Chapter 7 – Cost Management – Flashcards

Unlock all answers in this set

Unlock answers
question
Actual cost (AC)
answer
the total of direct and indirect costs incurred in accomplishing work on an activity during a given period
question
Analogous estimates
answer
a cost-estimating technique that uses the actual cost of a previous, similar project as the basis for estimating the cost of the current project; also called top-down estimates
question
Baseline
answer
the original project plan plus approved changes
question
Bottom-up estimates
answer
a cost-estimating technique based on estimating individual work items and summing them to get a project total
question
Budget at completion (BAC)
answer
the original total budget for a project
question
Budgetary estimate
answer
a cost estimate used to allocate money into an organization's budget
question
Cash flow analysis
answer
A method for determining the estimated annual costs and benefits for a project
question
Contingency reserves
answer
Dollar amounts included in a cost estimate to allow for future situations that may be partially planned for (sometimes called known unknowns) and that are included in the project cost baseline
question
Cost baseline
answer
a time-phased budget that project managers use to measure and monitor cost performance
question
Cost performance index (CPI)
answer
the ratio of earned value to actual cost; can be used to estimate the projected cost to complete the project
question
Cost variance (CV)
answer
the earned value minus the actual cost
question
Definitive estimate
answer
a cost estimate that provides an accurate estimate of project costs
question
Direct costs
answer
Costs that can be directly related to creating the products and services of the project
question
Earned value (EV)
answer
an estimate of the value of the physical work actually completed
question
Earned value management (EVM)
answer
A project performance measurement technique that integrates scope, time, and cost data
question
Estimate at completion (EAC)
answer
an estimate of what it will cost to complete the project based on performance to date
question
Indirect costs
answer
Costs that are not directly related to the products or services of the project, but are indirectly related to performing the project
question
Intangible costs or benefits
answer
Costs or benefits that are difficult to measure in monetary terms
question
Known unknowns
answer
Dollar amounts included in a cost estimate to allow for future situations that may be partially planned for (sometimes called contingency reserves) and that are included in the project cost baseline
question
Learning curve theory
answer
a theory that when many items are produced repetitively, the unit cost of those items normally decreases in a regular pattern as more units are produced
question
Life cycle costing
answer
the total cost of ownership, or development plus support costs, for a project
question
Management reserves
answer
Dollar amounts included in a cost estimate to allow for future situations that are unpredictable (sometimes called unknown unknowns)
question
Overrun
answer
the additional percentage or dollar amount by which actual costs exceed estimates
question
Parametric estimating
answer
A cost-estimating technique that uses project characteristics (parameters) in a mathematical model to estimate project costs
question
Planned value (PV)
answer
the portion of the approved total cost estimate planned to be spent on an activity during a given period
question
Profit margin
answer
the ratio between revenues and profits
question
Profits
answer
Revenues minus expenses
question
Project cost management
answer
the processes required to ensure that the project is completed within the approved budget
Get an explanation on any task
Get unstuck with the help of our AI assistant in seconds
New