Chapter 3 – Managing Systems Projects – Flashcards

Unlock all answers in this set

Unlock answers
question
action words
answer
Words that signal a sequence of events
question
activity
answer
Basic units of work that a project manager plans, schedules, and monitors
question
calendar view
answer
Shows tasks as an overlay on the actual calendar
question
code review
answer
A type of structured walk-through that takes place during the SDLC
question
concurrent task
answer
One of several tasks that can start at the same time
question
critical path
answer
A series of tasks whose delay would affect a project's completion date
question
Critical Path Method
answer
Developed by private industry to manage complex projects
question
dependent tasks
answer
Tasks that must be completed one after another
question
duration
answer
The amount of time it will take to complete a task
question
event
answer
Examples may include the start of user training or completion of interviews
question
Gantt chart
answer
Horizontal bar chart that represents a set of tasks
question
Microsoft Project
answer
Program having a dominant share of the project management software industry
question
milestone
answer
Recognizable reference point that can be used to monitor progress
question
network diagram
answer
Microsoft's name for a PERT chart
question
open source
answer
Type of program that is supported by a community of users and developers
question
predecessor task
answer
Must be completed before another task can start
question
program evaluation review technique
answer
Developed by the U.S. Navy to manage very complex projects
question
project coordinator
answer
Handles administrative responsibilities for a project team
question
project creep
answer
Process in which projects expand gradually without specific authorization
question
project leader
answer
Used interchangeably with the term project manager
question
project management
answer
Includes planning, scheduling, and reporting on information system development
question
project manager
answer
A project team member who is usually a senior systems analyst
question
project monitoring
answer
Requires guiding, supervising, and coordinating a project team's workload
question
project planning
answer
Includes identifying all project tasks and estimating their completion time
question
project reporting
answer
Includes regular progress reports to management, users, and the project team
question
project scheduling
answer
Involves the creation of a specific timetable, usually in the form of charts
question
project status meetings
answer
Opportunity for project manager to seek input and hold brainstorming sessions
question
project triangle
answer
Includes three legs, which often represent cost, scope, and time
question
qualitative risk analysis
answer
Estimates the probability that a risk will occur and its degree of impact
question
quantitative risk analysis
answer
Can involve a modeling process called what-if analysis
question
risk
answer
An event that could affect a project negatively
question
risk identification
answer
Lists each risk and assesses the likelihood that it could affect a project
question
risk management
answer
Process whose purpose is to minimize the impact of risks on a project
question
risk management plan
answer
Includes a review of internal or external factors that might affect a project
question
risk response plan
answer
Proactive effort to anticipate a risk and describe a plan to deal with it
question
slack time
answer
Amount of time a task can be late without delaying a project's completion date
question
successor task
answer
A concurrent task dependent upon a single prior task
question
task
answer
Has a beginning and an end and requires the use of company resources
question
task box
answer
A rectangular box in a PERT/CPM chart
question
task group
answer
Combination of several activities that contain subsidiary tasks
question
task id
answer
A number or code that provides unique identification
question
task name
answer
Should be brief and descriptive, but does not have to be unique in a project
question
task pattern
answer
Can involve dependent, multiple successor, and multiple predecessor tasks
question
weight
answer
An importance value that managers assign to each time estimate
question
work breakdown structure
answer
Involves breaking a project down into a series of smaller tasks
question
a. U.S. Navy
answer
The Program Evaluation Review Technique was developed by the ________ to manage very complex projects. a. U.S. Navy b. IT industry c. U.S. Army d. private sector
question
b. False
answer
A project manager's best course of action is to attempt to handle all situations single-handedly and avoid alerting management until a problem is serious. a. True b. False
question
d. project leader
answer
In a systems project, the program manager, or ________ , usually is a senior systems analyst or an IT department manager if the project is large. a. project analyst b. project coordinator c. project programmer d. project leader
question
c. PERT chart
answer
A project manager can use a ________ to convert task start and finish times to actual dates by laying out an entire project on a calendar. a. quantitative risk analysis b. structured walk-through c. PERT chart d. Gantt chart
question
b. False
answer
A task ID does not need to be unique in a project and should be brief and descriptive. a. True b. False
question
c. scheduling
answer
Project ________ involves selecting and staffing a project team and assigning specific tasks to team members. a. reporting b. planning c. scheduling d. monitoring
question
a. dependent
answer
The pattern of tasks for a large project can be broken down into ________ tasks, multiple successor tasks, and multiple predecessor tasks. a. dependent b. milestone c. activity d. critical
question
b. critical path
answer
The completion of a project will be delayed if any task on the ________ falls behind schedule. a. risk management plan b. critical path c. work breakdown structure d. testing review
question
c. structured walk-throughs
answer
Many project managers institute ________ , which are reviews of a project team member's work by other members of the team. a. predecessor tasks b. project triangles c. structured walk-throughs d. probable-case estimates
question
b. Gantt charts
answer
When the project manager provides status reports to management and users, ________ are often included as a means for showing the project's status graphically. a. critical paths b. Gantt charts c. task patterns d. design reviews
question
a. successor
answer
If a predecessor task has more than one successor task, the predecessor task's finish time is used to determine the start time for all ________ tasks. a. successor b. concurrent c. predecessor d. dependent
question
c. Apptivo
answer
________ offers several levels of business applications, including project management, and has a plan that is available free of charge with unlimited duration. a. Microsoft Project b. RiskyProject Professional c. Apptivo d. GanttProject
question
d. risk response plan
answer
The ________ is effective if the overall impact of a risk can be reduced by triggering timely and appropriate action. a. quantitative analysis b. qualitative analysis c. risk management plan d. risk response plan
question
d. business requirements
answer
When an information system does not meet ________ , causes might include inadequately defined scope, imprecise targets, and lack of change control procedures. a. budget requirements b. probable-case estimates c. schedule requirements d. business requirements
question
d. Project management
answer
________ for IT professionals includes planning, scheduling, monitoring and controlling, and reporting on information system development. a. Quantitative risk analysis b. Risk management c. Qualitative risk analysis d. Project management
question
c. constraints
answer
In order for a project to be successful, there must be a balance of cost, scope, and time against a set of ________ . a. milestones b. activities c. constraints d. tasks
question
c. Microsoft
answer
________ states that in most projects, at least one side of the project triangle is fixed, and you are not likely to change it. a. Apptivo b. GanttProject c. Microsoft d. MIS CourseMate
question
b. project leader
answer
In a systems project, the program manager, or ________ , usually is a senior systems analyst or an IT department manager if the project is large. a. project programmer b. project leader c. project analyst d. project coordinator
question
d. project coordinator
answer
Most large projects have a project manager and a ________ who handles administrative responsibilities for the team. a. project programmer b. project leader c. project analyst d. project coordinator
question
a. monitoring
answer
Project ________ requires guiding, supervising, and coordinating the project team's workload. a. monitoring b. planning c. scheduling d. reporting
question
d. reporting
answer
Effective project ________ requires strong communication skills and a sense of what others want and need to know about the project. a. monitoring b. planning c. scheduling d. reporting
question
c. PERT/CPM
answer
The two primary chart types that should be understood before creating work breakdown structures are Gantt charts and ________ charts. a. Microsoft Project b. WBS c. PERT/CPM d. risk management
question
d. Gantt chart
answer
The ________ was developed by a mechanical engineer and management consultant over 100 years ago. a. Critical Path Method b. PERT c. WBS d. Gantt chart
question
c. U.S. Navy
answer
The Program Evaluation Review Technique was developed by the ________ to manage very complex projects. a. U.S. Army b. private sector c. U.S. Navy d. IT industry
question
d. bottom-up
answer
PERT is a ________ technique because it analyzes a large, complex project as a series of individual tasks. a. top-down b. quantitative c. qualitative d. bottom-up
question
d. network diagram
answer
The term ________ is the Microsoft equivalent to the PERT chart. a. probable-case estimate b. worst-case estimate c. project triangle d. network diagram
question
c. activity
answer
Any work that has a beginning and an end and requires the use of company resources, such as people, time, or money, is referred to as a task or a(n) ________ . a. milestone b. event c. activity d. estimate
question
a. milestone
answer
A(n) ________ , or event, is a recognizable reference point that you can use to monitor a project's progress. a. milestone b. gateway c. activity d. task
question
c. duration
answer
Task ________ can be measured in person-days, which are units that represent the work that one person can complete in one day. a. groups b. patterns c. duration d. management
question
b. probable-case
answer
Prior to assigning a weight to each estimate, a project manager will make a best-case estimate, a(n) ________ estimate, and worst-case estimate for each task. a. risk-response b. probable-case c. person-day d. task-pattern
question
a. 4
answer
A common approach to calculating expected task duration is to use a ratio of B = 1, P = ________ , and W =1. a. 4 b. 1 c. 2 d. 5
question
d. human resources
answer
Assembling and guiding a development team is part of the ________ factor that is considered when developing duration estimates. a. project size b. constraints c. experience with similar projects d. human resources
question
b. large
answer
Developing time and cost estimates using the experience method may not be reliable for projects involving ________ systems. a. medium-size b. large c. small d. Web-based
question
d. groups
answer
Task ________ can be used when managing a complex project with many tasks. a. boxes b. patterns c. names d. groups
question
b. boxes
answer
In a PERT/CPM chart, project tasks are shown as task ________ , arranged in the sequence in which they must be performed. a. names b. boxes c. patterns d. groups
question
a. Dependent
answer
________ tasks must be completed one after another. a. Dependent b. Concurrent c. Open source d. Structured
question
d. concurrent
answer
When several tasks can start at the same time, each is called a ________ task. a. dependent b. multiple predecessor c. predecessor d. concurrent
question
a. predecessor
answer
Often, two or more concurrent tasks, depend on a single prior task, which is called a ________ task. a. predecessor b. structured c. successor d. dependent
question
c. statement
answer
Task patterns can be identified by looking carefully at the wording of the task ________ . a. name b. ID c. statement d. summary
question
c. patterns
answer
Task ________ determine the order in which tasks are performed. a. groups b. names c. patterns d. IDs
question
b. critical path
answer
If the series of tasks, known as the ________ , is delayed, the completion date of the overall project will be affected. a. risk response plan b. critical path c. design review d. testing review
question
b. slack
answer
The amount of time that a task can be late without delaying the completion date of an entire project is called ________ time. a. risk b. slack c. worst-case d. creep
question
d. structured walk-through
answer
Many project managers have project members review the work of other team members, which is referred to as a ________ . a. qualitative risk analysis b. bottom-up technique c. risk management plan d. structured walk-through
question
b. testing
answer
Depending on the phase of the SDLC, a structured walk-through may be referred to as a design review, code review, or ________ review. a. risk b. testing c. duration d. gateway
question
c. status
answer
A project ________ meeting provides team members with an opportunity to share information, discuss common problems, and explain new techniques. a. monitoring b. scheduling c. status d. reporting
question
a. management
answer
Members of a project team regularly report their progress to the project manager, who in turn reports to ________ and users. a. management b. software developers c. network administrators d. project leaders
question
d. dependencies
answer
When constructing a PERT/CPM chart from a task list, the first step is to identify the tasks, determine task ________ , and enter the task name, ID, and duration. a. groups b. risks c. patterns d. dependencies
question
d. latest
answer
If a successor task has more than one predecessor task, the ________ finish time of the predecessor tasks should be used to determine the start time for the successor task. a. earliest b. quickest c. previous d. latest
question
c. Microsoft
answer
________ invites prospective customers to view an extensive demo that showcases the features of their Project program, which holds the dominant share of the project management software market. a. Apptivo b. GanttProject c. Microsoft d. Intaver Institute
question
d. calendar view
answer
Microsoft Project's ________ shows tasks, similar to a PERT chart, as an overlay on the actual calendar. a. task group b. gateway c. structured walk-through d. calendar view
question
b. open source
answer
GanttProject is a free ________ program that is supported by a community of users and developers. a. design review b. open source c. code review d. testing review
question
d. integrated
answer
A significant advantage of ________ project management software is that it allows the project manager to adjust schedules, estimates, and resource assignments rapidly. a. quantitative b. gateway c. structured d. integrated
question
b. Risk management
answer
________ is the process of identifying, analyzing, anticipating, and monitoring risks to minimize their impact on a project. a. Best-case estimation b. Risk management c. Probable-case estimation d. Weighting
question
d. management
answer
A risk ________ plan includes a review of a project's scope, stakeholders, budget, schedule, and any other internal or external factors that might affect a project. a. identification b. response c. analysis d. management
question
b. Qualitative
answer
________ risk analysis evaluates each risk by estimating the probability that it will occur and the degree of impact. a. Dependent b. Qualitative c. Quantitative d. Independent
question
c. Quantitative
answer
________ risk analysis is performed to better understand the actual impact in terms of dollars, time, project scope, or quality. a. Dependent b. Qualitative c. Quantitative d. Independent
question
b. response
answer
A risk ________ plan is a proactive effort to anticipate risk and describe an action plan to deal with it. a. identification b. response c. management d. analysis
question
b. Intaver Institute
answer
________ offers an add-on risk management package for Microsoft Project, which includes a color-coded matrix that reflects risk probability and impact. a. GanttProject b. Intaver Institute c. Apptivo d. Final Four Industries
question
a. business
answer
To be successful, an information system must satisfy ________ requirements, stay within budget, be completed on time, and be managed effectively. a. business b. user c. project team d. security
question
d. project creep
answer
A process referred to as ________ can increase risk when a project does not have clear scope definitions. a. slack time b. Brooks' Law c. risk identification d. project creep
question
a. Cost overruns
answer
________ may result from unrealistic estimates that are too optimistic or based on incomplete information. a. Cost overruns b. Slack time c. Weighting d. Project creep
question
c. Brooks' Law
answer
In some situations, adding more people to a project might increase the time necessary to complete the project because of a principle called ________ . a. slack time b. project creep c. Brooks' Law d. open source
question
d. IBM
answer
Frederick Brooks Jr., a(n) ________ engineer, observed that adding manpower to a late software project only made it later because new team members first had to be educated and instructed by existing employees whose own productivity was reduced accordingly. a. U.S. Navy b. Microsoft c. Intaver Institute d. IBM
question
d. gateway
answer
In business process modeling notation, a(n) ________ is like a fork in the road, allowing the flow to go one way or another. a. finish day/date b. start day/date c. activity d. gateway
question
a. True
answer
Identifying all project tasks and estimating the completion time and cost of each is referred to as project planning. a. True b. False
question
b. False
answer
The Critical Path Method (CPM) was developed by the U.S. Navy to manage very complex projects. a. True b. False
question
a. True
answer
Project managers often use a weighted formula for estimating the duration of each task. a. True b. False
question
b. False
answer
A task ID does not need to be unique in a project and should be brief and descriptive. a. True b. False
question
a. True
answer
Slack time is the amount of time a task can be late without pushing back the completion date of an entire project. a. True b. False
question
b. False
answer
A project manager's best course of action is to attempt to handle all situations single-handedly and avoid alerting management until a problem is serious. a. True b. False
question
b. False
answer
A project triangle displays the same information as the Gantt chart, but uses task boxes to include much more detail. a. True b. False
question
a. True
answer
A risk management plan should define project roles and responsibilities, risk management methods and procedures, categories of risk, and contingency plans. a. True b. False
question
b. False
answer
A mitigation plan identifies a condition that would initiate a contingency plan. a. True b. False
question
a. True
answer
A principle called Brook's Law demonstrates that adding more people to a project might increase the time necessary to complete the project. a. True b. False
question
time
answer
Successful projects must balance cost, scope, and _______ against a set of constraints.
question
tasks (activities)
answer
Conducting interviews, designing a report, selecting software, waiting for the delivery of equipment, and training users are examples of _______.
question
person-day
answer
A(n) _______ represents the work that one person can complete in one day.
question
work breakdown structure
answer
Tasks in a(n) _______ must be arranged in a logical sequence called a task pattern.
question
critical path
answer
Microsoft Project and other project management software can highlight the series of tasks that form the _______.
question
brainstorming
answer
Project status meetings provide a project manager with an opportunity to seek input and conduct _______ sessions.
question
PERT/CPM
answer
To transform a task list into a(n) _______ chart, you first enter the task name, ID, duration, and predecessors for each task.
question
GanttProject
answer
_______ is a free open source program that has a similar look and feel as Microsoft Project.
question
risk matrix
answer
A Microsoft Excel XY chart can be used to display a(n) _______ that shows risk probability and potential impact.
question
cost overrun
answer
When the progress of a project is poorly monitored and responses to early warning signs of problems are slow, the result can be a(n) _______ .
Get an explanation on any task
Get unstuck with the help of our AI assistant in seconds
New