Business Project Management – Chap 13 pt.2 – Flashcards

21 test answers

Unlock all answers in this set

Unlock answers 21
question
MathModelLastSlide & MonthlyStatusReport?
answer
MathModelLastSlide & MonthlyStatusReport?
question
Budget=PV=Baseline
answer
Budget=PV=Baseline
question
Earned Value (EV)
answer
Budgeted cost of the work performance. X for a task = (percent complete) x (original budget). Stated differently, EV is the percent of the original budget that has been earned by actual work completed. [BCWP - budgeted cost of the work performed]
question
Planned Value (PV)
answer
The X starts with the time-phased costs that provide the project budget baseline, which is called the X of the work scheduled. The time-phased baseline. X of the work scheduled. [BCWS—budgeted cost of the work scheduled]
question
Actual costs (AC)
answer
Actual cost of the work completed. The sum of the costs incurred in accomplishing the work to date. [ACWP—actual cost of the work performed]
Unlock the answer
question
Cost variance
answer
X tells us if the work accomplished costs more or less than was planned at any point over the life of the project. X: difference between the earned value and the actual costs for the work completed to date . [X = EV - AC]
Unlock the answer
question
Schedule variance (SV)
answer
X: difference between the earned value and the baseline line to date. [X = EV - PV]
Unlock the answer
question
BAC
answer
Budgeted cost at completion. Total budgeted cost of the baseline or project direct cost accounts.
Unlock the answer
question
EAC
answer
Estimated cost at completion.
Unlock the answer
question
ETC
answer
Estimated cost to complete remaining work.
Unlock the answer
question
VAC
answer
Estimated cost to complete remaining work.
Unlock the answer
question
CV (Cost variance)
answer
Indicates if the work accomplished using labor and materials costs more or less than was planned at any point in the project.
Unlock the answer
question
SV (Schedule Variance)
answer
Presents an overall assessment in dollar terms of the progress of all work packages in the project scheduled to date.
Unlock the answer
question
Baseline (PV)
answer
An anchor point for measuring performance. The X is the sum of the cost accounts, and each cost account is the sum of the work packages in the cost account. Three direct costs are typically included in Xs: Labor, equipment and materials (and project direct overhead costs). Costs the PM can control. Overhead costs and profits are typically added later.
Unlock the answer
question
Cost performance (CPI)
answer
X index: Measures the cost efficiency of work accomplished to date. (Earned Value) / (Actual cost)
Unlock the answer
question
Scheduling performance (SPI)
answer
X index: Measures scheduling efficiency (Earned Value) / (Planned Value)
Unlock the answer
question
PCIB
answer
Percent complete index, which compare the to-date progress to the end of the project Percent complete X: Looks at percent complete in terms of budget amounts X = (Earned Value) / (Budgeted cost at completion) X = EV / BAC
Unlock the answer
question
PCIC
answer
Percent complete index, which compare the to-date progress to the end of the project Percent complete X: Views percent complete in terms of actual dollars spent to accomplish the work to date and the actual expected dollars for the completed project. X = (Actual Cost) / (Estimated cost at completion) X = AC / EAC
Unlock the answer
question
EACre
answer
Method for revising estimates of future project cost: We use X to represent revisions made by experts and practitioners associated with the project (usually done in smaller projects). X = (Actual Cost) / (Revised estiated cost to complete ramaining work) X = AC / ETCre
Unlock the answer
question
EACf
answer
Method for revising estimates of future project cost: This method uses the actual cost to date plus and efficiency index (CPI). I.e., estimated total cost at completion. X = ETC + AC ETC = (BAC-EV)/(EV/AC) (BAC-EV)->Work remaining (EV/AC)-> CPI ETC: Estimated cost to complete remaining work AC: Cumulative actual cost of work completed to date CPI: Cumulative cost index to date BAC: Total budget of the baseline EV: Cumulative budgeted cost of work completed to date
Unlock the answer
question
To Complete Performance Index (TCPI)
answer
This ratio measures the amount of value each remaining dollar in the budget must earn to stay within the budget X = (BAC-EV) / (BAC-AC) BAC: Total budget of the baseline AC: Cumulative actual cost of work completed to date EV: Cumulative budgeted cost of work completed to date X < 1: Complete project without using the whole budget. Opens possibilities to improve quality and increase scope (Increase profit).
Unlock the answer
Get an explanation on any task
Get unstuck with the help of our AI assistant in seconds
New