Ch. 14 – MRP ; ERP – Flashcards
Unlock all answers in this set
Unlock answersquestion
What is dependent demand?
answer
Demand for one item is related to the demand for another item.
question
What does MRP stand for?
answer
material requirements planning
question
What is MRP?
answer
A dependent demand technique that uses a bill-of-material inventory, expected receipts, and a master production schedule to determine material requirements.
question
What are the benefits of MRP?
answer
1. Better response to customer orders as the result of improved adherence to schedules 2. Faster response to market changes 3. Improved utilization of facilities and labor 4. Reduced inventory levels
question
Effective use of dependent inventory models requires managers to know what five things?
answer
1. MPS 2. BOM 3. Inventory available 4. Purchase orders outstanding 5. Lead times
question
What does MPS stand for?
answer
master production schedule
question
What is an MPS?
answer
A timetable that specifies what is to be made (usually finished goods) and when.
question
What is the difference between the aggregate plan and the MPS?
answer
The aggregate plan is established in terms of families or larger amounts, while the MPS is established in terms of specific products. ex. Amount of bats Louisville Slugger is going to produce in January vs. Birch C271 bats to be produced in January
question
What is a fixed, firm, or frozen schedule?
answer
A production schedule where the near-term portion of the plan does not change. Ex. A 14-day fixed schedule means that the schedule can only be changed 14 days out.
question
What does BOM stand for?
answer
bill of material
question
What is a BOM?
answer
A listing of the components, their description, and the quantity of each required to make one unit of a product.
question
In a BOM, what are items above any level called?
answer
Parents
question
In a BOM, what are items below any level called?
answer
Children or components
question
What are modules?
answer
Components that can be produced and assembled into units
question
What is a modular bill?
answer
A BOM for modules
question
What is a planning bill?
answer
A material grouping created in order to assign an artificial parent to a bill of material; also called "pseudo" bill, kitted material, or kit
question
What is a phantom BOM?
answer
A BOM for components, usually assemblies, that exist only temporarily; they are never inventoried
question
What is low-level coding?
answer
A number that identifies items at the lowest level at which they occur.
question
What is lead time?
answer
The time between recognition of the need for an order and receiving it.
question
What is a gross material requirements plan?
answer
A schedule that shows the total demand for an item and 1) when it must be ordered from suppliers, or 2) when production must be started to meet its demand by a particular date; assumes there is no inventory on hand
question
What is a net requirements plan?
answer
The result of adjusting gross requirements for inventory on hand and scheduled receipts.
question
What is a planned order receipt?
answer
The quantity planned to be received at a future date.
question
What is a planned order release?
answer
The scheduled date for an order to be released.
question
What is system nervousness?
answer
Frequent changes in an MRP system.
question
What are time fences?
answer
A means for allowing a segment of the master schedule to be designated as "not to be rescheduled."
question
What is pegging?
answer
In MRP systems, tracing upward in the bill of material from the component to the parent item.
question
What are buckets?
answer
Time units in an MRP system.
question
What is a lot-sizing decision?
answer
The process of, or techniques used in, determining lot size.
question
What is lot-for-lot?
answer
A lot-sizing technique that generates exactly what is required to meet the plan.
question
What does EOQ stand for?
answer
economic order quantity
question
What is EOQ?
answer
An inventory-control technique that minimizes the total of ordering and holding costs (see ch. 12)
question
What does POQ stand for?
answer
periodic order quantity
question
What is POQ?
answer
An inventory ordering technique that issues orders on a predetermined time interval, with the order quantity covering the total of the interval's requirements.
question
What is MRP II?
answer
A system that allows, with MRP in place, inventory data to be augmented by other resource variables; in this case, MRP becomes material resource planning.
question
What is closed-loop MRP?
answer
A system that provides feedback to the capacity plan, master production schedule and production plan so planning can be kept valid at all times.
question
What is a load report?
answer
A report showing the resource requirements in a work center for all work currently assigned there as well as planned and expected orders.
question
What are the three ways closed-loop MRP systems can smooth load and minimize lead times?
answer
1. Overlapping 2. Operations splitting 3. Order or lot splitting
question
What does DRP stand for?
answer
distribution resource planning
question
What is DRP?
answer
A time-phased stock-replenishment plan for all levels of a distribution network (supply chain).
question
What does ERP stand for?
answer
enterprise resource planning
question
What is ERP?
answer
An information system for identifying and planning the enterprise-wide resources needed to take, make, ship, and account for customer orders.
question
What three things does ERP software allow a company to do?
answer
1. Automate and integrate many of their business processes 2. Share a common database and business practices throughout the enterprise 3. Produce information in real time.
question
In addition to MRP, ERP usually provides what information?
answer
1. Financial 2. Human resources management 3. Supply-chain management 4. Customer relationship management (CRM) 5. Sustainability