Project human resource management is concerned with making effective use of the people involved with a project.
answer
true
question
The enterprise project management software, which aids project and portfolio management, is a low-end tool.
answer
False
question
When you separate business and organizational issues from project management planning, you do a better job of ensuring project success.
answer
False
question
The team members of a virtual team are all of the same nationality.
answer
False
question
Leadership style has no impact on the success of virtual teams.
answer
False
question
Initiating processes take place during each phase of a project.
answer
True
question
Identifying the project sponsor is a pre-initiation task.
answer
True
question
The burndown chart is a Scrum created artifact that provides a list of features prioritized by business value.
answer
False
question
The ROI is always positive.
answer
False
question
The project scope statement, stakeholder requirements documentation, and organizational process assets are the primary inputs for creating a WBS.
answer
True
question
The scope baseline in a WBS consists of the requirements documentation and enterprise environmental factors.
answer
False
question
The tasks in a WBS must be developed as a sequential list of steps.
answer
False
question
When deciding what projects to invest in or continue, one should include sunk costs.
answer
False
question
A cost management plan can include organizational procedures links, control thresholds, and process descriptions.
answer
True
question
Definitive estimates are made one year or less prior to project completion.
answer
True
question
Project procurement management mainly involves:
answer
buying goods and services for a project from outside the performing organization.
question
Fast tracking is an example of a tool used in _____ management.
answer
time
question
A _____ is an organizational group responsible for coordinating the project management function throughout an organization.
answer
Project Management Office
question
Projects must operate in a broad organizational environment, and project managers need to consider projects within the greater organizational context. _____ describes this holistic view of carrying out projects within the context of the organization.
answer
Systems thinking
question
In a _____organizational structure, program managers, rather than functional managers or vice presidents, report to the CEO. Their staffs have a variety of skills needed to complete all required tasks within their programs.
answer
project
question
_____ processes include defining and authorizing a project or project phase.
answer
Initiating
question
Developing a _____ is a planning process that occurs in the Project Integration Management knowledge area.
answer
project management plan
question
The project stakeholder management knowledge area maps to the _____ process group by identifying stakeholders.
answer
initiating
question
Which of the following is true about the agile method?
answer
It uses several iterations or deliveries of software instead of waiting until the end of the project to provide a product.
question
The improvement of the product and process in the Scrum method is discussed at the _____.
answer
sprint reflection meeting
question
Payback occurs when:
answer
the net cumulative benefits equal the net cumulative costs.
question
The business case includes information on _____.
answer
the project objective, high-level requirements, and time and cost goals
question
An IT company revises its process parameters in response to complaints from vendors that products were not ready on time. This would be an example of _____.
answer
a corrective action
question
A(n) _____ is a deliverable-oriented grouping of the work involved in a project that defines the total scope of the project.
answer
work breakdown structure
question
The _____ approach for constructing a WBS involves refining the work into greater and greater levels of detail.
answer
top-down
question
A network diagramming technique in which boxes represent activities is known as a(n) _____.
answer
PDM
question
_____ states that work expands to fill the time allowed.
answer
Parkinson's Law
question
Work performance information and cost forecasts are main outputs of the _____ process.
answer
cost control
question
Profits may be defined as:
answer
revenues minus expenditures.
question
Indirect costs are:
answer
not directly related to the products or services of a project.
question
A rough order of magnitude estimate can be referred to as a _____ estimate.
answer
ballpark
question
Analogous estimates are also known as _____ estimates.
answer
top-down
question
Which of the following is true of analogous estimates?
answer
They are most reliable when previous projects are similar in fact with current projects.
question
The budget is one of the three values of earned value management and is also known as _____.
answer
planned value
question
Which of the following is true of earned value?
answer
It is an estimate of the value of the physical work actually completed.
question
"What is the project's budget?" This is an example of a project's _____ constraint.
answer
cost
question
In the _______ phase of the project life cycle, the work is completed, and customers should accept the entire project.
answer
close-out
question
________ are new requirements imposed by management, government, or some external influence.
answer
Directives
question
A(n) _____________ is a methodology that converts value drivers, such as customer service, innovation, operational efficiency, and financial performance, to a series of defined metrics.
answer
balanced scorecard
question
A category of software that can help align projects with business strategy is called ____________________ tools.
answer
Business Service Management (BSM)
question
____________ is the tendency for project scope to keep getting bigger and bigger.
answer
Scope Creep
question
One of the first reality checks on scheduling that a project manager should make is to review the ________________.
answer
draft schedule
question
In addition to providing input for budgetary estimates, the process of _______________ provides a cost baseline.
answer
cost budgeting
question
The ____________ is the portion of the approved total cost estimate planned to be spent on an activity during a given period.
answer
planned value
question
The total direct and indirect costs incurred in accomplishing work on an activity during a given period is known as the _______________.
answer
actual cost