EVM – Flashcards

Unlock all answers in this set

Unlock answers
question
Earned Value Management (EVM)
answer
is a tool that allows both Government and contractor Program Managers (PMs) to have visibility into technical, cost, and schedule planning, performance, and progress on their contracts.
question
Cost Variance =
answer
BCWP - ACWP
question
Schedule Variance =
answer
BCWP - BCWS
question
Cost Performance Index =
answer
BCWP/ACWP
question
Schedule Performance Index =
answer
BCWP/BCWS
question
Contracts of _______ or more require a formal EVM system validation
answer
$50M
question
Earned Value Management (EVM)
answer
is an integrated management system; coordinates work scope, schedule, and budget goals, and objectively measures progress towards these goals.
question
The Defense Contract Management Agency (DCMA)
answer
is the only organization recognized by DoD to perform EVMS Validation.
question
The Defense Contract Audit Agency (DCAA)
answer
is responsible for conducting audit reviews of the contractor's accounting system policies, procedures, and activities.
question
For contract's awarded prior to July 1, 2012, the Contract Performance Report (CPR)
answer
is a contractually required report, prepared by the contractor, containing performance information derived from the internal EVMS.
question
For contracts awarded after July 1, 2012 the Integrated Program Management Report (IPMR)
answer
has replaced the Contract Performance Report (CPR) and Integrated Master Schedule (IMS) contractual requirements
question
The Defense Contract Audit Agency (DCAA) is
answer
responsible for conducting audit reviews of the contractor's accounting system policies, procedures, and activities.
question
For contract's awarded prior to July 1, 2012,
answer
the Contract Performance Report (CPR) is a contractually required report, prepared by the contractor, containing performance information derived from the internal EVMS.
question
For contracts awarded after July 1, 2012 the Integrated Program Management Report (IPMR)
answer
has replaced the Contract Performance Report (CPR) and Integrated Master Schedule (IMS) contractual requirements
question
Cost Variance (CV) indicates how much
answer
over or under budget the project is
question
Schedule Variance indicates how much
answer
ahead or behind schedule the project is
question
Cost Performance Index (CPI) measures how efficiently
answer
the contractor is performing the work based on the original planned budget.
question
the basic elements of performance measurement
answer
is the comparison of actual performance against a baseline plan.
question
PMB development follows a 3 step process:
answer
Define the work (WBS) Schedule the work Allocate budgets
question
The Performance Measurement Baseline (PMB) is the sum of the time-phased BCWS
answer
for all work, planning, and summary level packages.
question
The PMB is the contractor's time-phased plan for accomplishing the work on the contract.
answer
It establishes the scope, schedule, and budget targets for the program.
question
Control accounts are management points for planning and control since
answer
they represent the work assigned to one responsible organizational element on one program WBS.
question
"Mini-Programs" having
answer
defined scope, schedule, and budget.
question
Understand the difference in the methods to measure performance against the Performance Measurement Baseline
answer
0-100 Method: Once job is finished, value is earned (short duration) 50/50 Method: Earn 50% when start, earn 50% when completed Value Milestone Method: Assign budgets to milestones and earn as each milestone is reached Completed or Equivalent Unit Method: Count units being fabricated or completed operations that go into a unit Planning Package (Rolling Wave): Lock in budgets prior to beginning work.
question
Labor Costs:
answer
Occur at work package level, recording man-hours on time cards (or equivalent method).
question
The Integrated Baseline Review
answer
Is a formal review conducted jointly between the Government and contractor Assesses the validity of control account budgets, resources, and time phasing Is mandatory for all EVMS contracts Is a process, not an event Ensures work package technical content consistent with contract SOW
question
DCMA performs two major types of EVMS surveillance
answer
System Surveillance Program / Contract Surveillance
question
The 32 EVMS guidelines in ANSI/EIA-748
answer
provide a framework to evaluate the adequacy of a contractor's EVM system.
question
Recognize the nine management processes associated with EVM
answer
Organizing Scheduling Work/Budget Authorization Accounting Indirect Management Managerial Analysis Change Incorporation Materiel Management Sub-contract Management
Get an explanation on any task
Get unstuck with the help of our AI assistant in seconds
New