1. Which of the following are metrics of a successful project ____. a. late completion b. completion with the same personnel as were on the team at the outset c. completion over budget d. delivery of a product that satisfies users
question
D
answer
2. A project manager's planning _____. a. involves guiding, supervising, and coordinating the project team's workload b. includes monitoring the progress of the project, evaluating results, and taking corrective action when necessary to stay on target c. consists of staffing, which includes selecting the project team and assigning specific tasks to team members d. includes identifying project tasks and estimating completion times and costs
question
C
answer
3. A project manager's scheduling function _____. a. involves guiding, supervising, and coordinating the project team's workload b. includes monitoring the progress of the project, evaluating results, and taking corrective action when necessary to stay on target c. involves staffing, which includes selecting the project team and assigning specific tasks to team members d. includes identifying and arranging project tasks and estimating completion times and costs
question
A
answer
4. For a project manager, monitoring _____. a. requires guiding, supervising, and coordinating the project team's workload b. involves controlling capital c. consists of staffing, which includes selecting the project team and assigning specific tasks to team members d. includes identifying and arranging project tasks and estimating completion times and costs
question
B
answer
5. For a project manager, reporting _____. a. involves controlling capital b. includes informing management, users, and the project team about the progress of the project c. consists of staffing, which includes selecting the project team and assigning specific tasks to team members d. includes identifying and arranging project tasks and estimating completion times and costs
question
A
answer
6. Effective project reporting requires ____. a. strong communication skills b. staffing the project team c. creating Gantt charts d. assigning specific tasks to team members
question
A
answer
7. The accompanying figure shows task ____, which simplify a complex task by combining several activities. a. groups c. aggregates b. clusters d. links
question
B
answer
8. PERT/CPM is called a(n) ____ technique, because it analyzes a large, complex project as a series of individual tasks. a. top-down c. indexed b. bottom-up d. cataloging
question
C
answer
9. The first step in the creation of a PERT/CPM chart is to ____. a. determine the logical order of project tasks b. identify the graphical planning aids to use c. identify all the project tasks d. determine the status of all tasks
question
B
answer
10. Many project managers find ____ charts more helpful for scheduling, monitoring, and controlling projects. a. Gantt c. index b. PERT/CPM d. task
question
C
answer
11. A(n) ____ chart displays complex task patterns and relationships. a. Gantt c. PERT/CPM b. index d. task
question
C
answer
12. The first step in creating a WBS is to ____. a. mark all recognizable events b. determine time requirements c. identify all tasks d. estimate task completion time and cost
question
A
answer
13. A event is a recognizable reference point that you can use to ____. a. monitor progress b. assign people c. manage time d. allocate money
question
B
answer
14. In addition to tasks, every project has ____, which are reference points used to monitor progress and manage the project. a. targets c. members b. milestones d. workloads
question
C
answer
15. A ____ might involve maximums for one or more resources. a. successor task b. task group c. constraint d. bottom-up technique
question
C
answer
16. In a PERT/CPM chart, each task has which of the following ____. a. references to successor tasks b. references to predecessor tasks c. start day/date d. resources allocated
question
D
answer
17. When several tasks can start at the same time, each is called a(n) ____ task. a. synchronous b. asynchronous c. baseline d. concurrent
question
A
answer
18. Two or more concurrent tasks often depend on a single prior task, which is called a(n) ____ task. a. predecessor b. a priori c. antecedent d. ancestor
question
B
answer
19. When two or more concurrent tasks depend on a single prior task, the concurrent tasks are called ____ tasks. a. descendent b. successor c. children d. antecedent
question
C
answer
20. A ____ path includes all tasks that are vital to the project schedule. a. vital c. critical b. baseline d. foundational
question
D
answer
21. Project managers always must be aware of the ____ path, so they can monitor the vital tasks and keep the project on track. a. vital c. foundational b. baseline d. critical
question
C
answer
22. When maintaining schedules, if enough ____ and frequent checkpoints exist, problems will be detected rapidly. a. success indices b. critical paths c. milestones d. all of the above
question
A
answer
27. A _____ cannot be started until one or more other tasks are completed. a. dependent task b. concurrent task c. predecessor task d. all of the above
question
D
answer
28. A ____ is an event that could affect a project negatively. a. menace c. doubt b. threat d. risk
question
B
answer
29. A risk management plan includes a review of ____. a. employees b. project scope c. program code d. open source
question
B
answer
30. Most risk identifications include a brief description of ____. a. the team member who might cause a risk to occur b. who would be responsible for responding to a given risk c. the project manager most vulnerable to a given risk d. the team member most vulnerable to a given risk
question
C
answer
32. A risk ____ plan is a proactive effort to anticipate a risk and describe an action plan to deal with it. a. identification c. response b. management d. balancing
question
A
answer
33. A continuous risk-tracking process can ____. a. identify new risks b. prevent human resource turnover issues c. increase employee satisfaction d. encourage team building
question
C
answer
36. When an information system does not meet business requirements, causes might include ____. a. identified requirements b. adequately defined scope c. imprecise targets d. sufficient testing
question
D
answer
37. ____ is a possible cause of cost overruns related to human resource issues. a. unrealistic estimates b. poor monitoring of progress c. inaccurate TCO forecast d. turnover
question
D
answer
38. Problems with timetables and project milestones can indicate ____. a. recognition of task dependencies b. continuity of project personnel c. good control methods d. personality conflicts among team members
question
B
answer
39. When a project manager first recognizes that a project is in trouble, the options available to her include ____. a. expanding the project requirements b. delaying the project deadline c. reducing the project resources d. eliminating controls and procedures
question
A
answer
40. A project triangle shows three legs: _____. a. project cost, scope, and time b. project cost, size, and scope c. project size, scope, and time d. project size, cost, and time