Project Integration Management – Flashcards
Unlock all answers in this set
Unlock answersquestion
Define Project Integration Management.
answer
The processes required to ensure that the various project elements are identified, combined, unified, and coordinated effectively. [Initiating, Planning, Executing, Monitoring and Controlling, and Closing]
question
What six major processes are included in Project Integration Management?
answer
Develop project charter, develop project management plan, direct and manage project work, monitor and control project work; perform integrated change control; and close project or phase. [Initiating, Planning, Executing, Monitoring and Controlling, and Closing]
question
List the one initiating process in Project Integration Management.
answer
Develop project charter. [Initiating]
question
What is the purpose of the direct and manage project work process?
answer
The process of leading and performing the work in the project management pan and implementing approved changes to achieve project objectives. [Executing]
question
What is meant by integrated change control?
answer
A formal process to review, approve, and manage changes to project deliverables, documents, organizational process assets, and the project management plan throughout the project and communicating their disposition. [Monitoring and Controlling]
question
What are two tools and techniques used to develop the project management plan?
answer
• Expert judgment. • Facilitation techniques. [Planning]
question
What is a major factor in making and prioritizing project selection decisions?
answer
The performing organization's strategic plan. [Initiating]
question
What are the four inputs to the develop project management plan process?
answer
• Project charter • Outputs from planning processes • Enterprise environmental factors • Organizational process assets [Planning]
question
What are the three categories of organizational process assets used in developing the project charter?
answer
• Organizational standards, processes, policies, and process definitions. • Templ ates. • Historical information and lessons learned knowledge base. [Initiating]
question
Provide five examples of the project management information system (PMIS) that can be used in direct and manage project work.
answer
• Scheduling software • Configuration management system • Information collection and distribution system • Web interface to other online automated systems • Work authorization system [Executing]
question
What is the purpose of the project charter?
answer
To authorize a project or a phase. It also documents the business needs, current understanding of the customer's needs and high-level requirements, assumptions and constraints, and the requirements for the project's new product, service, or result. It provides the project manager with the authority to apply organizational resources to the project. [Initiating]
question
In the close project process, what are the three updates to organizational process assets?
answer
• Project files • Project or phase closure documents • Historical information [Closing]
question
When should the project manager be identified and assigned?
answer
As early in the project as is feasible, but always prior to the start of project planning and preferably during project charter development. [Initiating]
question
What are three tools and techniques used in close project or phase?
answer
• Expert judgment • Analytical techniques • Meetings
question
What are the three items referenced in the project statement of work?
answer
• Business need • Product scope description • Strategic plan [Initiating]
question
Who should issue the project charter?
answer
The sponsor, PMO staff person, or a portfolio governing body chairperson, or an authorized representative at a level appropriate to procure funding and commit resources to the project. [Initiating]
question
What is a project management plan?
answer
A formal, approved document that defines how a project is executed, monitored and controlled, and closed. [Planning]
question
What does the project charter authorize the project manager to do?
answer
Authorizes the project manager to apply resources to project activities. [Initiating]
question
During which project integration management process is the majority of the project's budget spent?
answer
Direct and manage project work [Executing]
question
What is meant by corrective actions?
answer
An intentional activity that realigns performance of the project work with the project management plan [Executing and Monitoring and Controlling]
question
What is involved in the close project process?
answer
Finalizing all activities across all Project Management Process Groups to formally complete the phase or project [Closing]
question
What are the three tools and techniques for direct and manage project work?
answer
• Expert judgment • Project management information system • Meetings [Executing]
question
What is a deliverable?
answer
Any unique and verifiable product, result, or capability to perform a service that must be produced and provided to complete a process, phase, or the project itself. [Executing]
question
What are the five outputs from the direct and manage project work process?
answer
• Deliverables • Work performance data • Change requests • Project management plan updates • Project document updates [Executing]
question
Why is change control necessary on projects?
answer
Because projects rarely run exactly according to the project management plan. [Monitoring and Controlling]
question
What are three types of meetings?
answer
• Information exchange • Brainstorming, option evaluation, or design • Decision making [Executing and Monitoring and Controlling]
question
List three configuration management activities included in the integrated change control process.
answer
• Configuration identification • Configuration status accounting • Configuration verification and audit [Monitoring and Controlling]
question
What should be done if the project is terminated prior to completion?
answer
Document the reasons for actions taken if the project is terminated before completion. [Closing]
question
What is meant by a defect repair?
answer
An intentional activity to modify a nonconforming product or product component [Executing and Monitoring and Controlling]
question
What is an element of the project management plan that affects the perform integrated change control process?
answer
Change management plan as it provides direction for managing the change control process and documents the formal change control board [Planning and Monitoring and Controlling]
question
What are the seven inputs to the Monitor and Control Project Work process?
answer
• Project management plan • Schedule forecasts • Cost forecasts • Validated changes • Work performance information • Enterprise environmental factors • Organizational process assets [Monitoring and Controlling]
question
What is a change control board (CCB)?
answer
A group of people responsible for reviewing, evaluating, approving, delaying, or rejecting changes to a project and recording and communicating the decisions [Monitoring and Controlling]
question
What three items are part of the project approval requirements in the project charter?
answer
• What constitutes project success • Who decides if the project is a success • Who signs off on the project [Initiating]
question
What are the four inputs to perform integrated change control?
answer
• Approved change requests • Change log • Project management plan updates • Project document updates [Monitoring and Controlling]
question
List seven sources of expert judgment.
answer
• Other units in the organization • Consultants • Stakeholders, including customers or sponsors • Professional and technical associations • Industry groups • Subject matter experts • Project management office [Initiating]
question
How is expert judgment used in perform integrated change control?
answer
As a tool and technique. Experts serve on the change control board to approve, review, evaluate, delay, or reject changes to the project baselines. [Monitoring and Controlling]
question
List seven reasons for which a business case for a project may be created.
answer
• Market demand • Organizational need • Customer request • Technological advance • Legal requirement • Ecological impact • Social need [Initiating]
question
What is the primary objective of the business case?
answer
To help the organization determine if the project is worth the required investment. [Initiating]
question
What are three elements of the project management plan that may be used in integrated change control?
answer
• Scope management plan • Scope baseline • Change management plan [Planning and Monitoring and Controlling]
question
List three items that may be part of work performance information.
answer
• Status of deliverables • Implementation status for change requests • Forecasted estimate to complete [Executing and Monitoring and Controlling]
question
What is the difference between a standard and a regulation?
answer
A standard provides for common and repeated use, rules, guidelines, or characteristics for activities or results. A regulation is a government-imposed requirement for which compliance is mandatory. [Planning and Executing]
question
What is a change control system?
answer
A set of procedures that describes how modifications to the project deliverables and documentation are managed and controlled [Monitoring and Controlling]
question
Change requests are issued, and approved changes are implemented in which process?
answer
Direct and manage project work [Executing]
question
What are approved change requests?
answer
A change request that has been processed through the integrated change control process and approved [Executing and Monitoring and Controlling]
question
Why is a change log used?
answer
To document changes that occur during a project especially in terms of time, cost, and risk; it also includes rejected change requests [Monitoring and Controlling]
question
What are three examples of personnel administration as an enterprise environmental factor in the direct and manage project work process?
answer
• Hiring and firing guidelines • Employee performance reviews • Training records [Executing]
question
What is rolling wave planning?
answer
A progressive detailing of the project plan, providing detailed information about the work to be done in the current phase of the project and less information about the work to be done in later phases. [Planning]
question
When is work performance data collected?
answer
During the direct and manage project work process [Executing]
question
What are the four inputs to the direct and manage project work process?
answer
• Project management plan • Approved change requests • Enterprise environmental factors • Organizational process assets [Executing]
question
The administrative closure procedure provides a stepby-step methodology that addresses three actions and activities. List them.
answer
• Satisfying completion and exit criteria for the phase or project • Transferring the project's products, services, or results to the next phase or to production or operations • Collecting phase or project records, auditing project successes or failures, gathering lessons learned, and archiving project information [Closing]
question
What are the five categories of project management processes?
answer
• Initiating • Planning • Executing • Monitoring and Controlling • Closing [Initiating, Planning, Executing, Monitoring and Controlling, and Closing]
question
What is a project management office (PMO)?
answer
An organization structure that standardizes project related governance processes and facilitates the sharing of resources, methodologies, tools, and techniques [Initiating, Planning, Executing, Monitoring and Controlling, and Closing]
question
At what level in the organization should the Project Sponsor be located?
answer
At a level where the Project Sponsor is authorized to fund the project. [Planning]
question
What are three project documents that may be updated as a result of the monitor and control project work process?
answer
• Forecasts • Performance reports • Issue log [Monitoring and Controlling]
question
What four tools and techniques are used to monitor and control project work?
answer
• Expert judgment • Analytical techniques • Project management information systems • Meetings [Monitoring and Controlling]
question
What is the project statement of work and how is it used in the develop project charter process?
answer
A narrative description of the products, services, or results to be supplied by the project. It is an input to the develop project charter process. [Initiating]
question
Name five subsidiary plans of the project management plan.
answer
Five of any of the following: • Scope management • Requirements management • Schedule management • Cost management • Quality management • Process improvement • Human resource • Communications management • Risk management • Procurement management • Stakeholder management [Planning]
question
What are three baselines that form the project baseline?
answer
• Scope baseline • Schedule baseline • Cost baseline [Planning]
question
When is the project management information system first introduced?
answer
Direct and manage project work process [Executing]
question
Provide four examples of items in the lessons learned knowledge base.
answer
• Project records and documents • Project closure information and documents • Results of previous project selection decisions and performance information • Information from risk management activities [Closing]