ACI Concrete Field Testing Technician- Grade I

question
The sensor of the temperature measuring device shall be submerged a minimum of _____ in. [_____mm] into the freshly mixed concrete.
answer
3 in. [75 mm]
question
The temperature measuring device shall have a capacity of measuring temperature of freshly mixed concrete to +- _____ degrees F [+- _____ C] throughout a range of _____.
answer
1 degree F [0.5 C], 30 degrees F to 120 F [0 C to 50 C]
question
The temperature measuring device shall be calibrated _____, or whenever there is a question of _____.
answer
Annually, accuracy
question
The temperature of concrete may be measured in a wheelbarrow. True or False?
answer
True
question
The temperature of concrete may be measured in a wall form. True of False
answer
True
question
A composite sample of concrete is required even if the only purpose for obtaining the sample is to determine temperature. True of False?
answer
False
question
What must be done to the sample container prior to sampling the concrete?
answer
Dampen (with water)
question
What must be done to the concrete surrounding the temperature measuring device after the device is submerged in the fresh concrete.
answer
Gently press the concrete around the temperature measuring device at the surface of the concrete
question
How long must the temperature measuring device remain in the freshly mixed concrete?
answer
At least 2 minutes but not more than 5 minutes
question
After the temperature of the concrete is read, what is required?
answer
Reporting of temperature
question
The temperature of concrete is reported to the nearest _____ degrees F [_____ C]
answer
1 degree F [0.5 C]
question
According to ASTM C1064, what is one reason to take the temperature of concrete?
answer
Verify conformance to a specified requirement for temperature of concrete
question
A maximum temperature of freshly mixed concrete is specified in ASTM C1064. True of False?
answer
False
question
The sample of concrete used for temperature determination must be rodded 25 times. True or False?
answer
False
question
Sampling by this method is required when tests are to be made to determine _____ with specification requirements.
answer
Compliance
question
This method covers sampling from four types of mixtures which are _____, _____, _____, and _____.
answer
Stationary mixers, paving mixers, revolving drum mixers, and open top mixers
question
The maximum allowable time between obtaining the first and final portions of a composite sample is _____ minutes.
answer
15
question
Portions of a composite sample shall be thoroughly remixed bfore beginning tests on the sample. True of False?
answer
True
question
The maximum elapsed time allowed between obtaining the final portion of the composite sample and beginning the tests for slump, temperature, and air content is _____ minutes.
answer
5
question
The molding of strength test specimens shall begin within _____ minutes after fabricating the composite sample.
answer
15
question
The concrete sample must be protected from contamination and _____.
answer
Rapid evaporation
question
The minimum size sample for making strength test specimens is _____.
answer
28 L (1ft^3)
question
When sampling from a stationary mixer, the batch must be sampled at _____ or more regularly spaced intervals during discharge of the middle portion of the batch
answer
2
question
The composite sample for a paving mixer must represent a minimum of _____ different portions of the batch of concrete taken from the pile after discharge.
answer
5
question
When sampling from a revolving drum truck mixer, concrete must be sampled at a minimum of _____ regularly spaced intervals during discharge of the middle portion of this batch.
answer
2
question
Concrete samples from a truck mixer must be obtained before any water or admixtures are added to the mixer at the job site. True or False?
answer
False
question
The composite samples from a truck mixer must be obtained from the _____ portion of the batch.
answer
Middle
question
When the concrete contains aggregate larger than that permitted for a particular test method, the sample of concrete must be _____ _____ before making the test.
answer
Wet sieved
question
The slump test is applicable to plastic concrete with a maximum size aggregate of _____.
answer
1.5 in. [37.5 mm]
question
When the concrete contains aggregate larger than allowed for the slump test, the large aggregate must be _____.
answer
Removed by wet sieving the sample over 1.5 in. [37.5 mm] sieve
question
The mold for making the slump test is in the shape of _____.
answer
The frustum of a cone
question
The height of the slump mold is _____.
answer
12 in. [300 mm]
question
The interior surface of the slump mold is allowed to have minor irregularities. True or False?
answer
False
question
For use in the slump test, the end or both ends of the tamping rod must be _____.
answer
Rounded to a hemispherical tip
question
The sample of concrete for use in making the slump test must be obained in accordance with ASTM Standard _____.
answer
C172, Standard Practice for Sampling Freshly Mixed Concrete
question
The slump mold should be in a dry condition before beginning the test. True or False?
answer
False
question
The surface on which the slump mold will be placed must be _____.
answer
Flat, level, moist, nonabsorbent, and free of vibration
question
The slump mold is filled in _____ layers.
answer
3
question
Each layer should fill approximately _____ the volume of the mold.
answer
One-third
question
The approximate concrete depth (in verticle distance) after placing the first layer is _____, and the second layer is _____.
answer
2 5/8 in. [70 mm], 6 1/8 in. [160 mm]
question
What is the specified number of roddings for each layer?
answer
25
question
How deep should the tamping rod penetrate into each layer?
answer
Rod each layer throughout its depth; on the second and final layers, the rod should penetrate into the previous layer approximately 1 in. [25 mm]
question
When rodding the bottom layer, the tamping rod must be _____ to uniformly distribute the strokes.
answer
Slightly inclined
question
What must be done if the concrete drops below the top of the slump mold while the top layer is being rodded?
answer
Add additional concrete to keep an excess of concrete above the top of the mold at all times
question
Prior to lifting the mold, concrete must be removed from _____.
answer
The area surrounding the base of the mold
question
After the final rodding, the sides of the slump mold should should be tapped lightly with the tamping rod. True or False?
answer
False
question
When raising the slump mold, it should not be rotated or twisted, True or False?
answer
True
question
How much time is allowed for lifting the slump mold?
answer
5 +- 2 seconds
question
The measurement for slump is made from the top of the mold to what point of the concrete specimen?
answer
The displaced original center of the top surface of the specimen
question
The slump of the concrete is measured and reported to the nearest _____.
answer
1/4 in. [5 mm]
question
How much time is allowed to conduct the slump test from beginning to completion?
answer
2 1/2 minutes
question
The diameter of the tamping rod used in the test method is _____.
answer
5/8 in. [16 mm]
question
What is the required shape of the tamping end of the rod?
answer
Rounded to a hemispherical tip
question
What is the required minimum frequency of the vibrator used in this test method?
answer
7000 vibrations per minute
question
The outside diameter or side dimension of the vibrating element must be at least _____ but not greater than _____.
answer
0.75 in. [19 mm], 1.50 in. [38 mm]
question
A plastic container can be used for the measure in this method. True or False?
answer
False, measure must be steel or another suitable metal
question
What is the minimum thickness of a metal strike-off plate?
answer
1/4 in. [6 mm]
question
What is the minimum thickness for a glass or acrylic strike-off plate?
answer
1/2 in. [12 mm]
question
What is the specified weight of the mallet used on measures that are 0.5 ft^3 [14 L] or smaller?
answer
1.25 +- 0.50 lb. [600 +- 200 g]
question
Measures other than air meter bowls used for this test must conform to ASTM _____.
answer
C29
question
Air meter bowls used for this test must conform to ASTM _____ and be calibrated for volumee according to ASTM _____.
answer
C231, C29
question
The concrete sample must be obtained in accodance with what ASTM method?
answer
C172
question
What method of consolidation must be used when the slump is greater than 3 in. [75 mm]?
answer
Rodding
question
What method of consolidation must be used when the slump is less than 1 in. (25 mm]?
answer
Vibration
question
If rodding is the method of consolidation being used, the measure must be filled in how many layers?
answer
3
question
For a measure of 0.5 ft^3 [14 L], what is the required number of strokes of the tamping rod for consolidation of each layer?
answer
25
question
When rodding the middle and the top layers, the tamping rod should penetrate into the layer below approximately _____.
answer
1 in. [25 mm]
question
If vibration is the method of consolidation, the measure must be filled in _____ approximately equal layers.
answer
2
question
If, after consolidation of the final layer, the concrete level is 1/2 in. (13 mm) above the top of the measure, what should be done?
answer
Remove a representative portion of the excess concrete with a trowel or scoop
question
After consolidation of the final layer, an excess of concrete ____ above the top of the measure is considered optimum.
answer
1/8 in. [3 mm]
question
After completing the strike-off procedure, what must be done before weighing the measure and sample?
answer
Clean off any excess concrete
question
The pressure method of determining air content can be used on concrete containing _____ _____ aggregate.
answer
Relatively Dense
question
The pressure method of determining air content cannot be used on concrete containing the following types of aggregates, _____, _____, _____.
answer
Lightweight, air-cooled blast furnace slag, or aggregates of high porosity
question
What is the minimum allowable capacity of the measuring bowl used in this test method?
answer
6 L (0.20 ft^3)
question
What are the required characteristics of the tamping rod used in this test method?
answer
Round, straight steel rod, with a 16 mm [5/8 in.] +- 2 mm [1/16 in.] diameter, length at least 100 mm [4 in.] greater than the depth of the measuring bowl, but not greater than 600 mm [24 in.] in overall length, with the tamping end rounded to a hemispherical tip of the same diameter as the rod.
question
What is the specified size of the mallet required for this test method when the measuring bowl has the capacity of 14 L [0.5 ft^3] or less?
answer
0.60 +- 0.25 kg [1.25 +- 0.50 lb.]
question
The sample of concrete used for this test is to be obtained in accordance with what ASTM Standard?
answer
C172
question
The maximum size aggregate allowed for this test method is _____.
answer
50 mm (2 in.)
question
If the concrete contains aggregate larger than the maximum allowed for this test, the sample must be _____.
answer
Wet sieved over a 1 1/2 in. (37.5 mm) sieve
question
If the concrete sample is to be consolidated by rodding, the measure is filled in _____ layers.
answer
3 equal
question
If the concrete sample is to be consolidated by vibration, the measure is filled in _____ layers.
answer
2 equal
question
When rodding the concrete sample, what is the specified number of strokes required for each layer?
answer
25
question
Vibration of the concrete sample is not allowed when the slump of concrete exceeds _____.
answer
75 mm (3 in.)
question
In rodding the sample, how deep should the rod penetrate each layer?
answer
Rod bottom layer to full depth; rod second and final layer penetrating the previous layer about 25 mm (1 in.)
question
After rodding each layer, what should be done to the measure before adding another layer of concrete?
answer
Tap the sides of the measure smartly 10 to 15 times with the mallet
question
When consolidating the concrete by vibration, how many times should the vibrator be inserted into each layer?
answer
Three (3)
question
What tools may be used to strike off the top surface of the concrete following consolidation of the final layer?
answer
A strike-off bar; a metal, glass, or acrylic plate
question
What must be done if there is a slight deficiency in the quantity of concrete in the measure of consolidation of final layer?
answer
Add a quantity of representative concrete before strike off
question
What must be done if there is an excessive amount of concrete in measure following consolidation of the final layer?
answer
Remove a representative quantity of concrete with the scoop or trowel before the strike off
question
The volumetric method of determining air content of concrete can be used on concrete containing what types of aggregate?
answer
All types of aggregate
question
What are the requirements for the tamping rod used in the test method?
answer
Round, straight 5/8 [16 mm] +- 1/16 in. [2 mm] diameter rod at least 5 in. [300 mm] greater in length than the depth of the bowl being used, with the tamping end rounded to a hemispherical tip of the same diameter, made of steel, high-density polyethylene, or other plastic of equal or greater abrasion resistance.
question
What are the requirements for the strike-off bar used in this test method?
answer
Flat, straight steel bar at least 1/8 by 3/4 by 12 in. [3 by 20 by 300 mm] or a 4.4 flat, straight high-density polyethylene bar, or other plastic of equal or greater abrasion resistance, at least 1/4 by 3/4 by 23 in [6 by 30 by 300 mm].
question
What is the approximate volume of the measuring cup used to add water to the air meter, in relation to teh volume of the air meter bowl?
answer
1.00% +- 0.04%
question
What type of alcohol and concentration must be used in this test method?
answer
Isopropyl, 70% by volume (65% by weight)
question
A mallet weighing ____ must be used to tap the sides of the bowl after rodding each layer.
answer
1.25 +- 0.50 lb. (600 +- 200 g)
question
The sample of concrete used in this test method must be obtained in accordance with what ASTM Standard?
answer
C172
question
The maximum size aggregate allowed in this test method is_____.
answer
1 1/2 in. (37.5 mm)
question
If the concrete sample contains aggregate larger than that allowed for this test, the sample must be _____.
answer
Wet sieved over a 1-in. (25-mm) sieve
question
When filling the bowl of the air meter, the concrete must be placed in _____ layers of equal depth.
answer
2
question
What is the specified number of strokes required when rodding each layer of concrete?
answer
25
question
It is necessary to tap the sides of the bowl after each layer has been rodded. True or False?
answer
True
question
The initial quantity of water and alcohol added to the air meter can be poured directly into the neck of the top section of the air meter. True or False?
answer
False; the funnel must be used
question
Upon final filling of the air meter with water, what part of the liquid level should be adjusted to teh zero mark on the meter?
answer
Bottom of the meniscus
question
How long should the air meter be inverted and agitated?
answer
No more than five seconds at a time, but must be repeated for a minimum of 45 seconds to free concrete from the base
question
How many times does the rolling operation occur?
answer
A minimum of 2, a minimum of 3
question
Why is the isopropyl alcohol added to the meter?
answer
To dispel any foam that may be on the surface of the water
question
The direct reading of the final liquid level in the neck of the air meter, is estimated to teh nearest _____.
answer
0.25%
question
If the air content is greater than the 9% range of the meter, _____.
answer
Calibrated cups of water are added to ring the liquid level within the graduated range
question
In order for an initial meter reading to be valid, the meter must not be leaking, the liquid level must stabilize within 6 minutes, and the foam on the surface of the liquid must not be greater than 2 full percent divisions. True or False?
answer
True
question
If less than 2.5 pints of alcohol are used, the air content is always indicated by the inal meter reading. True or False?
answer
False, if the air content is more than 9%, the number of calibrated cups of water introduced into the meter to bring the liquid level within the graduated range must be added
question
If more than 2.5 pints of alcohol are used, the final meter reading is always adjusted using _____.
answer
A correction factor
question
When large amounts of alcohol are used, the direct reading will tend to indicate a _____ air content.
answer
Higher
question
At the end of the procedure, the air meter is _____.
answer
Disassembled and its contents examined
question
If portions of undisturbed concrete are found in the air meter at the end of the test, _____.
answer
The test is invalid
question
ASTM Method gives standardized requirements for _____, _____, _____, and _____, of test specimens.
answer
Making, curing, protecting, transporting
question
For cylinders with a diameter of 6 in. [150 mm] or greater, the tamping rod must be a round, straight steel rod with a diameter of _____.
answer
5/8 +- 1/16 in [16 mm +- 2 mm]
question
The minimum frequency of an internal vibrator used in this procedure is _____.
answer
9000 vibrations per minute [150 Hz]
question
The container for obtaining the concrete sample used in this procedure can be a _____, _____, or _____.
answer
Metal pan, wheelbarrow, flat, clean nonabsorbent mixing board
question
A 6 by 12 in [150 mm by 300 mm] cylinder mold can be used for concrete containing aggregate with particles not exceeding _____ in size, without the need for wet sieving the concrete.
answer
2 in. [50 mm]
question
The sample of concrete used in molding test specimens must be obtained in accordance with what ASTM Standard?
answer
C172
question
When strenght specimens are to be made, what three other tests must be made?
answer
Slump, air content, temperature
question
After molding test specimens, you should wait two hours before moving them to the location of initial storage. True or False?
answer
False; the specimens must be moved immediately
question
The supporting surface on which specimens are stored shall be level within _____.
answer
1/4 in. per ft. [20 mm per m]
question
For concrete with a slump of less than 1 in. [25 mm], the test specimens must be consolidated by _____.
answer
Vibration
question
If the concrete is to be consolidated by vibration, a standard 4 by 8 in. [100 mm by 200 mm] cylinder mold must be filled in _____ equal layers.
answer
2
question
When rodding a standard 6 by 12 in [150 mm by 300 mm] cylinder, each layer must be rodded _____ times.
answer
25
question
When rodding each upper layer of concrete in a cylinder, the tamping rod should penetrate into the underlying layer by about _____.
answer
1 in. [25 mm]
question
When using an internal vibrator to consolidate a 6 by 12 in. [150 mm by 300 mm] compressive strength test specimen, the vibrator must be inserted at _____ different points for each layer.
answer
2
question
When consolidating a flexural strength test specimen by rodding, rod one stroke for each _____ of top surface area.
answer
2 in.^2 [14 cm^2]
question
When internal vibration is used to consolidate a standard flexural strength test specimen, the technician should insert the bibrator at intervals not exceeding _____ along the center line of the beam.
answer
6 in. [150 mm]
question
Concrete mixtures with specified strengths of 6000 psi [40 MPa] or greater shall have an initial curing temperature between __________.
answer
68 and 78 degrees F [20 and 26 C]
question
Up to 48 hours after molding, test specimens that are to be standard cured shall be stored in a temperature range between _____ to _____.
answer
60 and 70 degrees F [16 and 27 C]
question
Upon completion of initial curing, the test specimens may be left in their molds and sealed in plastic bags. True or False?
answer
False; specimens are to be demoled and placed in water storage tanks or moist rooms with free water at a temperature of 73.5 +- 3.5 degrees F [23.0 +- 2.0 C]
question
During transportation, test specimens must be protected from damage due to _____, _____, and _____.
answer
Jarring, freezing temperatures, moisture loss
question
Specimens shall not be transported until _____ after final set.
answer
8h
question
Transportation time shall not exceed _____.
answer
4h
question
Standard Curing is the curing method used when test specimens are to be used for _________.
answer
Acceptance testing for specified strength, checking the adequacy of mixture proportions for strength, quality control
question
Field Curing is the curing method used when test specimens are to be used for __________.
answer
Determination of whether the structure is capable of being put into service; Comparison with standard cured specimens test results or with results from various in-place test methods; Adequacy of curing and protection of concrete in the Structure, or Form or shoring removal time requirements
question
Cylinders that are to be field cured are stored __________ and protected __________.
answer
In or on the structure as near to the point of deposit of the concrete represented as possible; In as near as possible the same way as the formed work
question
The temperature and moisture environment for field cured cylinders must be __________.
answer
The same as the structural work
question
Cylinders made for the purpose of determining when a structure may be put into service shall be removed from the mold __________.
answer
At the time of the removal of formwork
1 of

Unlock all answers in this set

Unlock answers
question
The sensor of the temperature measuring device shall be submerged a minimum of _____ in. [_____mm] into the freshly mixed concrete.
answer
3 in. [75 mm]
question
The temperature measuring device shall have a capacity of measuring temperature of freshly mixed concrete to +- _____ degrees F [+- _____ C] throughout a range of _____.
answer
1 degree F [0.5 C], 30 degrees F to 120 F [0 C to 50 C]
question
The temperature measuring device shall be calibrated _____, or whenever there is a question of _____.
answer
Annually, accuracy
question
The temperature of concrete may be measured in a wheelbarrow. True or False?
answer
True
question
The temperature of concrete may be measured in a wall form. True of False
answer
True
question
A composite sample of concrete is required even if the only purpose for obtaining the sample is to determine temperature. True of False?
answer
False
question
What must be done to the sample container prior to sampling the concrete?
answer
Dampen (with water)
question
What must be done to the concrete surrounding the temperature measuring device after the device is submerged in the fresh concrete.
answer
Gently press the concrete around the temperature measuring device at the surface of the concrete
question
How long must the temperature measuring device remain in the freshly mixed concrete?
answer
At least 2 minutes but not more than 5 minutes
question
After the temperature of the concrete is read, what is required?
answer
Reporting of temperature
question
The temperature of concrete is reported to the nearest _____ degrees F [_____ C]
answer
1 degree F [0.5 C]
question
According to ASTM C1064, what is one reason to take the temperature of concrete?
answer
Verify conformance to a specified requirement for temperature of concrete
question
A maximum temperature of freshly mixed concrete is specified in ASTM C1064. True of False?
answer
False
question
The sample of concrete used for temperature determination must be rodded 25 times. True or False?
answer
False
question
Sampling by this method is required when tests are to be made to determine _____ with specification requirements.
answer
Compliance
question
This method covers sampling from four types of mixtures which are _____, _____, _____, and _____.
answer
Stationary mixers, paving mixers, revolving drum mixers, and open top mixers
question
The maximum allowable time between obtaining the first and final portions of a composite sample is _____ minutes.
answer
15
question
Portions of a composite sample shall be thoroughly remixed bfore beginning tests on the sample. True of False?
answer
True
question
The maximum elapsed time allowed between obtaining the final portion of the composite sample and beginning the tests for slump, temperature, and air content is _____ minutes.
answer
5
question
The molding of strength test specimens shall begin within _____ minutes after fabricating the composite sample.
answer
15
question
The concrete sample must be protected from contamination and _____.
answer
Rapid evaporation
question
The minimum size sample for making strength test specimens is _____.
answer
28 L (1ft^3)
question
When sampling from a stationary mixer, the batch must be sampled at _____ or more regularly spaced intervals during discharge of the middle portion of the batch
answer
2
question
The composite sample for a paving mixer must represent a minimum of _____ different portions of the batch of concrete taken from the pile after discharge.
answer
5
question
When sampling from a revolving drum truck mixer, concrete must be sampled at a minimum of _____ regularly spaced intervals during discharge of the middle portion of this batch.
answer
2
question
Concrete samples from a truck mixer must be obtained before any water or admixtures are added to the mixer at the job site. True or False?
answer
False
question
The composite samples from a truck mixer must be obtained from the _____ portion of the batch.
answer
Middle
question
When the concrete contains aggregate larger than that permitted for a particular test method, the sample of concrete must be _____ _____ before making the test.
answer
Wet sieved
question
The slump test is applicable to plastic concrete with a maximum size aggregate of _____.
answer
1.5 in. [37.5 mm]
question
When the concrete contains aggregate larger than allowed for the slump test, the large aggregate must be _____.
answer
Removed by wet sieving the sample over 1.5 in. [37.5 mm] sieve
question
The mold for making the slump test is in the shape of _____.
answer
The frustum of a cone
question
The height of the slump mold is _____.
answer
12 in. [300 mm]
question
The interior surface of the slump mold is allowed to have minor irregularities. True or False?
answer
False
question
For use in the slump test, the end or both ends of the tamping rod must be _____.
answer
Rounded to a hemispherical tip
question
The sample of concrete for use in making the slump test must be obained in accordance with ASTM Standard _____.
answer
C172, Standard Practice for Sampling Freshly Mixed Concrete
question
The slump mold should be in a dry condition before beginning the test. True or False?
answer
False
question
The surface on which the slump mold will be placed must be _____.
answer
Flat, level, moist, nonabsorbent, and free of vibration
question
The slump mold is filled in _____ layers.
answer
3
question
Each layer should fill approximately _____ the volume of the mold.
answer
One-third
question
The approximate concrete depth (in verticle distance) after placing the first layer is _____, and the second layer is _____.
answer
2 5/8 in. [70 mm], 6 1/8 in. [160 mm]
question
What is the specified number of roddings for each layer?
answer
25
question
How deep should the tamping rod penetrate into each layer?
answer
Rod each layer throughout its depth; on the second and final layers, the rod should penetrate into the previous layer approximately 1 in. [25 mm]
question
When rodding the bottom layer, the tamping rod must be _____ to uniformly distribute the strokes.
answer
Slightly inclined
question
What must be done if the concrete drops below the top of the slump mold while the top layer is being rodded?
answer
Add additional concrete to keep an excess of concrete above the top of the mold at all times
question
Prior to lifting the mold, concrete must be removed from _____.
answer
The area surrounding the base of the mold
question
After the final rodding, the sides of the slump mold should should be tapped lightly with the tamping rod. True or False?
answer
False
question
When raising the slump mold, it should not be rotated or twisted, True or False?
answer
True
question
How much time is allowed for lifting the slump mold?
answer
5 +- 2 seconds
question
The measurement for slump is made from the top of the mold to what point of the concrete specimen?
answer
The displaced original center of the top surface of the specimen
question
The slump of the concrete is measured and reported to the nearest _____.
answer
1/4 in. [5 mm]
question
How much time is allowed to conduct the slump test from beginning to completion?
answer
2 1/2 minutes
question
The diameter of the tamping rod used in the test method is _____.
answer
5/8 in. [16 mm]
question
What is the required shape of the tamping end of the rod?
answer
Rounded to a hemispherical tip
question
What is the required minimum frequency of the vibrator used in this test method?
answer
7000 vibrations per minute
question
The outside diameter or side dimension of the vibrating element must be at least _____ but not greater than _____.
answer
0.75 in. [19 mm], 1.50 in. [38 mm]
question
A plastic container can be used for the measure in this method. True or False?
answer
False, measure must be steel or another suitable metal
question
What is the minimum thickness of a metal strike-off plate?
answer
1/4 in. [6 mm]
question
What is the minimum thickness for a glass or acrylic strike-off plate?
answer
1/2 in. [12 mm]
question
What is the specified weight of the mallet used on measures that are 0.5 ft^3 [14 L] or smaller?
answer
1.25 +- 0.50 lb. [600 +- 200 g]
question
Measures other than air meter bowls used for this test must conform to ASTM _____.
answer
C29
question
Air meter bowls used for this test must conform to ASTM _____ and be calibrated for volumee according to ASTM _____.
answer
C231, C29
question
The concrete sample must be obtained in accodance with what ASTM method?
answer
C172
question
What method of consolidation must be used when the slump is greater than 3 in. [75 mm]?
answer
Rodding
question
What method of consolidation must be used when the slump is less than 1 in. (25 mm]?
answer
Vibration
question
If rodding is the method of consolidation being used, the measure must be filled in how many layers?
answer
3
question
For a measure of 0.5 ft^3 [14 L], what is the required number of strokes of the tamping rod for consolidation of each layer?
answer
25
question
When rodding the middle and the top layers, the tamping rod should penetrate into the layer below approximately _____.
answer
1 in. [25 mm]
question
If vibration is the method of consolidation, the measure must be filled in _____ approximately equal layers.
answer
2
question
If, after consolidation of the final layer, the concrete level is 1/2 in. (13 mm) above the top of the measure, what should be done?
answer
Remove a representative portion of the excess concrete with a trowel or scoop
question
After consolidation of the final layer, an excess of concrete ____ above the top of the measure is considered optimum.
answer
1/8 in. [3 mm]
question
After completing the strike-off procedure, what must be done before weighing the measure and sample?
answer
Clean off any excess concrete
question
The pressure method of determining air content can be used on concrete containing _____ _____ aggregate.
answer
Relatively Dense
question
The pressure method of determining air content cannot be used on concrete containing the following types of aggregates, _____, _____, _____.
answer
Lightweight, air-cooled blast furnace slag, or aggregates of high porosity
question
What is the minimum allowable capacity of the measuring bowl used in this test method?
answer
6 L (0.20 ft^3)
question
What are the required characteristics of the tamping rod used in this test method?
answer
Round, straight steel rod, with a 16 mm [5/8 in.] +- 2 mm [1/16 in.] diameter, length at least 100 mm [4 in.] greater than the depth of the measuring bowl, but not greater than 600 mm [24 in.] in overall length, with the tamping end rounded to a hemispherical tip of the same diameter as the rod.
question
What is the specified size of the mallet required for this test method when the measuring bowl has the capacity of 14 L [0.5 ft^3] or less?
answer
0.60 +- 0.25 kg [1.25 +- 0.50 lb.]
question
The sample of concrete used for this test is to be obtained in accordance with what ASTM Standard?
answer
C172
question
The maximum size aggregate allowed for this test method is _____.
answer
50 mm (2 in.)
question
If the concrete contains aggregate larger than the maximum allowed for this test, the sample must be _____.
answer
Wet sieved over a 1 1/2 in. (37.5 mm) sieve
question
If the concrete sample is to be consolidated by rodding, the measure is filled in _____ layers.
answer
3 equal
question
If the concrete sample is to be consolidated by vibration, the measure is filled in _____ layers.
answer
2 equal
question
When rodding the concrete sample, what is the specified number of strokes required for each layer?
answer
25
question
Vibration of the concrete sample is not allowed when the slump of concrete exceeds _____.
answer
75 mm (3 in.)
question
In rodding the sample, how deep should the rod penetrate each layer?
answer
Rod bottom layer to full depth; rod second and final layer penetrating the previous layer about 25 mm (1 in.)
question
After rodding each layer, what should be done to the measure before adding another layer of concrete?
answer
Tap the sides of the measure smartly 10 to 15 times with the mallet
question
When consolidating the concrete by vibration, how many times should the vibrator be inserted into each layer?
answer
Three (3)
question
What tools may be used to strike off the top surface of the concrete following consolidation of the final layer?
answer
A strike-off bar; a metal, glass, or acrylic plate
question
What must be done if there is a slight deficiency in the quantity of concrete in the measure of consolidation of final layer?
answer
Add a quantity of representative concrete before strike off
question
What must be done if there is an excessive amount of concrete in measure following consolidation of the final layer?
answer
Remove a representative quantity of concrete with the scoop or trowel before the strike off
question
The volumetric method of determining air content of concrete can be used on concrete containing what types of aggregate?
answer
All types of aggregate
question
What are the requirements for the tamping rod used in the test method?
answer
Round, straight 5/8 [16 mm] +- 1/16 in. [2 mm] diameter rod at least 5 in. [300 mm] greater in length than the depth of the bowl being used, with the tamping end rounded to a hemispherical tip of the same diameter, made of steel, high-density polyethylene, or other plastic of equal or greater abrasion resistance.
question
What are the requirements for the strike-off bar used in this test method?
answer
Flat, straight steel bar at least 1/8 by 3/4 by 12 in. [3 by 20 by 300 mm] or a 4.4 flat, straight high-density polyethylene bar, or other plastic of equal or greater abrasion resistance, at least 1/4 by 3/4 by 23 in [6 by 30 by 300 mm].
question
What is the approximate volume of the measuring cup used to add water to the air meter, in relation to teh volume of the air meter bowl?
answer
1.00% +- 0.04%
question
What type of alcohol and concentration must be used in this test method?
answer
Isopropyl, 70% by volume (65% by weight)
question
A mallet weighing ____ must be used to tap the sides of the bowl after rodding each layer.
answer
1.25 +- 0.50 lb. (600 +- 200 g)
question
The sample of concrete used in this test method must be obtained in accordance with what ASTM Standard?
answer
C172
question
The maximum size aggregate allowed in this test method is_____.
answer
1 1/2 in. (37.5 mm)
question
If the concrete sample contains aggregate larger than that allowed for this test, the sample must be _____.
answer
Wet sieved over a 1-in. (25-mm) sieve
question
When filling the bowl of the air meter, the concrete must be placed in _____ layers of equal depth.
answer
2
question
What is the specified number of strokes required when rodding each layer of concrete?
answer
25
question
It is necessary to tap the sides of the bowl after each layer has been rodded. True or False?
answer
True
question
The initial quantity of water and alcohol added to the air meter can be poured directly into the neck of the top section of the air meter. True or False?
answer
False; the funnel must be used
question
Upon final filling of the air meter with water, what part of the liquid level should be adjusted to teh zero mark on the meter?
answer
Bottom of the meniscus
question
How long should the air meter be inverted and agitated?
answer
No more than five seconds at a time, but must be repeated for a minimum of 45 seconds to free concrete from the base
question
How many times does the rolling operation occur?
answer
A minimum of 2, a minimum of 3
question
Why is the isopropyl alcohol added to the meter?
answer
To dispel any foam that may be on the surface of the water
question
The direct reading of the final liquid level in the neck of the air meter, is estimated to teh nearest _____.
answer
0.25%
question
If the air content is greater than the 9% range of the meter, _____.
answer
Calibrated cups of water are added to ring the liquid level within the graduated range
question
In order for an initial meter reading to be valid, the meter must not be leaking, the liquid level must stabilize within 6 minutes, and the foam on the surface of the liquid must not be greater than 2 full percent divisions. True or False?
answer
True
question
If less than 2.5 pints of alcohol are used, the air content is always indicated by the inal meter reading. True or False?
answer
False, if the air content is more than 9%, the number of calibrated cups of water introduced into the meter to bring the liquid level within the graduated range must be added
question
If more than 2.5 pints of alcohol are used, the final meter reading is always adjusted using _____.
answer
A correction factor
question
When large amounts of alcohol are used, the direct reading will tend to indicate a _____ air content.
answer
Higher
question
At the end of the procedure, the air meter is _____.
answer
Disassembled and its contents examined
question
If portions of undisturbed concrete are found in the air meter at the end of the test, _____.
answer
The test is invalid
question
ASTM Method gives standardized requirements for _____, _____, _____, and _____, of test specimens.
answer
Making, curing, protecting, transporting
question
For cylinders with a diameter of 6 in. [150 mm] or greater, the tamping rod must be a round, straight steel rod with a diameter of _____.
answer
5/8 +- 1/16 in [16 mm +- 2 mm]
question
The minimum frequency of an internal vibrator used in this procedure is _____.
answer
9000 vibrations per minute [150 Hz]
question
The container for obtaining the concrete sample used in this procedure can be a _____, _____, or _____.
answer
Metal pan, wheelbarrow, flat, clean nonabsorbent mixing board
question
A 6 by 12 in [150 mm by 300 mm] cylinder mold can be used for concrete containing aggregate with particles not exceeding _____ in size, without the need for wet sieving the concrete.
answer
2 in. [50 mm]
question
The sample of concrete used in molding test specimens must be obtained in accordance with what ASTM Standard?
answer
C172
question
When strenght specimens are to be made, what three other tests must be made?
answer
Slump, air content, temperature
question
After molding test specimens, you should wait two hours before moving them to the location of initial storage. True or False?
answer
False; the specimens must be moved immediately
question
The supporting surface on which specimens are stored shall be level within _____.
answer
1/4 in. per ft. [20 mm per m]
question
For concrete with a slump of less than 1 in. [25 mm], the test specimens must be consolidated by _____.
answer
Vibration
question
If the concrete is to be consolidated by vibration, a standard 4 by 8 in. [100 mm by 200 mm] cylinder mold must be filled in _____ equal layers.
answer
2
question
When rodding a standard 6 by 12 in [150 mm by 300 mm] cylinder, each layer must be rodded _____ times.
answer
25
question
When rodding each upper layer of concrete in a cylinder, the tamping rod should penetrate into the underlying layer by about _____.
answer
1 in. [25 mm]
question
When using an internal vibrator to consolidate a 6 by 12 in. [150 mm by 300 mm] compressive strength test specimen, the vibrator must be inserted at _____ different points for each layer.
answer
2
question
When consolidating a flexural strength test specimen by rodding, rod one stroke for each _____ of top surface area.
answer
2 in.^2 [14 cm^2]
question
When internal vibration is used to consolidate a standard flexural strength test specimen, the technician should insert the bibrator at intervals not exceeding _____ along the center line of the beam.
answer
6 in. [150 mm]
question
Concrete mixtures with specified strengths of 6000 psi [40 MPa] or greater shall have an initial curing temperature between __________.
answer
68 and 78 degrees F [20 and 26 C]
question
Up to 48 hours after molding, test specimens that are to be standard cured shall be stored in a temperature range between _____ to _____.
answer
60 and 70 degrees F [16 and 27 C]
question
Upon completion of initial curing, the test specimens may be left in their molds and sealed in plastic bags. True or False?
answer
False; specimens are to be demoled and placed in water storage tanks or moist rooms with free water at a temperature of 73.5 +- 3.5 degrees F [23.0 +- 2.0 C]
question
During transportation, test specimens must be protected from damage due to _____, _____, and _____.
answer
Jarring, freezing temperatures, moisture loss
question
Specimens shall not be transported until _____ after final set.
answer
8h
question
Transportation time shall not exceed _____.
answer
4h
question
Standard Curing is the curing method used when test specimens are to be used for _________.
answer
Acceptance testing for specified strength, checking the adequacy of mixture proportions for strength, quality control
question
Field Curing is the curing method used when test specimens are to be used for __________.
answer
Determination of whether the structure is capable of being put into service; Comparison with standard cured specimens test results or with results from various in-place test methods; Adequacy of curing and protection of concrete in the Structure, or Form or shoring removal time requirements
question
Cylinders that are to be field cured are stored __________ and protected __________.
answer
In or on the structure as near to the point of deposit of the concrete represented as possible; In as near as possible the same way as the formed work
question
The temperature and moisture environment for field cured cylinders must be __________.
answer
The same as the structural work
question
Cylinders made for the purpose of determining when a structure may be put into service shall be removed from the mold __________.
answer
At the time of the removal of formwork