The Information Systems Audit and Control Association has created a set of standard practices called ________ that are often used in the assessment stage of the BPM cycle.
answer

COBIT
question

Once a system has passed integrated testing, the organization installs the new system. Which term is used to refer to this activity?
answer

system conversion
question

If a defined project is determined to be feasible in the SDLC, the immediate next step is to ________.
answer

form the project team
question

________ are collections of related tasks that receive inputs and produce outputs.
answer

Activities
question

In BPMN diagrams, a square with a plus sign means that ________.
answer

an activity is independent of the process and is defined in detail in another diagram
question

________ set the stage for the requirements for any information systems and applications that need to be created or adapted.
answer

business process models
question

The ________ is a sequence of activities that determines the earliest date by which a project will be completed.
answer

critical path
question

A ________ involves balancing of three critical factors: requirements, cost, and time.
answer

trade off
question

Which of the following is true for the relationship between business processes and information systems?
answer

A business process need not relate to any information system, but an information system relates to at least one business process.
question

Which of the following is an accurate representation of the steps in the business process management cycle?
answer

model processes; create components; implement processes; assess results
question

The situation that occurs when adding more resources creates inefficiencies is known as ________.
answer

diseconomies of scale
question

In business process management, once the as-is model is created, the very next step that a team must take is to ________.
answer

create system components
question

A(n) ________ is a formal description of a system’s response to use and misuse scenarios.
answer

test plan
question

The term ________ refers to a set of management policies, practices, and tools that developers use to maintain control over the project’s resources.
answer

configuration control
question

A ________ installation is the riskiest because the old system is shut down and the new system is introduced.
answer

plunge
question

The resulting project plan from the system definition is the input to the second SDLC phase, which is ________.
answer

requirement analysis
question

Fixing a system so that it works correctly, or adapting it to changes in requirements, occurs in the ________ phase of the SDLC.
answer

maintenance
question

A ________ is a person who is well versed in an organization’s strategy and who focuses, primarily, on ensuring that business processes and information systems meet the organization’s competitive strategies.
answer

business analyst
question

Tasks in the ________ phase of the SDLC are to build and test system components and to convert users to the new system.
answer

implementation
question

In BPMN, ________ depict the flow or sequence of activities in a process.
answer

solid arrows
question

________ include identifying what is to be produced, how frequently and how fast it is to be produced.
answer

requirements
question

Plunge installation is sometimes called ________ installation.
answer

direct
question

The ________ is a software-industry standards organization that created a standard set of terms and graphical notations for documenting business processes.
answer

OMG
question

In a BPMN process diagram, a ________ represents an activity.
answer

rectangle with rounded corners
question

In systems development, documents, designs, prototypes, data models, database designs, working data entry screens, and the like are examples of ________.
answer

deliverables
question

Which of the following is true of information systems?
answer

Every information system has at least one application.
question

________ is a standard set of terms and graphical notations for documenting business processes.
answer

Business Process Modeling Notation
question

A ________ is a network of activities, repositories, roles, resources, and data flows that interact to accomplish a business function.
answer

business process
question

Once we have defined a project’s goals and scope, the immediate next step is to ________.
answer

assess feasibility
question

An as-is model ________.
answer

documents the current situation of a business process
question

With ________ installation, the organization implements the entire system/business processes on a limited portion of the business.
answer

pilot
question

The first step in the system definition phase of systems development is to ________.
answer

determine the goals and scope
question

In systems development, documents, designs, prototypes, data models, database designs, working dataentry screens, and the like are examples of ________.
answer

deliverables
question

During the requirements definition stage of developing an information system, the project team will include mostly ________.
answer

business and systems analysts
question

What are the four dimensions of feasibility?
answer

cost, schedule, technical, and organizational feasibility
question

Which of the following is an accurate representation of the steps in the business process management cycle?
answer

model processes; create components; implement processes; assess results
question

According to the Scrum process, once the tasks are known for a given set of requirements, the next step is to assign each task a difficulty score, called ________.
answer

points
question

The final WBS plan is denoted as the ________ WBS, and it shows planned tasks, dependencies, durations, and resource assignments.
answer

baseline
question

According to Brooks’ Law, adding more people to a late project will ________.
answer

create diseconomies of scale
question

According to the SDLC, progress of a business process goes in a linear sequence from requirements to design to implementation. This is called the ________.
answer

waterfall method
question

In a BPMN process diagram, all activities for a given role are shown in that role’s ________.
answer

swim lane
question

In paired programming ________.
answer

two team members share the same computer to write a computer program together
question

A ________ shows the tasks, start and finish dates, and dependencies for the tasks of a project.
answer

Gantt chart
question

Organizational feasibility concerns whether the new system aligns with ________.
answer

legal requirements
question

In the SDLC, the first major task for an assembled project team is to ________.
answer

plan the project
question

In a business process, resources are ________.
answer

people or computer applications that are assigned to roles
question

Project teams create a ________, which is a hierarchy of the tasks required to complete a project.
answer

work-breakdown structure
question

In a business process, a role refers to ________.
answer

a collection of activities
question

The rapid application development, the unified process, extreme programming, and Scrum are examples of ________.
answer

agile development
question

The final phase of systems development involves ________.
answer

maintaining the system
question

The first phase of systems development involves ________.
answer

defining the system
question

A ________ shows the tasks, start and finish dates, and dependencies for the tasks of a project..
answer

Gantt chart