EVM – Flashcards
Unlock all answers in this set
Unlock answersquestion
            Earned Value Management (EVM)
answer
        is a tool that allows both Government and contractor Program Managers (PMs) to have visibility into technical, cost, and schedule planning, performance, and progress on their contracts.
question
            Cost Variance =
answer
        BCWP - ACWP
question
            Schedule Variance =
answer
        BCWP - BCWS
question
            Cost Performance Index =
answer
        BCWP/ACWP
question
            Schedule Performance Index =
answer
        BCWP/BCWS
question
            Contracts of _______ or more require a formal EVM system validation
answer
        $50M
question
            Earned Value Management (EVM)
answer
        is an integrated management system; coordinates work scope, schedule, and budget goals, and objectively measures progress towards these goals.
question
            The Defense Contract Management Agency (DCMA)
answer
        is the only organization recognized by DoD to perform EVMS Validation.
question
            The Defense Contract Audit Agency (DCAA)
answer
        is responsible for conducting audit reviews of the contractor's accounting system policies, procedures, and activities.
question
            For contract's awarded prior to July 1, 2012, the Contract Performance Report (CPR)
answer
        is a contractually required report, prepared by the contractor, containing performance information derived from the internal EVMS.
question
            For contracts awarded after July 1, 2012 the Integrated Program Management Report (IPMR)
answer
        has replaced the Contract Performance Report (CPR) and Integrated Master Schedule (IMS) contractual requirements
question
            The Defense Contract Audit Agency (DCAA) is
answer
        responsible for conducting audit reviews of the contractor's accounting system policies, procedures, and activities.
question
            For contract's awarded prior to July 1, 2012,
answer
        the Contract Performance Report (CPR) is a contractually required report, prepared by the contractor, containing performance information derived from the internal EVMS.
question
            For contracts awarded after July 1, 2012 the Integrated Program Management Report (IPMR)
answer
        has replaced the Contract Performance Report (CPR) and Integrated Master Schedule (IMS) contractual requirements
question
            Cost Variance (CV) indicates how much
answer
        over or under budget the project is
question
            Schedule Variance indicates how much
answer
        ahead or behind schedule the project is
question
            Cost Performance Index (CPI) measures how efficiently
answer
        the contractor is performing the work based on the original planned budget.
question
            the basic elements of performance measurement
answer
        is the comparison of actual performance against a baseline plan.
question
            PMB development follows a 3 step process:
answer
        Define the work (WBS)  Schedule the work  Allocate budgets
question
            The Performance Measurement Baseline (PMB) is the sum of the time-phased BCWS
answer
        for all work, planning, and summary level packages.
question
            The PMB is the contractor's time-phased plan for accomplishing the work on the contract.
answer
        It establishes the scope, schedule, and budget targets for the program.
question
            Control accounts are management points for planning and control since
answer
        they represent the work assigned to one responsible organizational element on one program WBS.
question
            "Mini-Programs" having
answer
        defined scope, schedule, and budget.
question
            Understand the difference in the methods to measure performance against the Performance Measurement Baseline
answer
        0-100 Method: Once job is finished, value is earned (short duration)   50/50 Method: Earn 50% when start, earn 50% when completed   Value Milestone Method: Assign budgets to milestones and earn as each milestone is reached   Completed or Equivalent Unit Method: Count units being fabricated or completed operations that go into a unit   Planning Package (Rolling Wave): Lock in budgets prior to beginning work.
question
            Labor Costs:
answer
        Occur at work package level, recording man-hours on time cards (or equivalent method).
question
            The Integrated Baseline Review
answer
        Is a formal review conducted jointly between the Government and contractor   Assesses the validity of control account budgets, resources, and time phasing   Is mandatory for all EVMS contracts   Is a process, not an event   Ensures work package technical content consistent with contract SOW
question
            DCMA performs two major types of EVMS surveillance
answer
        System Surveillance   Program / Contract Surveillance
question
            The 32 EVMS guidelines in ANSI/EIA-748
answer
        provide a framework to evaluate the adequacy of a contractor's EVM system.
question
            Recognize the nine management processes associated with EVM
answer
        Organizing   Scheduling   Work/Budget Authorization   Accounting   Indirect Management   Managerial Analysis   Change Incorporation   Materiel Management   Sub-contract Management
