FInal Exam SCMA 350 – Flashcards

Unlock all answers in this set

Unlock answers
question
The organization's leadership should establish the strategic objectives to set the stage for the strategic analysis.
answer
False
question
Project selection scoring models are very useful in providing performance data that can be used to terminate a project.
answer
False
question
The project scope refers to the features and functions that characterize a product, service or result
answer
False
question
The signing of the project portfolio statement signals the transition from the high-level project initiating stage into the more detailed project planning stage.
answer
False
question
The length of time to perform an activity is often dependent upon who will dependent upon who will do the work.
answer
True
question
Plan Risk Responses focuses on developing options and actions for every identified and
answer
False
question
The primary output of risk identification Matrix(RIM).
answer
False
question
W. Edwards Deming argued that managers must understand cause and effect relationships to predict future behavior.
answer
True
question
Typically, a steering team or leadership team is responsible for all of the following project related roles EXCEPT:
answer
providing rigid policies, procedures, standards and guidelines
question
Which of the following statements regarding project life cycles is most accurate?
answer
The control needs of an organization determine the name and number of phases in the project life cycle that it adopts.
question
There are several tasks that a project customer (or sponsor acting in that capacity) can do to enhance the probability of success. Which of the following are generally performed independent of the project contractor who will perform the work?
answer
Prioritize the project need
question
All of the following represent appropriate sources to identify new potential projects EXCEPT
answer
Lessons learned from previous projects.
question
There are several tasks that a project customer (or sponsor acting in that capacity) can do to enhance the probability of success. Which of the following are generally performed independent of the project contractor who will perform the work?
answer
Prioritze the project need.
question
All of the following represent appropriate sources to identify new potential projects EXCEPT:
answer
lessons learned from previous projects
question
All of the following items describe the project sponsor's responsibilities for the project EXCEPT
answer
selects a manageable set of projects to be implemented
question
Which of the following is a disadvantage associated with managing projects in a projectized organization?
answer
Team members assigned to a project are often underutilized.
question
Which of the following executive roles is responsible for overall priority setting, project selection and sponsor selection, as well as general guidance and encouragement?
answer
Steering Team
question
Subject matter experts often perform specific project activities when necessary. Which of the following statements accurately describes the role of subject matter experts in support of a project?
answer
The subject matter experts may not relate strongly with a project due to the temporary nature of their involvement.
question
Within the project charter, the scope overview accomplishes all of the following EXCEPT:
answer
documents the operating principles for the team
question
All of the following conventions are widely adopted when project teams create the second level of the project Work Breakdown Structure (WBS) EXCEPT:
answer
The second level may be organized by activities and tasks
question
Consider the network scheduling data presented above. How many days of slack are associated with activity F?
answer
80
question
Formally documented procedures that define how project deliverables and documentation will be controlled, changed and approved are collectively known by which of the following terms?
answer
A change control system
question
Consider the network scheduling data provided above. Which activities constitute the critical path for this project network?
answer
A-B-E-G-I
question
The project communications matrix lists important "who," "what" and "when" items that must be considered in planning for project communications. All of the following "who" items are typically included in the project communications matrix EXCEPT:
answer
Who take the minutes at the next status meeting
question
Consider the System Integration Project depicted above. Based on the information provided, which activities can be delayed one day without impacting the expected project completion date?
answer
Activity C - Purchase Software and Activity D - Prepare Test Plan
question
All of the following methods have proven to be useful techniques to help project teams identify the risks that might impact the project EXCEPT:
answer
deriving lessons learned
question
All of the following describe an appropriate application of Plan Risk Responses in project management EXCEPT:
answer
Responses should be created for every identified project risk
question
Fact-based management includes four key ideas. Which of the following is among the key ideas associated with fact-based management?
answer
the need to understand variation
question
Which of the following quantitative risk analysis techniques relies upon the calculation of net present value to determine if a project should be pursued or abandoned?
answer
Financial Engineering
question
Which of the following describes the appropriate use of a cause and effect diagram to support project risk analysis?
answer
It is often easier to alter the effect by changing the underlying cause.
question
Which of the following activities illustrates a risk response strategy designed to research a threat or an opportunity?
answer
adopt a prototype to learn more about a candidate solution
question
The components (principles) of Critical Chain Project Management include which of the following?
answer
Avoid multi-tasking
Get an explanation on any task
Get unstuck with the help of our AI assistant in seconds
New