Chapter 1/Project Management

question

_____ refers to the process in which organizations group and manage projects and programs as a cluster of investments that contribute to the entire enterprise’s success.
answer

Project portfolio management
question

The _____ software integrates information from multiple projects to show the status of active, approved, and future projects across an entire organization.
answer

portfolio project management
question

Project _____ management includes estimating how long it will take to complete work, develop an acceptable project schedule, and ensure timely completion of a project.
answer

time
question

Project _____ management consists of preparing and managing the budget for a project.
answer

cost
question

The question, “What unique product does the customer expect from the project?” is an example of a(n) _____ constraint.
answer

scope
question

Until the 1980s, project management primarily focused on providing _____ and resource data to top management in the military, computer, and construction industries.
answer

schedule
question

High-end tools in project management software have enterprise and _____ functions that summarize and combine individual project information to provide an enterprise view of all projects.
answer

portfolio management
question

Soft skills are also known as _____ skills.
answer

human relation
question

Ethics is a set of principles that guides decision making based on _____ of what is considered right and wrong.
answer

personal values
question

The _____ of project management includes quality, scope, time, and cost constraints.
answer

quadruple constraint
question

A(n) _____ is a temporary endeavor undertaken to create a unique product, service, or result.
answer

project
question

Project management _____ describe the key competencies that project managers must develop.
answer

knowledge areas
question

In project management, the three limitations of scope, time, and cost are referred to as the _____.
answer

triple constraint
question

The question, “What is the project’s schedule?” is an example of a(n) _____ constraint.
answer

time
question

Passing the CPA exam is a standard for accountants. Similarly, passing the PMP exam is becoming a standard for _____.
answer

project managers