Intro to Project Management Chapter 4 – Flashcards

Unlock all answers in this set

Unlock answers
question
activity attributes
answer
Information that provides schedule-related information about each activity, such as predecessors. successors, logical relationships. leads and lags, resource requirements, constraints, imposed dates, and assumptions related to the activity.
question
activity list
answer
A tabulation of activities to be included on a project schedule.
question
activity-on-arrow (AOA)
answer
A network diagramming technique in which activities are represented by arrows and connected at points called nodes to illustrate the sequence of activities.
question
arrow diagramming method (ADM)
answer
A network diagramming technique in which activities are represented by arrows and connected at points called nodes to illustrate the sequence of activities.
question
analogous estimates / top-down estimates
answer
The estimates that use the actual cost of a previous, similar project as the basis for estimating the cost of the current project.
question
baseline
answer
A starting point, a measurement, or and observation that is documented so that it can be used for future comparison; also defined as the original project plans plus approved changes.
question
bottom-up estimates
answer
Cost estimates created by estimating individual activities and summing them to get a project total.
question
buffer
answer
Additional time to complete a task, added to an estimate to account for various factors.
question
burst
answer
An occurrence when two or more activities follow a single node on a network diagram.
question
cost baseline
answer
A time-phased budget that project managers use to measure and monitor cost performance.
question
crashing
answer
A technique for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost.
question
critical chain scheduling
answer
A method of scheduling that takes limited resources into account when creating a project schedule and includes buffers to protect the project completion date.
question
critical path method (CPM) / analysis
answer
A networking diagramming techniques used to predict total project duration.
question
dependency / relationship
answer
The sequence of project activities or tasks.
question
discretionary dependencies
answer
The dependencies that are defined by the project team.
question
duration
answer
The actual amount of time spent working on an activity plus elapsed time.
question
effort
answer
The number of workdays or work hours required to complete a task.
question
external dependencies
answer
The dependencies that involve relationships between project and non-project activities.
question
fast tracking
answer
A scheduling compression technique where you do activities in parallel that you would normally do in sequence.
question
feeding buffers
answer
Additional time added before tasks on the critical path that are preceded by non-critical path tasks.
question
Gantt charts
answer
A standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a calendar format.
question
mandatory dependencies
answer
The dependencies that are inherent in the nature of the work being performed on a project.
question
merge
answer
A situation when two or more nodes precede a single node on a network diagram.
question
milestone
answer
A significant event on a project.
question
multitasking
answer
When a resource works on more than one tasks at a time.
question
Murphy's Law
answer
If something can go wrong, it will.
question
network diagram
answer
A schematic display of the logical relationships among or sequencing of project activities.
question
node
answer
The starting and ending of an activity-on-arrow network diagram.
question
parametric modeling
answer
A technique that uses project characteristics (parameters) in a mathematical model to estimate project cost.
question
Parkinson's Law
answer
Work expands to fill time allowed.
question
precedence diagramming method (PDM)
answer
A network diagramming technique in which boxes represent activities.
question
Program Evaluation and Review Technique (PERT)
answer
A network analysis technique used to estimate project duration when there is a high degree of uncertainty about the individual activity duration estimates
question
project buffer
answer
The additional time added before a project's due date to account for unexpected factors.
question
project management plan
answer
A document which is a deliverable for the project integration management knowledge area, used to coordinate all project planning documents and to help guide a project's execution and control.
question
scope baseline
answer
The approved project scope statement and its associated WBS and WBA dictionary
question
scope management plan
answer
A document that includes descriptions of how the team will prepare the project scope statement , create the WBS, verify completion if the project deliverables, and control requests for changes to the project scope.
question
slack / float
answer
The amount of time an activity may be delayed without delaying a succeeding activity or the project finish date.
question
team contract
answer
A document created to help promote team work and clarify team communications.
question
Theory of Constraints (TOC)
answer
A management philosophy that states that any complex system at any point in time often has only one aspect or constraint that is limiting its ability to achieve more of its goal.
question
three-point estimate
answer
An estimate that includes an optimistic, most likely and pessimistic estimate.
question
work breakdown structure (WBS)
answer
A deliverable-oriented grouping of the work involved in a project that defines the total scope of the project.
question
work breakdown structure (WBS) dictionary
answer
A document that describes detailed information about WBS tasks.
question
work package
answer
A task at the lowest level of the WBS.
question
requirement
answer
a condition or capability that must be met or possessed by a system, product, service, result, or component to satisfy a contract, standard, specification, or other formal document
question
requirements management plan
answer
a plan that describes how project requirements will be analyzed, documented, and managed.
question
requirements tractability matrix (RTM)
answer
A table that lists requirements, various attributes of each requirement, and the status of the requirements to ensure that all of them are addressed.
question
Scope Creep
answer
The tendency for project scope to continually increase
question
Critical path
answer
The series of activities that determine the earliest by which the project can be completed; it is the longest path through the network diagram and has the least amount of slack or float
question
Organizational process assets
answer
Policies and procedures related to project management, past project files, and lessons-learned reports from previous, similar projects
question
Execution
answer
The main purpose of project planning is to guide ______.
question
"you plan to fail?"
answer
End of the saying, "If you fail to plan..."
question
all of them
answer
Number of knowledge areas that include planning processes
question
planning
answer
Often the most difficult and unappreciated process in project management
question
gets managed
answer
End of the saying, "What gets measured..."
question
project management plan
answer
Plan that coordinates all other project plans
question
team contract
answer
Document created to help promote teamwork and clarify team communications (a ________ contract)
question
baseline
answer
A starting point or measurement that can be used for future comparison
question
dynamic or flexible
answer
As opposed to static, project management plans should be this
question
variable
answer
The length of a project management plan is ______.
question
meeting
answer
The ______ guidelines section of a team contract describes items like arranging telephone or video-conferencing, developing and following agendas, etc.
question
subsidiary plans
answer
Other plans that the project management plan refers to, such as the scope management plan, risk management plan, etc. are called ________ plans
question
work package
answer
Lowest level of the WBS
question
work breakdown structure
answer
Meaning of the acronym WBS
question
scope
answer
The _____ management plan involves defining and controlling what work is or is not included in the project
question
statement
answer
The project scope ______ defines the scope of a project
question
mind mapping
answer
approach for creating a WBS that that uses branches radiating out from a core idea to structure thoughts and ideas
question
activities
answer
Process in project time management that seems more like a scope task - defining ________
question
milestone
answer
A significant event on a project
question
SMART
answer
Acronym for creating milestones that are specific, measureable, assignable, realistic, and time-framed
question
critical
answer
Shows the shortest time in which a project can be completed; also the longest path through a network diagram - the ______ path
question
chain
answer
A method of scheduling that considers limited resources when creating a project schedule - critical ____ scheduling
question
parametric
answer
Type of estimate that uses project characteristics in a mathematical model, such as number of square feet of a house
question
cost budgeting
answer
Allocating the overall cost estimate to individual tasks over time
question
bottom-up estimate
answer
Type of estimate that can be very accurate but also very expensive to create
question
analogous or top-down
answer
Type of estimate that uses the actual costs of a similar project as its basis
question
baseline
answer
A time-phased budget that project managers use to measure and monitor cost performance - a cost ______
question
guide project execution
answer
The main purpose of project planning is to
question
85-90%
answer
EI accounts for ______ of the difference between outstanding leaders and their more average peers.
question
emotion
answer
When dealing with people, remember you are not dealing with creatures of logic, but creatures of ______
question
Self-awareness Self-management Social-Awareness Relationship Management
answer
Four Dimensions to Emotional Intelligence
question
Mindfulness
answer
being aware of our own inner experience (attuned to self), and paying attention to what is happening around us (attuned to others and the world around us).
Get an explanation on any task
Get unstuck with the help of our AI assistant in seconds
New