question
_____ refers to the difference between planned and actual performance.
answer
Variance
question
The scope baseline in a WBS consists of the requirements documentation and enterprise environmental factors.
answer
False The scope baseline includes the approved project scope statement and its associated WBS and WBS dictionary.
question
_____ involves reviewing the project charter, requirements documents, and organizational process assets to create a scope statement, adding more information as requirements are developed and change requests are approved.
answer
Defining scope
question
Scope refers to all the work involved in creating the products of the project and the processes used to create them.
answer
True One of the most important and most difficult aspects of project management is defining the scope of a project. Scope refers to all the work involved in creating the products of the project and the processes used to create them.
question
The scope management plan can be informal and broad or formal and detailed, based on the needs of the project.
answer
True
question
The main technique used in creating a WBS is _____, which involves subdividing project deliverables into smaller pieces.
answer
decomposition
question
Scope refers to:
answer
the work involved in creating the products and the processes used to create them.
question
The scope of a project is clear and specific from the start.
answer
False
question
_____ uses highly organized and intensive workshops to bring together project stakeholders—the sponsor, users, business analysts, programmers, and so on—to jointly define and design information systems.
answer
JAD
question
A(n) _____ is a table that lists requirements, their various attributes, and the status of the requirements to ensure that all are addressed.
answer
requirements traceability matrix A requirements traceability matrix (RTM) is a table that lists requirements, their various attributes, and the status of the requirements to ensure that all are addressed.
question
The _____ technique for creating a WBS uses branches radiating from a core idea to structure thoughts and ideas instead of writing down tasks in a list or immediately trying to create a structure for tasks.
answer
mind mapping Mind mapping is a technique that uses branches radiating from a core idea to structure thoughts and ideas.Instead of writing down tasks in a list or immediately trying to create a structure for tasks, mind mapping allows people to write and even draw pictures of ideas in a nonlinear format.
question
The _____ approach for constructing a WBS involves refining the work into greater and greater levels of detail.
answer
top-down
question
Many organizations provide different guidelines and templates for developing WBSs.
answer
True
question
Scope creep refers to:
answer
the tendency for project scope to keep getting bigger and bigger.
question
Project scope statements must include the project boundaries, constraints, and assumptions.
answer
False Project scope statements should include at least a product scope description, product user acceptance criteria, and detailed information on all project deliverables. It is also helpful to document other scope-related information, such as the project boundaries, constraints, and assumptions.
question
The project scope statement, stakeholder requirements documentation, and organizational process assets are the primary inputs for creating a WBS.
answer
True
question
The _____ approach for constructing a WBS starts with the largest items of the project and breaks them into subordinate items.
answer
top-down
question
In the _____ approach, team members first identify as many specific tasks related to the project as possible and then aggregate the specific tasks and organize them into summary activities, or higher levels in the WBS.
answer
bottom-up In the bottom-up approach, team members first identify as many specific tasks related to the project as possible. They then aggregate the specific tasks and organize them into summary activities, or higher levels in the WBS. Project managers often use the bottom-up approach for projects that represent entirely new systems or approaches to doing a job, or to help create buy-in and synergy with a project team.
question
_____ involves formal acceptance of the completed project scope by the stakeholders.
answer
Scope validation
question
A work package represents one component of the product that the project aims to deliver.
answer
False A work package is a task at the lowest level of the WBS. It represents the level of work that the project manager monitors and controls.
question
The tasks in a WBS must be developed as a sequential list of steps.
answer
False A concern when creating a WBS is how to organize it to provide the basis for the project schedule. You should focus on what work needs to be done and how it will be done, not when it will be done. In other words, the tasks do not have to be developed as a sequential list of steps.
question
The WBS is organized solely around project phases.
answer
False A project team often organizes the WBS around project products, project phases, or the project management process groups.
question
_____ refers to the process of developing a working replica of the system or some aspect of the system.
answer
Prototyping
question
The executing tasks of the WBS remain constant from project to project.
answer
False The executing tasks vary the most from project to project, but many of the tasks under the other project management process groups would be similar for all projects.
question
Deliverables are only product-related, such as a piece of hardware or software.
answer
False Deliverables can be product-related, such as a piece of hardware or software, or process-related, such as a planning document or meeting minutes.
question
A similarity between the crashing technique and the fast tracking technique is that:
answer
both can shorten the time needed to finish a project.
question
_____ is the amount of time an activity can be delayed from its early start without delaying the planned project finish date.
answer
Total slack
question
In an AOA network diagram, _____ occur when two or more activities follow a single node.
answer
bursts
question
_____ dependencies are sometimes referred to as soft logic and should be used with care because they may limit later scheduling options.
answer
Discretionary
question
A disadvantage of using Gantt charts is that they do not provide a standard format for displaying planned project schedule information.
answer
False The main advantage of using Gantt charts is that they provide a standard format for displaying planned and actual project schedule information.
question
Start-to-finish relationships are the most frequently used dependencies between activities.
answer
False One of the four types of dependencies or relationships between activities is the start-to-finish dependency. This is a relationship in which the "from " activity must start before the "to" activity can be finished. This type of relationship is rarely used, but it is appropriate in some cases.
question
Which of the following dependencies involve relationships between project and non-project activities?
answer
External
question
Which of the following is one of the main outputs of estimating activity resources process?
answer
Project documents update
question
The main disadvantage of crashing is that it lengthens the time needed to finish a project.
answer
False The main advantage of crashing is that it shortens the time needed to finish a project. The main disadvantage is that it often increases total project costs.
question
The technique of fast tracking can result in lengthening the project schedule.
answer
True The main disadvantage of fast tracking is that it can lengthen the project schedule because starting some tasks too soon often increases project risk and results in rework.
question
AOA network diagrams use only _____ dependencies.
answer
finish-to-start
question
Knowing the amount of float allows project managers to know whether a project schedule is flexible.
answer
True Knowing the amount of float or slack allows project managers to know whether the schedule is flexible and how flexible it might be. A fast and easy way to determine early and late start and finish dates and free and total slack amounts for activities is by using project management software.
question
Critical chain scheduling protects tasks on the critical chain from being delayed by using _____, which consist of additional time added before tasks on the critical chain that are preceded by non-critical-path tasks.
answer
feeding buffers
question
The final process in project time management is developing the schedule.
answer
False The final process in project time management is controlling the schedule Like scope control, schedule control is a portion of the integrated change control process under project integration management.
question
In a critical path analysis, the shortest path is what drives the completion date for the project.
answer
False In a critical path analysis, several tasks are done in parallel on projects, and most projects have multiple paths through a network diagram. The longest path or the path that contains the critical tasks is what drives the completion date for the project.
question
Which of the following is an output of schedule control?
answer
Lessons-learned reports
question
In project time management, which of the following processes primarily involve identifying and documenting the relationships between project activities?
answer
Sequencing activities
question
In project time management, a(n) _____ is an output of controlling the schedule
answer
project management plan update
question
A dependency pertains to the sequencing of project activities or tasks.
answer
True A dependency or relationship pertains to the sequencing of project activities or tasks. Determining these relationships or dependencies among activities has a significant impact on developing and managing a project schedule.
question
The first process involved in project time management is _____ .
answer
planning schedule management
question
A drawback of the precedence diagramming method is that it cannot be used unless dummy activities are employed.
answer
False The precedence diagramming method offers a number of advantages over the AOA technique. One advantage is that using this method avoids the need to use dummy activities.
question
A backward pass through the network diagram determines the early start and early finish dates for each activity.
answer
False A backward pass through the network diagram determines the late start and late finish dates for each activity. In contrast, a forward pass determines the early start and early finish dates for each activity.
question
In project time management, the main goal of _____ is to ensure that the project team has complete understanding of all the work they must do as part of the project scope so they can start scheduling the work.
answer
defining activities
question
Network diagrams are the preferred technique for showing activity sequencing.
answer
True Network diagrams are the preferred technique for showing activity sequencing. A network diagram is a schematic display of the logical relationships among project activities and their sequencing.
question
Project schedules grow out of basic documents such as the project charter.
answer
True Project schedules grow out of the basic documents that initiate a project. The project charter often mentions planned project start and end dates, which serve as the starting points for a more detailed schedule.
question
In a bottom-up estimate, the size of the individual work items is one of the factors that drives the accuracy of the estimates.
answer
True The size of the individual work items and the experience of the estimators drive the accuracy of the estimates. Using smaller work items increases the accuracy of the cost estimate because the people assigned to do the work develop the cost estimate instead of someone unfamiliar with the work.
question
Good Earth, a company manufacturing packaged food products, sets up its stores in Baltonia. However, a year later, the company closes the store down due to high operating costs. In such a scenario, the money spent in paying for the rent of the store in Baltonia would be an example of _____ costs.
answer
sunk
question
Newtech Inc. hires John for the position of a software programmer to work on their new project. Salary paid to John by Newtech Inc. would be an example of _____ costs.
answer
direct
question
Spreadsheets are a common tool for cost estimating, cost budgeting, and cost control.
answer
True Most organizations use software to assist in various activities related to project cost management. Spreadsheets are a common tool for cost estimating, cost budgeting, and cost control.
question
If cost variance is a positive number, it means that performing the work costs more than planned.
answer
False Cost variance (CV) is the earned value minus the actual cost. If cost variance is a negative number, it means that performing the work costs more than planned. If cost variance is a positive number, performing the work costs less than planned.
question
Intangible costs can be easily measured in monetary terms.
answer
False Intangible costs or benefits are difficult to measure in monetary terms. Conversely, tangible costs or benefits can easily be measured in dollars.
question
The formulas for variances and indexes start with EV, the earned value.
answer
True The formulas for variances and indexes start with EV, the earned value. Variances are calculated by subtracting the actual cost or planned value from EV, and indexes are calculated by dividing EV by the actual cost or planned value.
question
Overrun is the additional percentage amount by which estimates exceed actual costs.
answer
False Overrun is the additional percentage or dollar amount by which actual costs exceed estimates.
question
The main goal of the _____ process is to produce a cost baseline for measuring project performance and project funding requirements.
answer
cost budgeting
question
When deciding what projects to invest in or continue, one should include sunk costs.
answer
False
question
Profits may be defined as:
answer
revenues minus expenditures.
question
Variances are calculated by subtracting the actual cost from _____.
answer
earned value
question
The process of controlling costs primarily involves:
answer
managing changes to the project budget.
question
IT project managers must be able to present and discuss project information both in financial and technical terms.
answer
True Most members of a company's executive board have a better understanding of financial terms than IT terms, and are more interested in finance. Therefore, IT project managers need to be able to present and discuss project information both in financial terms and technical terms.
question
One of the reasons why project cost estimates are inaccurate is because human beings are biased toward underestimation.
answer
True One of the reasons why project cost estimates are very inaccurate is because human beings are biased toward underestimation. It is thus important for project managers and top management to review estimates and ask important questions to make sure the estimates are not biased.
question
A _____ estimate is used for making many purchasing decisions for which accurate estimates are required and for estimating final project costs.
answer
definitive
question
Project managers must conduct cash flow analysis to determine net present value.
answer
True Cash flow analysis is a method of determining the estimated annual costs and benefits for a project and the resulting annual cash flow. Project managers must conduct cash flow analysis to determine net present value.
question
_____ are those costs that are difficult to measure in monetary terms.
answer
Intangible costs
question
Analogous estimates are called activity-based costing.
answer
False Analogous estimates are also called top-down estimates. Such estimates use the actual cost of a previous, similar project as the basis for estimating the cost of the current project.
question
_____ helps develop an accurate projection of a project's financial expenses and benefits.
answer
Life cycle costing
question
The budget is one of the three values of earned value management and is also known as _____.
answer
planned value
question
It is important for project managers to focus on indirect costs because they can be easily controlled.
answer
False Direct costs can be directly related to creating the products and services of the project. Project managers should focus on direct costs because they can be controlled.
question
The Level of Accuracy section of the cost management plan specifies rounding guidelines for the cost estimate (e.g. to the nearest $1,000).
answer
True
question
The Control Thresholds section of the cost management plan specifies the amount of cost variance that is allowed before action must be taken.
answer
True
question
The Rules of Performance Measurement section of the cost management plan may specify how often actual costs will be tracked and to what level of detail.
answer
True
question
The _____ stage of information technology planning outlines business processes that are central to achieving strategic goals and helps determine which ones could most benefit from information technology.
answer
business area analysis
question
The _____ is the minimum acceptable rate of return on an investment.
answer
required rate of return
question
In a Gantt chart, thick black bars represent milestones achieved in a project.
answer
False
question
A _____ is a document that recognizes the existence of a project and provides direction on the project's objectives and management.
answer
project charter
question
Which of the following is a network diagramming technique used primarily to predict total project duration?
answer
Critical path analysis
question
Generating ideas by comparing specific project practices or product characteristics to those of other projects or products inside or outside the performing organization is known as _____.
answer
benchmarking
question
_____ states that work expands to fill the time allowed.
answer
Parkinson's Law
question
One of PERT's main disadvantages is that it does not address the risk associated with duration estimates.
answer
False
question
The _____ section of the project management plan describes specific methodologies a project might use and explains how to document information.
answer
technical processes
question
The first step in determining the NPV is to _____.
answer
determine the estimated costs and benefits for the life of the project and the products it produces
question
Projects that address broad organizational needs are likely to fail.
answer
False
question
The critical path is the _____ path through a network diagram, and it represents the _____ amount of slack or float.
answer
longest; shortest
question
Opportunities and directives are essentially the same thing.
answer
False
question
A merge occurs when one node precedes multiple nodes.
answer
False
question
In project time management, the process of_____ primarily involves checking and managing changes to the project schedule.
answer
controlling the schedule
question
Which of the following is a proactive process undertaken to reduce the probability of negative consequences associated with project risks?
answer
Preventive actions
question
A Tracking Gantt chart is based on the percentage of work completed for project tasks or the actual start and finish dates.
answer
True
question
The number of interfaces in a single project is limited, and does not depend on the number of people involved in the project.
answer
Variance
question
In a weighted scoring model, the sum of the weights of all the criteria must total _____ percent.
answer
100
question
Project scope management includes the processes involved in defining and controlling what is or is not included in a project.
answer
True
question
_____ involves formalizing acceptance of the project deliverables and during this phase the key project stakeholders, such as the customer and sponsor for the project, inspect and then formally accept the deliverables.
answer
Validating scope
question
In project time management, the ultimate goal of _____ is to provide a basis for monitoring project progress for the time dimension of the project.
answer
developing a schedule
question
_____ involves defining and documenting the features and functions of the products produced during the project as well as the processes used for creating them.
answer
Collecting requirements
question
Change requests are always made in writing.
answer
False
question
As projects progress, the organization must reevaluate the need, funding, and will for each project to determine if the project should be continued, redefined, or terminated.
answer
True
question
A(n) ____ is a task at the lowest level of the WBS.
answer
work package
question
In project time management, the next step after defining project activities is:
answer
determining their dependecies
question
The first step in the planning process is _____.
answer
to tie the information technology strategic plan to the organization's overall strategic plan
question
Which of the following is true of return on investment or ROI?
answer
It is always a percentage.
question
A schedule management plan includes information which describes the format and frequency of schedule reports required for the project.
answer
True
question
Mind mapping allows people to write and even draw pictures of ideas in a nonlinear format.
answer
True
question
The majority of time on a project is usually spent on _____, as is most of the project's budget.
answer
execution
question
Critical chain scheduling assumes that resources multitask and maximizes multitasking.
answer
False
question
Payback period is the amount of time it will take to recoup, in the form of net cash inflows, the total dollars invested in a project.
answer
True
question
A project's internal rate of return can be determined by finding what discount rate results in an NPV of _____ for the project.
answer
zero
question
In project time management, one should control the scheule before estimating the duration for each activity.
answer
False
question
Which of the following types of dependencies are inherent in the nature of work being performed on a project?
answer
Mandatory
question
Corrective actions reduce the probability of negative consequences associated with project risks, while preventive actions should result in improvements in project performance.
answer
False
question
The ROI is always positive.
answer
False