question
Which Rating Systems will award a project one or more points for already being LEED Certified in another rating system? (Choose 3) A. LEED for Schools B. LEED for Homes C. LEED for Commercial Interiors D. LEED for Operations and Maintenance
answer
B,C,D
question
Which of the following is not a required design consideration for the recycling collection and storage area prerequisite? A. Convenient location B. Collection truck access C. Appropriate signage D. Protection from the elements
answer
B Collection truck access
question
When a general contractor is collecting documentation for the construction waste management credit, which two of the following pieces of information regarding measurement of materials diverted would be most helpful? (Choose 2) A. The number of assorted windows donated to Habitat for Humanity B. The weight of concrete used as fill material C. The volume of scrap metal sent to a recycler D. The volume of land-clearing debris composted E. The linear footage of wood waste burned (incinerated) on site
answer
B,C goes by volume and mass, therefore # of windows would not count. land clearing debris is not considered
question
The Heat Island Effect may raise the temperature in an urban area by how many degrees above the temperature in nearby rural areas? A. 2 degrees B. 4 degrees C. 6 degrees D. 8 degrees E. 10 degrees
answer
E. 10 degrees
question
If a contractor wishes to use source control as a component of a construction waste management plan, which of the following strategies might he pursue for this portion of his plan? (Choose 2) A. Salvaging materials by donating them to Habitat for Humanity B. Ordering pre-assembled products C. Using modular construction techniques D. Recycling product packaging materials E. Reusing scrap materials on-site
answer
B, C Only pre assembly and modular construction address source reduction
question
Which of the following products would be considered to contain postconsumer recycled content that would contribute to the LEED credit for recycled content? (Choose 3) A. Steel Beams made from used railroad ties B. Glass tiles made from glass broken during the window manufacturing process C. Carpet made from recycled soda bottles D. Plumbing pipe made from recycled plastic components E. A countertop made from newspapers
answer
A, C, E glass tiles would be pre-consumer; content in plumbing pipe does not contribute to credit because this credit only involves materials in CSI divisions 2-10
question
What percentage of the solid waste stream each year is attributable to construction and demolition waste? A. 10% B. 20% C. 30% D. 40% E. 50%
answer
D 40%
question
Which of the following people should not have access to LEED Online? A. Architect B. Building Owner C. Building User D. General Contractor E. Landscape Architect
answer
C Building user should not access
question
Which type of refrigerant has an essentially zero ozone depletion potential (ODP) but still has high global warming potential (GWP)? A. Natural Refrigerants B. Chlorofluorocarbons (CFCs) C. Hydrofluorocarbons (HFCs) D. Hydrochlorofluorocarbons (HCFCs)
answer
C. HFC
question
Which Rating System requires a project team to establish a Preliminary Rating? A. LEED for Schools B. LEED for Core and Shell C. LEED for Neighborhood Development D. LEED for Operations and Maintenance E. LEED for Homes
answer
E. Homes
question
Which of the following materials may not contribute to construction waste management strategies? (Choose 2) A. Land clearing debris B. Scrap Wood C. Asbestos Floor Tiles D. Concrete E. Product Packaging
answer
A, C
question
Which specific refrigerant has the highest global warming potential (GWP) of all the common refrigerants? A. CFC-502 B. HCFC-123 C. HFC-404A D. CFC-11 E. HFC-23
answer
E
question
What project features are included in the "development footprint"? (choose 3) A. The building itself B. A natural pond C. A wooded area D. Landscaping E. A parking lot F. Sidewalks
answer
A, E, F
question
A project team is using cotton insulation that is grown and manufactured 200 miles from the project site. What credit(s) will the use of this material count toward? A. Recycled Content B. Rapidly Renewable Materials C. Regional Materials D. Recycled Content and Regional Materials E. Rapidly Renewable Materials and Regional Materials
answer
E Cotton is grown and harvested in less than 10 years and grown within 500 miles
question
"Green Tags" is a common term for: A. Any form of renewable energy B. Sustainable products certifications C. Renewable Energy Certificates (RECs) D. Incentives for purchasing fuel-efficient vehicles
answer
C
question
If a project team working on a LEED BD+C project can obtain documentation of where a product is manufactured but not where it is harvested or extracted, how can they count this material toward compliance with the regional materials credit? A. They may only count 50% of the value of the material B. They may count the entire value of the material C. They cannot count the material at all D. They can count the material, but only if it was manufactured within 100 miles of the project site
answer
C No partial credit
question
Which Rating System offers an Innovation and Design credit for holding a LEED charrette? A. LEED for Building Design and Construction B. LEED for Interior Design and Construction C. LEED for Operations and Maintenance D. LEED for Homes E. LEED for Neighborhood Development
answer
D Homes
question
Local codes and regulations may affect which of the following two strategies? A. Construction waste management B. Use of rainwater for toilet flushing C. Minimizing parking capacity D. Managing indoor air quality during construction E. Purchasing green power
answer
B, C
question
Which of the following is not required of an Innovation and Design strategy? A. It must be comprehensive B. It must be cost effective C. It must be repeatable by other projects D. It must be quantifiable E. It must be a strategy not already covered in the LEED Rating System
answer
B cost effective
question
If a LEED project that is providing preferred parking for fuel-efficient and low-emitting vehicles has multiple parking lots, where should the preferred parking spaces be located? A. Preferred parking spaces only need to be provided in one lot B. Preferred parking spaces only need to be located in the lot designated for visitors C. Preferred parking spaces only need to be provided in the lot designated for staff D. Preferred parking spaces must be distributed among all lots
answer
D
question
Which type of system or equipment would not be a consumer of process water? A. Domestic hot water heater B. Dishwasher C. Clothes Washer D. Cooling Tower E. Food Steamer
answer
A
question
What is the minimum amount of pervious area a paving system must have to be considered "open-grid"? A. 20% B. 30% C. 40% D. 50% E. 60%
answer
D
question
What is required as documentation for each and every prerequisite and credit in the LEED for Building Design and Construction Rating Systems? A. A project narrative B. A project drawings C. Photos D. A letter template E. A required signatory
answer
D
question
94. What does the construction activity pollution prevention plan aim to prevent? (Choose 3) A. Erosion B. Solid Waste Generation C. Construction Worker Accidents D. Carbon Emissions E. Sedimentation F. Airborne Dust Pollution
answer
A, E, F
question
96. Use of a dry urinal would decrease the fixture's water use from the Energy Policy Act baseline urinal water usage by how much? A. 1.6 GPF B. 1.0 GPF C. .5 GPF D. 2.5 GPM
answer
B
question
Which of the following is not a category in the LEED for Operations and Maintenance Rating System? A. Water Efficiency B. Materials and Resources C. Indoor Air Quality D. Innovation in Operations E. Regional Priority
answer
C
question
Which refrigerant is environmentally preferrable? A) CFC B) HCFC C) HFC D) All of the above
answer
C) HFC
question
SCAQMD is for what products?
answer
Adhesives, Sealants, primers, wood finishes
question
Green Seal
answer
Aerosols, adhesives, architectural paints, anti-rust/ corrosive coating
question
Green label
answer
carpet cushions
question
Green label plus
answer
Carpets
question
Floorscore
answer
vinyl, linoleum,laminate wood, rubber flooring
question
Greenguard
answer
Furniture and seating
question
Ashrae 52.2
answer
Air filter standards
question
Ashrae 55
answer
thermal comfort. Air velocity, temperature, humidity,
question
What is a "Densely occupied space?"
answer
25 people / 1,000 sq. ft.
question
How close must a building be to public transportation to receive credit?
answer
1/2 mile to rail or subway, 1/4 mile to at least 2 bus stops
question
How close to basic services for credit?
answer
1/2 mile
question
What is the required timeline for phasing out CFCs in all air conditioning equipment in major renovations?
answer
Must be phased out prior to project completion. Exception is if phasing out cfc is not economically feasible, in which case it must be phased out within 5 years.
question
What pieces of info are required to complete FSC Certified wood? (Choose 3) a) volume of wood and where it was harvested b) Chain of custody (COC) certification number c) Name of the product manufacturer d) cost of each product e) list of paints / coatings used on each FSC certified product
answer
B, C, D By cost not volume
question
Which two standards relate to low emitting materials, paints & coatings
answer
Green Seal, SCAQMD
question
what does not qualify for the community connectivity credit? a) Brownfield site b) Greenfield site c) Site located within 1/2 mile of basic services d) site located within 1/2 mile of train and subway
answer
Greenfield sites (raw, virgin land) do not apply to the Community Connectivity credit. In other words, projects that develop on untouched, virgin land located in an urban center will not be awarded points for site selection.
question
How far for regional materials?
answer
500 miles harvested/extracted and manufactured
question
Which of the following sources must be contained and treated before it may be used to irrigate landscaping? (Choose 2) a) greywater from sinks and showers b) Blackwater from urinals c) Rainwater collected on site d) cooling tower water e) non-potable municipally supplied water
answer
B, D
question
Which organization provides certification for green power?
answer
Center for Resource Solutions, Green-e
question
ASHRAE 62.1
answer
Used to determine minimum ventilation requirements in mechanically and naturally ventilated buildings and how to increase ventilation and improve air quality in a building
question
What is a Basic Service (community connectivity)
answer
Bank, place of worship, convenience store, grocery, day care, cleaners, fire station, beauty, hardware, laundry, library, medical/dental, senior care, park, pharmacy, post office, restaurant, school, theater, community center, fitness, museum
question
What standard can be used to calculate a baseline for on-site renewable energy? a) Green-e b) Commercial Building Energy Consumption Survey c) The Advanced Building Benchmarking Tool d) ASHRAE 62.1
answer
b) Commercial Building Energy Consumption Survey
question
Which reference standard sets limits on VOC for sealants? a) South Coast Air Quality Management District b) SMACNA c) Green Seal d) Green Label
answer
a) SCAQMD is used as the reference standard for mac VOC concentration in sealants as well as finishes, stains, and sealers Green label is the Carpet and rug institues' program and the reference standard that sets maximum VOC concentration for carpets and carpet padding CMACNA sets guidlines for buildings under construction to protect air quality Green Seal is used by LEED as a reference for low-VOC aerosols and paints
question
roducts that meet ISO 14000 standards are:
answer
environmentally preferable products
question
Which of the following is used to determine if a product is pre-consumer or post-consumer recycled content? A LEED Online Calculators B Local codes C ASHRAE 62.1 D ISO 14021
answer
D ISO 14021
question
Which of the following refrigerants has the least global warming potential? A HCFC-123 B CFC-11 C HFC-23 D CFC-12
answer
A HCFC-123
question
Who can view CIRs posted to USGBC? (Choose2) a) individuals with a USGBC account b) registered employees of USGBC companies c) LEED APs d) registered project team members
answer
B, D
question
LEED O&M references credits by function, which of the following are functional characteristic groups? a) adminstration b) materials in c) sustainable sites d) waste management e) water efficiency
answer
A, B
question
What is included in life-cycle cost calculations (choose 2) a) equipment b) facility alterations c) maintenance d) occupant transportation e) utilities
answer
c, e
question
For a credit uploaded to LEED online, what does a white check mark next to credit name indicate? a) being pursued, no documentation uploaded b) being pursued, some documentation uploaded, c) complete and ready for submission d) not being pursued
answer
B
question
What is the role of the TAC (choose 2) a) ensure technical soundness of LEED ref guide and training b) maintain technical rigor and consistency in the development of LEED credits c) resolve issues to maintain consistency across different LEED rating systems d) respond to CIRs submitted by LEED project teams
answer
A, C
question
A project teams choice of paint will not affect which of the following credits a) Heat island b) low-emitting materials c) material reuse d) rapidly renewable materials
answer
C
question
Which of the following requires an explanation of the proposed credit requirements? a) CIR submittal b) Innovation in Design exemplary performance submittal c) LEED credit equivalence submittal D) LEED Online letter template submital
answer
C
question
The international cost council (ICC) inclused which of the following codes? (Choose 3) a) building automation (IBAC) b) energy conservation (IECC) c) Lighting (ILC) d) Mechanical (IMC) e) Plumbing (IPC)
answer
B, D, E
question
hat is the minimum percentage of points a project team can earn to achieve LEED Platinum a) 70% b) 80% c) 90% d) 100%
answer
B
question
According to the Sustainable Building Technical Manua, which of the following are steps of an environmentally responsive design process? (choose 3) a) bid, B) design C) Post-design D) pre-design E) re-bid F) vendor selection
answer
A, B, D
question
The BOD must contain which of the following (choose 3) A) building materials selection B) indoor environmental quality criteria C) mechanical systems description D) process equipment energy consumption information E) references to applicable codes
answer
B, C, E