PMBOK Ch 6- Project Time Management – Flashcards
Unlock all answers in this set
Unlock answersquestion
process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule. -guidance
answer
(6-1)Plan Schedule Management
question
The ____ processes and their associated tools and techniques for each process are documented in the schedule management plan.
answer
Project Time Management
question
a subsidiary plan of the project management plan through the Develop Project Management process.
answer
schedule management plan
question
a representation of the plan for executing the project's activities including durations, dependencies, and other planning information (refer to practice standard for scheduling*)
answer
schedule model
question
process of identifying and documenting the specific actions to be performed to produce the project deliverables.
answer
(6-2) Define Activities
question
process of identifying and documenting relationships among the project activities.
answer
(6-3) Sequence Activities
question
process of estimating the type and quantities of material, human resources, equipment, or supplies required to perform each activity
answer
(6-4) Estimate Activity Resources
question
process of estimating the number of work periods needed to complete individual activities with estimated resources
answer
(6-5) Estimate Activity Durations
question
process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model
answer
(6-6) Develop Schedule
question
process of monitoring the status of project activities to update project progress and manage changes to the schedule baseline to achieve the plan
answer
(6-7) Control Schedule
question
(6-1) Plan Schedule Management Inputs -_______ -_______ -_______ -_______ Tools & Techniques -expert judgement -analytical techniques -_______ Outputs -__________
answer
Project management plan; Project Charter; Enterprise environmental factors; Organizational process assets; meetings; schedule management plan
question
(6-2) Define Activities Inputs -______ -______ -______ environmental factors -_Organizational _____ Tools & Techniques -______ -______ -______ Outputs -______ -______ -______
answer
Schedule management plan; Scope baseline; Enterprise; organizational; Decomposition; Rolling wave planning; expert judgement; Activity list; Activity attributes; Milestone list
question
(6-3) Sequence activities Inputs -_______ -_______ -______ -______ -______ -Enterprise environmental factors -Organizational process assets Tools & Techniques -______ -______ -______ Outputs -_______ -_______
answer
Schedule management plan; activity list; activity attributes; milestone list; project scope statement; precedence diagramming method (PDM); dependency determination; leads and lags; project schedule network diagrams; project documents updates
question
(6-4) Estimate Activity Resources Inputs -Schedule Management Plan -_______ -_______ -________ -_______ -_______ -_______ -Enterprise environmental factors _Organization process assets Tools & Techniques -Expert judgement -______ -______ -_______ -______ Outputs -______ -______ -______
answer
activity list; activity attributes; resource calendars; risk register; activity cost estimates; alternative analysis; published estimating data; bottom-up estimating; project management software; activity resource requirements; resource breakdown structure; project documents updates
question
(6-5) Estimate Activity Durations Inputs -Schedule management plan -_________ -_________ -_________ -________ -_________ -________ -________ -Enterprise environmental factors -Organizational process assets
answer
activity list; activity attributes; activity resource requirements; resource calendars; project scope statement; risk register; resource breakdown structure
question
(6-6) Develop Schedule Inputs -Schedule management plan -Activity list -Activity attributes -_______ -_______ -_______ -_______ -________ -________ -_______ -_______ -Enterprise environmental factors -Organizational process assets Tools & Techniques -_____ -_____ -______ -______ -______ -_____ -______ -______ Outputs -______ -______ -______ -______ -______ -______
answer
activity resource requirements; resource calendars; activity duration estimates; project scope statement; risk register; project staff assignments; resource breakdown structure; schedule network analysis; critical path method; critical chain method; resource optimization techniques; modeling techniques; leads and lags; schedule compression; scheduling tool; scheduling baseline; project schedule; schedule data; project calendars; project management plan
question
(6-7) Control Schedule Inputs -Project management plan -_____ -_____ -_____ -_____ -Organizational process assets Tools & Techniques -______ -_____ -_____ -_____ -_____ -_____ -_____ Outputs -_____ -_____ -_____ -_____ -_____ -Organizational process assets updates
answer
project schedule; work performance data; project calendars; schedule data; performance reviews; project management software; resource optimization techniques; leads and lags; schedule compression; scheduling tool; work performance information; schedule forecasts; change requests; project management plan updates; project documents update;
question
Some of the better known scheduling methods include: (2)
answer
critical path method (CPM) and critical chain method (CCM)
question
activity list, bar chart, and network diagram
answer
Examples of Project Schedule Presentations
question
Includes the project scope statement and the WBS details used for: defining activities duration estimation schedule management other information- "other scheduling related cost, risk, and communications decisions"
answer
scope baseline
question
(Plan Schedule Management: Inputs) defines the summary milestone schedule and project approval requirements
answer
project charter
question
-Monitoring/reporting tools to be used -Historical information -Schedule control tools -Existing formal and informal schedule control related policies, procedures, & guidelines -Templates -Project closure guidelines -Change control procedures -Risk control procedures (risk categories, probability & impact definitions, and probability & impact matrix
answer
organizational process assets
question
Guided by historical info., it provides valuable insight about the environment and info. from prior SIMILAR projects -Experts skilled in WBS, project schedules, etc.
answer
expert judgement
question
-scheduling methodology -scheduling tools & techniques -estimating approaches -formats
answer
analytical techniques
question
Project teams may hold ___ to develop the schedule management plan.
answer
meetings
question
(Plan Schedule Management: Outputs) The scheduling methodology and the scheduling tool to be develop the project schedule model
answer
Project schedule model development
question
(Plan Schedule Management: Outputs) The acceptable range used in determining realistic activity duration estimates is specified and may include an amount for contingencies.
answer
Level of accuracy
question
(Plan Schedule Management: Outputs) Each unit used in measurements is defined for each of the resources (staff hours/days/weeks, or meters/liters/tons, cubic yards) time measure or quantity measure
answer
Units of measure
question
(Plan Schedule Management: Outputs) The WBS provides the framework for the schedule management plan.
answer
Organizational procedure links
question
(Plan Schedule Management: Outputs) The process used to update the status and record progress of the project in the schedule model during the execution of the project.
answer
Project schedule model maintenance
question
(Plan Schedule Management: Outputs) Variance thresholds for monitoring schedule performance may be specified to indicate an agreed-upon amount of variation to be allowed before some action needs to be taken. Percentage deviations from parameters established in baseline plan
answer
Control thresholds
question
(Plan Schedule Management: Outputs) Earned value management (EVM) rules or other physical measurement rules of performance measurement are set
answer
Rules of performance measurement
question
(Plan Schedule Management: Outputs) The formats and frequency for the various schedule reports are defined.
answer
Reporting formats
question
(Plan Schedule Management: Outputs) Descriptions of each of the schedule management processes are documented.
answer
Process descriptions
question
-Lessons learned knowledge -Standardized processes -Templates -formal/informal activity that already exist
answer
Organizational process assets (input)
question
-Organizational cultures & structure -Published commercial information from commercial databases -PMIS
answer
Enterprise Environmental Factors (input)
question
(Define Activities: Tools & Techniques) _____ is a technique used for dividing and subdividing the project scope and project deliverables
answer
Decomposition
question
(Define Activities: Tools & Techniques) The activity list, WBS, and WBS dictionary can be developed either sequentially or concurrently, with the ___ and _____ as the basis for development of the final activity list.
answer
WBS; WBS dictionary
question
(Define Activities: Tools & Techniques) an iterative planning technique in which the work to be accomplished in the near term is planned in detail, while the work in the future is planned at a higher level.
answer
Rolling wave planning (progressive elaboration)
question
(Define Activities: Outputs) a comprehensive list that includes all schedule activities required on the project for each activity Includes: -activity identifier -scope of work activity in sufficient detail
answer
Activity list
question
(Define Activities: Outputs) -activity identifier(ID) -WBS ID -label/name -codes* -description* -predecessor* -successor* -leads & lags* -resource requirements* -imposed dates* -constraints* -assumptions*
answer
Activity attributes
question
(Outputs) a list identifying all project milestones and indicates whether the milestone is mandatory(contract, optional) such as those based upon historical information. "have 0 duration. represent moments".
answer
Milestone list
question
(Outputs) a significant point/event in a project.
answer
milestone
question
The process of identifying and documenting relationships among the project activities. Defines the logical sequence of work to obtain greatest efficiency given all project straints.
answer
Sequence Activities (6-3)
question
a technique used for constructing a schedule model in which activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are to be performed.
answer
Precedence diagramming method (PDM)
question
A ____ activity is an activity that logically comes before a dependent activity in a schedule. A ___ activity is a dependent activity that logically comes after another activity in a schedule.
answer
predecessor; successor
question
a logical relationship in which a successor activity cannot start until a predecessor activity has finished.
answer
Finish-to-start (FS) PDM)
question
a logicaly relationship in which a successor activity cannot finish until a predecessor activity has finished.
answer
Finish-to-finish (FF) (PDM)
question
a logical relationship in which a successor activity cannot start until a predecessor activity has started.
answer
Start-to-start (SS) (PDM)
question
a logical relationship in which a successor activity cannot finish until a predecessor activity has started. rarely used*
answer
Start-to-finish (SF) (PDM)
question
(Sequencing Activities: Dependency Determination) dependencies that are legally/contractually required or inherent in the nature of work. -phsyical limitations
answer
Mandatory dependencies
question
(Sequencing Activities: Dependency Determination) sometimes referred to as preferred logic, preferential logic, or soft logic. Based on knowledge of best practices within a particular application area or some unusual aspect of the project where a specific sequence is desired.
answer
Discretional dependencies
question
(Sequencing Activities: Dependency Determination) Involve a relationship between project activities and non-project activities. . Usually outside of project team's control.
answer
External dependencies
question
Involve a precedence relationship between project activities and are generally inside the project team's control.
answer
Internal dependencies
question
the amount of time whereby a successor activity can be advanced with respect to a predecessor activity.
answer
Lead
question
the amount of time whereby a successor activity will be delayed with respect to a predecessor activity.
answer
Lag
question
(Sequence Activities: Outputs) a graphical representation of the logical relationships -summary narrative may accompany it.
answer
Project Schedule Network Diagrams
question
A ____ project team will need to be familiar with local building codes.
answer
construction
question
(Estimate Activity Resources: Inputs) a calendar that identifies the working days and shifts on which each specific resource is available.
answer
Resource calendars
question
(Estimate Activity Resources: Inputs) Risk events may impact resource selection and availability. Updates to the _____ are included with project documents updates.
answer
Risk register
question
(Estimate Activity Resources: Inputs) the cost of resources may impact resource selection.
answer
Activity cost estimates
question
Many schedule activities have alternative methods of accomplishment.
answer
Alternative analysis
question
(Estimate Activity Resources: Tools & Techniques) Several organizations routinely publish updated production rates and unit costs resources for an extensive array of labor trades, material, and equipment for different countries and geographical locations within countries.
answer
Published estimating data
question
(Estimate Activity Resources: Tools & Techniques) a method of estimating project duration or cost by aggregating the estimates of the lower-level components of the WBS.
answer
Bottom-up estimating
question
(Estimate Activity Resources: Tools & Techniques) has the capability to help plan, organize, and manage resource pools and dvelop resource estimates.
answer
Project management software
question
(Estimate Activity Resources: Outputs) identify the types and quantities of resources required for each activity in a work package.
answer
Activity resource requirements
question
is a hierarchical representation of resources by category and type. -labor -material -equipment -supplies
answer
Resource breakdown structure
question
Project documents that may be _____ include, but are not limited to: -Activity list -Activity attributes -Resource calendars
answer
updated (Output-Project document updates)
question
(Estimate Activity Durations: Tools & Techniques) a technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project. Uses parameters(duration, budget,, size, etc.) from a previous SIMILAR project
answer
Analogous estimating
question
(Estimate Activity Durations: Tools & Techniques) an estimating technique in which an algorithm is used to calculate cost or duration based on historical data and project parameters. Uses statistical relationship between historical data and other variables to calculate an estimate for activity parameters(budget, duration, etc.)
answer
Parametric estimating