ISDS 3115 – Flashcards

Unlock all answers in this set

Unlock answers
question
The ES of an activity that only has one predecessor is simply the EF of that predecessor.
answer
TRUE
question
One phase of a large project is scheduling.
answer
TRUE
question
A project organization works best for an organization when the project resides in only one of its functional areas.
answer
FALSE
question
By their very nature, projects have a limited lifetime, and that sets project mgt apart from the mgt of more traditional activites.
answer
TRUE
question
One responsibility of a project manager is to make sure that the project meets its quality goals.
answer
TRUE
question
Work Breakdown Structure is a useful tool in project mgt because it addresses the timing of individual work elements.
answer
FALSE
question
Project mangers have their own code of ethics, established by the Project Management Institute.
answer
TRUE
question
Ethical issues which can arise in projects include bid rigging, bribery, and "low balling".
answer
TRUE
question
Gantt charts give a timeline of a project's activities, but do not adequately show the interrelationship of activities.
answer
TRUE
question
PERT, but not CPM, has the ability to consider the precedence relationships in a project.
answer
FALSE
question
The shortest of all paths through the network is the critical path.
answer
FALSE
question
The findamental difference between PERT and CRM is that PERT uses the beta distribution fo rcrashing projects while CPM uses cost estimates.
answer
FALCE
question
Slack is the amount of time an activity can be delayed without delaying the entire project.
answer
TRUE
question
Every network has at least one critical path.
answer
TRUE
question
The critical path can be determined by use of either the "forward pass" or the "backward pass".
answer
FALSE
question
The PERT pessimistic time estimate is an estimate of the minimum time an activity will require.
answer
FALSE
question
The standard deviation of project duration is the average of the standard deviation of all activities on the critical path.
answer
FALSE
question
In PERT analysis, the identification of the critical path can be incorrect if a noncritical activity takes substantially more than its expected time.
answer
TRUE
question
Shortening the project's duration by deleting unnecessary activities is called "project crashing"
answer
FALSE
question
In project management, crashing an activity must consider the impact on all paths in the network.
answer
TRUE
question
Which of the following statements regarding Bechtel is TRUE?
answer
ALL OF THE ABOVE ARE TRUE (its competitive advantage is project management, Bechtel was the construction contractor for the Hoover Dam, bechtel's procurement program is global in nature, AND while helping to rebuild Iraq, Bechtel's crews had to travel under armed escort)
question
Which of the following statements about Bechtel is true?
answer
Bechtel is the world's premier manager of massive construction and engineering project
question
The phases of project management are:
answer
planning, scheduling, and controlling
question
A project organization
answer
A and E are both true (is effective for companies with multiple large projects AND is formed to ensure that programs/projects get proper management and attention)
question
Which of the following statements regarding project management is false?
answer
Project organization works well when the work contains simple, independent tasks.
question
A code of ethics especially for project managers :
answer
has been established by the Project Management Institute
question
Divulging information to some bidders on a project to give them an unfair advantage
answer
is known as bid rigging
question
Ethical issues that may arise in projects large and small include:
answer
all of the above (bid rigging, expense account padding, compromised safety or health standards, AND bribery
question
Which of the following statements regarding Gantt charts is true?
answer
Gantt charts are visual devices that show the duration of activities in a project.
question
Which of the following statements regarding critical paths is true?
answer
On a specific project, there can be multiple critical paths, all with exactly the same duration
question
Which of the following statements regarding CPM is true?
answer
All activities on the critical path have their LS equal to their predecessors EF
question
A simple CPM network has three activities, A, B, and C. A in an immediate predecessor of B and C. B is an immediate predecessor of C. The activity durations are A=4, B=3, C=8.
answer
The critical path is A-B-C, duration 15.
question
A simple CPM network has three activities, D, E, and F. D is an immediate predecessor of E and of F. E is an immediate predecessor of F. The activity durations are D=4, E=3, and F=8.
answer
The critical path is D-E-F, duration 15
question
A simple CPM network has five activities, A, B, C, D, and E. A is an immediate predecessor of C and D. B is an immediate predecessor of C and of D. C and D are both immediate predecessors of E.
answer
There are four paths in this network.
question
Activity D on a CPM network has predecessors B and C, and has successor F. D has duration 6. B's earliest finish is 18, while c's is 20. F's late start is 26. Which of the following is tru?
answer
D is critical, and has zero slack.
question
Which of the following statements regarding CPM networks is TRUE?
answer
If a specific project has multiple critical paths, all of them have the same duration.
question
Activity M on a CPM network has predecessors N and R, and has sucessor S. M has duratino 5. N's late finish is 18, while R's is 20. S's late start is 14. Which of the following is true?
answer
The last start time of S is impossible.
question
Which of the following statements concerning CPM activities is FALSE?
answer
The late finish of an activity is the earliest late start of all preceding activities.
question
The-------distribution is used by PERT analysis to calculate expected activity times and variances.
answer
Beta
question
The expected activity time in PERT analysis is calculated as
answer
the weighted average of A, M, and B, with M weighted 4 times as heavily as A and B
question
Which of the following statements regarding PERT times is true?
answer
The optimistic time is an estimate of the minimum time an activity will require.
question
Which of the folllowing statements regarding PERT times is TRUE?
answer
The probablye time estimate is calculates as t= (a + 4m +b)/6
question
The Beta distribution is used in project management to
answer
NONE OF THE ABOVE (calculate slack on activities not on the critical path, calculate the probability that a project will be completed within its budget, calculate pessimistic and optimistic activity times, and determine which activity should be crashed)
question
The Beta distribution is used in project management to:
answer
calculate expected activity times.
question
In a PERT network, non-critical activities that have little slack need to be monitored closely
answer
because near-critical paths could become critical paths with small delays in these activities
question
Which of the following statements regarding PERT analysis is TRUE?
answer
Only critical activities contribute to the project variance.
question
A project being analyzed by PERT has 60 activities, 13 of which are on the path. If the estimated time along the critical path is 214 days with a project variance of 100, the probability that the project will take 224 days or more to complete is:
answer
0.1587
question
An activity on a PERT network has these time estimates: optimistic=2, most likely=5, and pessimistic=10. Its expected time is
answer
5.33
question
An activity on a PERT network has these time estimates: optimistic=1, most likely=2, and pessimistic=5. Its expected time is
answer
2.33
question
An activity on a PERT network has three time estimates: optimistic=2, most likely=3, and pessimistic=8. Its expected time and variance (if its a critical activity) are
answer
3.67, 1
question
A local project being analyzed by PERT has 42 activities, 12 of which are one the critical path. If the estimated time along the critical path is 105 days with a project variance of 25, the probablility that the project will be completed in 95 days or less is.
answer
0.0228 (if need more practice-54)
question
Analysis of a PERT problem shows the estimated time for the critical path to be 108 days with a variance of 64. There is a .90 probability that the project will be completed before approximately day
answer
118 (if need more 60)
question
Contract requirements state that a project must be completed within 180 working days, or it will incur penalties for late completion. Analysis of the activity network reveals an estimated project time of 145 working days with a project variance of 400. What is the probability that the project will be completed before the late payment deadline?
answer
0.9599
question
Which of these statements regarding time-cost tradeoffs in CPM networks is TRUE?
answer
crashing shortens the project duration by assigning more resources to one or more of the critical tasks.
question
What was the name of the construction project to rebuild the Pentagon after the terrorist attacks on Sept. 11, 2001?
answer
Project Phoenix
question
Which of the following statements regarding time-cost tradeoffs in CPM networks is FALSE?
answer
Crashing sometimes has the reverse result of lengthening the project duration
question
If an activity whose normal duration is 13 days can be shortened to 10 days for an added cost of $1500, the crash cost per period is
answer
$500 (look at 67)
question
If an activity whose normal duration is 15 days can be shortened to 10 days for an added cost of $2,000, the crash cost per period is
answer
$400
question
A network has been crashed to the point where all activities are critical. Additional crashing:
answer
may require crashing multiple tasks simultaneously
Get an explanation on any task
Get unstuck with the help of our AI assistant in seconds
New