            Rising client expectations during execution of a project may lead to a condition known as
answer
        scope creep
question
            Five attributes that characterize a project include:
answer
        Performance, lifecycle, uniqueness, conflict, interdependencies
question
            With respect to project goals throughout the project's lifecycle, early in the lifecycle, the project team's focus should be on how to achieve the required ________.
answer
        performance
question
            An important implication of the project lifecycle concept is that a project will resist ________ of its existence
answer
        termination
question
            According to the authors, the prime objectives of project management are cost, time and
answer
        performance
question
            The text identifies two basic types of project selection models. They are
answer
        Numeric and nonnumeric
question
            If the NPV for a project is > 0, it indicates that the project will
answer
        Cover its hurdle rate
question
            The process of modeling a problem seeks to carve away the ________ from the bones of a problem
answer
        unwanted reality
question
            Reference to an external standard is necessary when taking an ________ measurement.
answer
        objective
question
            According to Wheelwright and Clark, ________ projects have objectives or deliverables that are only incrementally different in both product and process from existing offerings.
answer
        derivative
question
            The RFP solicitation document includes information about price and ________.
answer
        methodology
question
            The mechanism by which the people in organizations make decisions is known as ________.
answer
        politics
question
            According to the authors, a Type 2 project is
answer
        not well understood and not routine
question
            The project manager needs to possess technical and ________ credibility
answer
        administrative
question
            During the ________ stage of the project lifecycle, there is no significant difference in the importance that project managers place on the three goals of cost, time, and performance.
answer
        Design or formation stage
question
            A set of interrelated components that accept inputs and produce outputs in a purposeful manner is called a ________.
answer
        system
question
            During the build-up stage of a project lifecycle, __________is the dominant goal of many project managers.
answer
        schedule
question
            Culture contains the following four elements: technology, ________, language, and arts.
answer
        institutions
question
            Art is the aspect of culture that communicates the ________ of the culture
answer
        aesthetic values
question
            Within the organization, conflicts are viewed as
answer
        Conflicts between allies
question
            If a resource conflict arises between two high-priority projects, precedence is typically given to the project with the
answer
        Earliest due date
question
            During project formation, lack of ________ about the relative power/influence/authority of the PM and the functional managers is a major component of all conflicts involving technical decisions, resource allocation, and scheduling.
answer
        clarity
question
            The project should move from a general concept to a highly detailed set of plans during the project ________ phase.
answer
        build-up
question
            During project build-up, the project manager seeks a commitment of people from the functional departments when the ________ matrix organizational structure is used to manage the project.
answer
        strong
question
            During project build-up, the project manager seeks a commitment of work from the functional departments when the ________ matrix organizational structure is used to manage the project.
answer
        weak
question
            The need to manage technical interfaces and to correct incompatibilities is likely to create technical conflicts during the __________ phase of the project lifecycle.
answer
        main program
question
            The total level of conflict in the project lifecycle is the highest during the project _____ stage.
answer
        build-up