRP planner? I. Release orders II. Confirm inventory counts on incoming shipments III. Reconcile MRP errors
answer
II only
question
Order launching occurs when a planned order release is in the action bucket
answer
True
question
In a well-functioning material requirements planning (MRP) system, what percent of parts would be expected to require planner review (via exception codes) in any given processing cycle?
answer
10-20%
question
Exception codes are usually generated for which of the following reasons? I.Open order timing/ amount not satisfactory II. Need for management intervention III. Generation of planned orders
answer
I and II only
question
What is the primary consideration when selecting a lot-sizing procedure?
answer
The nature of the net requirements data
question
Material requirements planning (MRP) lot-sizing procedures are specifically designed for situations where demand is continous
answer
False
question
Material requirements planning (MRP) lot-sizing assumptions include which of the following? I. All requirements for a given period are available at the beginning of that period II. Ordering decision occur at regular time intervals III.Demand for future periods can be backordered
answer
I and II only
question
Which of the following are potential sources of uncertainty in a material requirements planning (MRP) system? I. Customer name II. Supply timing III. Demand quantity
answer
II and III only
question
In a situation where the main source of uncertainty is due to timing of customer orders, which buffering strategy would be expected to perform best?
answer
Safety lead time
question
In a situation where the main source of uncertainty is due to quantity of demand, which buffering strategy would be expected to perform best
answer
Safety stock
question
Material requirements planning (MRP) system nervousness can be attributed to which of the following? I. Unplanned demand II. MRP parameter errorss III. Firm planned orders
answer
I and II only
question
Which of the following strategies can be useful in reducing material requirements planning (MRP) system nervousness? I. Introducing system stability through time fences II. Careful use of lot-sizing procedures III. Using firm planned orders
answer
I, II, and III
question
When capacity does not match the plan, which of the following actions can be taken? I. Provide sufficient capacity II. Change the material plan III. Modify capacity calculations
answer
I and II only
question
Which of the following is an objective of capacity planning? I. Building excess capacity for possible future use II. Estimating capacity requirements early enough to take action if necessary III. Execution of the plan to avoid surprises
answer
I and III only
question
Which capacity planning activities are considered short-range planning?
answer
Finite loading and input/output anallysis
question
Resource planning is most closely linked to which manufacturing planning and control (MPC) element?
answer
Sales and operation planning (SOP)
question
Capacity requirements planning (CRP) is most closely linked to which manufacturing planning and control (MPC) element?
answer
Detailed material planning
question
Which capacity planning technique is based on accounting and/ or historical data?
answer
Capacity planning using overall factors (CPOF)
question
The capacity requirements using overall factors (CPOF) planning method is likely to function poorly in a just-in-time (JIT) environment
answer
False
question
The capacity bill planning technique provides more direct linkages to end products than does the capacity requirements using overall factors (CPOF) planning method.
answer
True
question
Under what conditions are both capacity requirements using overall factors (CPOF) and capacity bills likely to return the same capacity requirement results?
answer
When planning for a single product that is produced in a single work center
question
Resource profile planning differs from capacity requirements using overall factors (CPOF) and capacity bills by considering which of the following?
answer
Projected workload in individual work centers
question
In which of the following ways does capacity requirements planning (CRP) differ from rough-cut capacity planning techniques? I. CRP uses a time-phased approach II. CRP considers service part demand III. CRP considers standard lot sizes
answer
I and II only
question
Capacity requirements planning (CRP) ignores current finished goods and work-in-process inventory levels.
answer
False
question
Which of theses planning techniques requires the most computing resources?
answer
Capacity requirements planning (CRP)
question
Which of the following are benefits of simultaneous planning of capacity and materials? I Fewer computer resources required II. Better utilization of existing capacity III. Eliminates the need to expand capacity
answer
II only
question
Finite scheduling techniques always assign jobs to available capacity on a first-come, first- served basis.
answer
False
question
The horizontal loading scheduling approach is more likely to result in higher capacity utilization.
answer
True
question
The vertical loading scheduling approach is more likely to result in more complete jobs at the end of the planning cycle.
answer
True
question
Advanced production scheduling (APS) system time estimates, it is desirable to overstate the time estimate to allow some slack in the system.
answer
False
question
Input/output control compares
answer
Planned inputs and outputs to actual values
question
According to the theory of constraints (TOC), bottleneck work centers should be managed identically to non- bottlenecks.
answer
False
question
According to the theory of constraints (TOC), which of these conditions is most desirable? I. 100% utilization of bottleneck work centers II. 100% utilization of non-bottleneck work centers III. Less than 100% utilization of bottleneck work centers
answer
I only
question
Which of the following are useful measures of capacity? I. Machine- hours II. Labor- hours III. Elapsed time
answer
I and II only
question
Which of the following are capacities that may need to be managed? I. Direct labor II. Inspection III. Engineering
answer
I, II, and III
question
Rough-cut planning (CRP) can be used in firms that don't utilize material requirements planning (MRP).
answer
False
question
Input/output control is especially important at a firm that uses just-in-time (JIT) systems.
answer
False
Get an explanation on any task
Get unstuck with the help of our AI assistant in seconds
New