This project aims to construct an ideal Log Cabin- a small holiday house, in the garden of the property, which will have living space of sq feet for two bedrooms, a bathroom, a kitchen, and a sq feet terrace along with a garden. The budget allotted for this project is EYE,824.7. The goal of this project is to build an affordable log cabin by utilizing materials obtained from the property and minimizing the building time and cost by employing personal labor. This project aims to provide a relaxing holiday home for people living in cities like London who are deprived of fresh environmental areas for short breaks while minimizing the cost and maximizing efficiency of construction.

The log cabin construction is planned to commence on March 13th, 2014, and finish on May 7th, 2014, taking a tota

...

l of 48 days to build using a kit home. The milestones include a summary list with respective dates for each milestone. Additionally, an introductory paragraph is included in this section to provide insight into the major milestones. This section also covers the actions taken if any changes to the milestones or delivery dates are required.Understanding the terms related to project management is crucial for good management. It helps project managers accurately determine if a project is on schedule. The following is a budget table for a log cabin project, including various tasks such as digging out the ground, preparing for concrete, and assembling the basic cabin. There are different costs associated with labor, materials, equipment, and extras. The total cost of all tasks comes out to be 8977 and the log cabin budget is 39924.7

View entire sample
Join StudyHippo to see entire essay

with an assumption that the cost of small digger will be calculation per working day and the cost of labor can be calculated by half day. To plan and execute this project, we have utilized a work breakdown structure (WEBS) and gaunt chart to determine the start and end date and indent structure of various project stages. In addition, we have assessed the impact and created a contingency plan for quality control purposes.Developing a task-oriented work breakdown structure is preferred as it is simpler to understand and view projects as tasks. However, creating a deliverable-oriented WBS may serve the project better, especially with extensive management controls for log cabin plans. A Gaunt chart is a powerful visual device for conveying project schedules as it displays the work breakdown, completion rate, project milestones, cost, risk, and time estimates. To create a log cabin project plan, a breakdown structure is used to split tasks into building sub-tasks with hierarchal order. The project's start date is March 3rd, 2014, and the finish date is May 7th, 2014. Milestones are set up as deadlines for finishing tasks wherein a zero duration milestone represents the completion of a task.

The importance of milestones in a log cabin project lies in its ability to show important dates and key events, without affecting any Gaunt chart calculations. The Work Breakdown Structure (WEBS) is crucial in managing a complex log cabin project, as it helps to break down the project into manageable chunks, enabling effective estimation, while also helping stakeholders, suppliers, and labor understand the project scope.

Impact assessments are designed to help project managers identify risks in advance and implement mitigation strategies

from the outset. The most likely and high-impact risks are added to the project schedule, ensuring that assigned risk managers take necessary measures to implement appropriate responses during the schedule. This information also enables project managers to identify issues in the project plan and adapt accordingly.

The risk assessment process for a log cabin kit project involves identifying, scoring, and ranking potential risks. The bi-weekly project team meetings include status updates on assigned risks only when the meetings coincide with their planned timeshare.

During the project's closing process, the project manager will conduct an analysis of both the risks and risk management process. Through this evaluation, any potential enhancements to the future project’s risk management process will be identified and appended to the lessons learned knowledge base. The process will be completed upon the accomplishment of the project.

A Risk Assessment Form was used to identify potential risks on a construction site. The risks included weather changes which may cause project delays, employee sickness, accidents with fire, material problems, equipment tool damage, labor injury, and flooding and storm damage. The Risk Severity Matrix was used to determine the impact of these risks on the log cabin. A Risk Response and Contingency plan was then created to address each risk, with measures such as delaying the cabin if necessary, contracting with insurance companies, buying new equipment tools, requesting money from insurance, and having other professionals contracted. The plan also included buying insurance for labor and for damaging the log cabin, having materials to protect the construction site, redoing the project plan, and purchasing fire apparatuses tool if needed.Foam fire extinguishers and fire alarm systems are important

for protecting log cabin buildings. Foam spray extinguishers are effective for fires involving solid combustible materials and flammable liquids. It is recommended to set up a fire alarm system to inform the fire department in case of a fire. Any risks should be considered and a contingency plan should be established to mitigate or reduce them. The log cabin kit project should have a documented contingency plan with cost estimates and funding to manage potential risks. A total risk budget of E 3210 is expected, which may be affected by changes in supply funds. It is important to use good quality exterior wood treatment for building a log cabin, which can be found from reputable suppliers.

We contacted Equipment Tool Company to borrow good quality tools such as a Spirit Level, Screwdriver, Measuring Tape, Hammer, Saw, Pliers, Drill, Ladder, Clear Silicone and Assembly Drawings Protective Gloves. These tools will aid in constructing the log cabin building. Upon receiving the materials, we open the packages and sort the components according to the Wall Plans on the Installation Drawing and Component Specification. We also ensure that we have some extra components available in case of any damage during transit or assembly. One crucial step is to ensure that the base is level and square to guarantee that the log cabin can adequately support its load without any problems. A faulty base foundation will result in walls that are not straight and doors and windows that cannot be regulated.

Extra protection from storms can be achieved by fixing the foundation frame to the foundation using steel angles or anchors (fixtures that are supplied with the cabin). We ensure

that the frame is completely laid before attaching the log cabin to it. We also fix the lap joints with woodpeckers, check the diagonals, and perform any other necessary tasks to make sure everything is secured. Additionally, we apply an advanced lasting clear coat to retain the natural color and beauty of the timber while providing extra durability and a light golden hue. This step helps avoid damage from harsh weather conditions such as strong sunshine or heavy rain.

Finally, quality planning is essential for all items/tasks throughout this process. We typically check when delivery arrived and materials were received and then inspect each component to ensure it meets our standards.

To ensure the components are not damaged, it is important to open the packages and check them. Electrical safety is crucial, and completion requires connecting the electrics. It is beneficial to have a registered electrician who can self-certify their work and a skilled labor when employing someone. The manager should confirm employee qualifications such as skills, experience, and education.

When setting up a log cabin, assembling the basic structure is important for stability. Structural calculations are required to demonstrate stability in various situations of combined loadings such as winds and snow loads. Concrete base preparation is crucial for carrying out ground work. It is recommended to find a satellite company of qualified house builders who have built thousands of cabins over the past six years and laid hundreds of concrete bases.

Monitoring the progress of a log cabin project is a recurring task beginning in the planning stage. It is helpful to check progress against plans as monitoring can be used for evaluation purposes. Progress can

be measured in terms of scope, cost, time, quality, risk, communications, procurements, human resources, and integration using proper monitoring techniques.The Gaunt chart, which includes baseline and tracking measures, illustrates how the project manager establishes a baseline plan and monitors progress against a log cabin project plan to identify deviations, evaluate corrective measures, and take appropriate action. The project team also manages project risks throughout the log cabin project. The text is aligned to justify.