ISDS 3115 Exam 1 chapter 3 – Flashcards

Unlock all answers in this set

Unlock answers
question
Which of the following statements regarding Bechtel is true? a. Its competitive advantage is project management. b. Bechtel was the construction contractor for the Hoover Dam. c. While helping to rebuild Iraq, Bechtel's crews had to travel under armed escort. d. Bechtel's procurement program is global in nature. e. All of the above are true.
answer
e. All of the above are true.
question
Which of the following statements about Bechtel is true? a. Even though Bechtel is over 100 years old, the Kuwaiti oil fields was its first "project." b. Bechtel is the world's premier manager of massive construction and engineering projects. c. Bechtel's competitive advantage is supply chain management. d. While its projects are worldwide, its network of suppliers is largely in the U.S. e. All of the above are true.
answer
b. Bechtel is the world's premier manager of massive construction and engineering projects.
question
The phases of project management are a. planning, scheduling, and controlling b. planning, programming, and budgeting c. planning, organizing, staffing, leading, and controlling d. different for manufacturing projects than for service projects e. GANTT, CPM, and PERT
answer
a. planning, scheduling, and controlling
question
A project organization a. is effective for companies with multiple large projects b. is appropriate only in construction firms c. often fails when the project cuts across organizational lines d. is formed to ensure that programs (projects) get proper management and attention e. a and d are both true
answer
e. a and d are both true
question
Which of the following statements regarding project management is false? a. Gantt charts give a timeline for each of a project's activities, but do not adequately show the interrelationships of activities. b. A project organization works best for a project that is temporary but critical to the organization. c. Project organization works well when the work contains simple, independent tasks. d. Gantt charts and PERT/CPM are never used together. e. None of the above is true.
answer
c. Project organization works well when the work contains simple, independent tasks.
question
A code of ethics especially for project managers a. has been established by the Project Management Institute b. has been formulated by the Federal government c. has been formulated by the World Trade Organization d. is inappropriate, since everyone should use the same guidance on ethical issues e. does not exist at this time
answer
a. has been established by the Project Management Institute
question
Divulging information to some bidders on a project to give them an unfair advantage a. is the same thing as altering a status report b. is bribery c. is permitted by NAFTA d. is known as bid rigging e. is acceptable for private corporations but not for government agencies
answer
d. is known as bid rigging
question
Ethical issues that may arise in projects large and small include a. bid rigging b. expense account padding c. compromised safety or health standards d. bribery e. All of the above are true.
answer
e. All of the above are true.
question
Which of the following statements regarding Gantt charts is true? a. Gantt charts give a timeline and precedence relationships for each activity of a project. b. Gantt charts use the four standard spines of Methods, Materials, Manpower, and Machinery. c. Gantt charts are visual devices that show the duration of activities in a project. d. Gantt charts are expensive. e. All of the above are true.
answer
c. Gantt charts are visual devices that show the duration of activities in a project.
question
Which of the following statements regarding critical paths is true? a. The shortest of all paths through the network is the critical path. b. Some activities on the critical path may have slack. c. Every network has exactly one critical path. d. On a specific project, there can be multiple critical paths, all with exactly the same duration. e. The duration of the critical path is the average duration of all paths in the project network.
answer
d. On a specific project, there can be multiple critical paths, all with exactly the same duration.
question
Which of the following statements regarding CPM is true? a. The critical path is the shortest of all paths through the network. b. The critical path is that set of activities that has positive slack. c. Some networks have no critical path. d. All activities on the critical path have their LS equal their predecessor's EF. e. All of the above are false.
answer
d. All activities on the critical path have their LS equal their predecessor's EF.
question
A simple CPM network has three activities, A, B, and C. A is an immediate predecessor of B and of C. B is an immediate predecessor of C. The activity durations are A=4, B=3, C=8. a. The critical path is A-B-C, duration 15. b. The critical path is A-C, duration 12. c. The critical path is A-B-C, duration 13.5 d. The critical path cannot be determined without knowing PERT expected activity times. e. The network has no critical path.
answer
a. The critical path is A-B-C, duration 15.
question
A simple CPM network has three activities, D, E, and F. D is an immediate predecessor of E and of F. E is an immediate predecessor of F. The activity durations are D=4, E=3, F=8. a. The critical path is D-E-F, duration 15. b. The critical path is D-F, duration 12. c. Slack at D is 3 units d. Slack at E is 3 units e. Both a and c are true
answer
a. The critical path is D-E-F, duration 15.
question
A simple CPM network has five activities, A, B, C, D, and E. A is an immediate predecessor of C and of D. B is also an immediate predecessor of C and of D. C and D are both immediate predecessors of E. a. There are two paths in this network. b. There are four paths in this network. c. There are five paths in this network. d. There are 25 paths through this network. e. None of these statements is true.
answer
b. There are four paths in this network.
question
Activity D on a CPM network has predecessors B and C, and has successor F. D has duration 6. B's earliest finish is 18, while C's is 20. F's late start is 26. Which of the following is true? a. B is a critical activity. b. C is completed before B. c. D has no slack but is not critical. d. D is critical, and has zero slack. e. All of the above are true.
answer
d. D is critical, and has zero slack.
question
Which of the following statements regarding CPM networks is true? a. There can be multiple critical paths on the same project, all with different durations. b. The early finish of an activity is the latest early start of all preceding activities. c. The late start of an activity is its late finish plus its duration. d. If a specific project has multiple critical paths, all of them will have the same duration. e. All of the above are true.
answer
d. If a specific project has multiple critical paths, all of them will have the same duration.
question
Activity M on a CPM network has predecessors N and R, and has successor S. M has duration 5. N's late finish is 18, while R's is 20. S's late start is 14. Which of the following is true? a. M is critical and has zero slack. b. M has no slack but is not critical. c. The last start time of S is impossible. d. N is a critical activity. e. S is a critical activity.
answer
c. The last start time of S is impossible.
question
Which of the following statements concerning CPM activities is false? a. The early finish of an activity is the early start of that activity plus its duration. b. The late finish is the earliest of the late start times of all successor activities. c. The late start of an activity is its late finish less its duration. d. The late finish of an activity is the earliest late start of all preceding activities. e. The early start of an activity is the latest early finish of all preceding activities.
answer
d. The late finish of an activity is the earliest late start of all preceding activities.
question
The time an activity will take assuming very unfavorable conditions is a. the optimistic time b. the pessimistic time c. the activity variance d. the minimum time e. exactly twice as long as the expected time
answer
b. the pessimistic time
question
The _____ distribution is used by PERT analysis to calculate expected activity times and variances. a. Normal b. Beta c. Alpha d. Gaussian e. Binomial
answer
b. Beta
question
The expected activity time in PERT analysis is calculated as a. the simple average of the optimistic, pessimistic, and most likely times b. the weighted average of a, m, and b, with m weighted 4 times as heavily as a and b c. the sum of the optimistic, pessimistic, and most likely times d. the sum of the optimistic, pessimistic, and most likely times, divided by six e. the sum of the activity variances, divided by six
answer
b. the weighted average of a, m, and b, with m weighted 4 times as heavily as a and b
question
Which of the following statements regarding PERT times is true? a. The optimistic time estimate is an estimate of the minimum time an activity will require. b. The optimistic time estimate is an estimate of the maximum time an activity will require. c. The probable time estimate is calculated as t = (a + 4m + b). d. Pessimistic time estimate is an estimate of the minimum time an activity will require. e. Most likely time estimate is an estimate of the maximum time an activity will require.
answer
a. The optimistic time estimate is an estimate of the minimum time an activity will require.
question
Which of the following statements regarding PERT times is true? a. Expected time is an estimate of the time an activity will require if everything goes as planned. b. The optimistic time estimate is an estimate of the maximum time an activity will require. c. The probable time estimate is calculated as t = (a + 4m + b)/6. d. Pessimistic time estimate is an estimate of the minimum time an activity will require. e. Most likely time estimate is an estimate of the maximum time an activity will require.
answer
c. The probable time estimate is calculated as t = (a + 4m + b)/6
question
The Beta distribution is used in project management to a. calculate slack on activities not on the critical path b. calculate the probability that a project will be completed within its budget c. calculate pessimistic and optimistic activity times d. determine which activity should be crashed e. none of the above
answer
e. none of the above
question
The Beta distribution is used in project management to a. determine which activity should be crashed b. calculate the probability that a project will be completed within its budget c. calculate expected activity times d. calculate slack for activities on the critical path e. none of the above
answer
c. calculate expected activity times
question
In a PERT network, non-critical activities that have little slack need to be monitored closely a. because PERT treats all activities as equally important b. because near-critical paths could become critical paths with small delays in these activities c. because slack is undesirable and needs to be eliminated d. because they are causing the entire project to be delayed e. because they have a high risk of not being completed
answer
b. because near-critical paths could become critical paths with small delays in these activities
question
Which of the following statements regarding PERT analysis is true? a. Each activity has two estimates of its duration. b. Project variance is the sum of all activity variances. c. Project standard deviation is the sum of all critical activity standard deviations. d. Only critical activities contribute to the project variance. e. None of the above is true.
answer
d. Only critical activities contribute to the project variance.
question
Which of these statements regarding time-cost tradeoffs in CPM networks is true? a. Crashing is not possible unless there are multiple critical paths. b. Crashing a project often reduces the length of long-duration, but noncritical, activities. c. Activities not on the critical path can never be on the critical path, even after crashing. d. Crashing shortens the project duration by assigning more resources to one or more of the critical tasks. e. None of the above is true.
answer
d. Crashing shortens the project duration by assigning more resources to one or more of the critical tasks
question
What was the name of the construction project to rebuild the Pentagon after the terrorist attacks on Sept. 11, 2001? a. Project Panther b. Project Pit Bull c. Project Python d. Project Piranha e. Project Phoenix
answer
e. Project Phoenix
question
Which of the following statements regarding time-cost tradeoffs in CPM networks is false? a. "Project Crashing" shortens project duration by assigning more resources to critical tasks. b. Crashing sometimes has the reverse result of lengthening the project duration. c. Crashing must consider the impact of crashing an activity on all paths in the network. d. Activities not on the critical path can become critical after crashing takes place. e. All of the above are true.
answer
b. Crashing sometimes has the reverse result of lengthening the project duration.
question
A network has been crashed to the point where all activities are critical. Additional crashing a. is unnecessary b. is impossible c. is prohibitively expensive d. may require crashing multiple tasks simultaneously e. can be done, but all critical tasks must be reduced in duration
answer
d. may require crashing multiple tasks simultaneously
question
____________ is an organization formed to ensure that programs (projects) receive the proper management and attention.
answer
Project organization
question
_______________ divides a project into more and more detailed components.
answer
Work breakdown structure or WBS
question
The _______________ has established a code of ethics especially for project managers
answer
Project Management Institute
question
_______________ is a network technique using only one time factor per activity that enables managers to schedule, monitor, and control large and complex projects.
answer
Critical path method or CPM
question
A diagram of all activities and the precedence relationships that exist between these activities in a project is a(n) _____________.
answer
network
question
The ____________ is the computed longest time path(s) through a network.
answer
critical path
question
The network analysis method that allows activity times to vary is _____________.
answer
PERT or Program Evaluation and Review Technique
question
______________ is the amount of time an individual activity in a network can be delayed without delaying the entire project.
answer
Slack time
question
The ______________ distribution is appropriate for calculating expected activity times and activity variances in PERT networks.
answer
Beta
question
_____________ is decreasing activity time in a network to reduce time on the critical path so total completion time is reduced.
answer
Crashing