6F051 Volume 3 – Flashcards
Unlock all answers in this set
Unlock answersquestion
What is the major difference between the responsibilities of the Financial Management Analysis (FMA) and the Defense Finance and Accounting Service (DFAS)?
answer
FMA handles the accounting processes at base level serves as a liaison between the base organizations and DFAS
question
Overall responsibility for obligation accounting is maintained by......
answer
Finance and Accounting
question
All accounting classifications must contain AT LEAST the accounting and disbursing station number (ADSN) and the......
answer
appropriation symbol
question
Which step in determining the elements of the accounting classification tells you to ensure the accounting station number is noted?
answer
Step 5
question
Which funds are established to record collections for no year and clearing accounts?
answer
Deposit
question
Which code identifies what is being purchased?
answer
EEIC
question
What code is the first subdivision of the accounting classification below the appropriation level and always starts with the letter ?P?
answer
Budget program
question
The disbursement accounting process begins when...
answer
service is requested
question
When a requirement is known but a firm price is not, an administrative reservation of funds is processed and is also known as......
answer
a commitment stage
question
Which stage of accounting liquidates the obligation?
answer
AEP
question
After receiving utilities estimates from Civil Engineering (CE), the Defense Finance and Accounting Service (DFAS) enters the estimate into......
answer
General Accounting and Finance System (GAFS) as unfilled customer orders (UFCO)
question
What is the first step in identifying the stages of accounting?
answer
Determine the type of accounting your working with
question
When identifying the stages of accounting for obligations, which step directs you to ensure that funds are at the proper disbursement stage?
answer
Step 3
question
The General Accounting and Finance System (GAFS) uses internal files to track funds and stores them on a magnetic disk, this storage is also called......
answer
immediate access storage
question
Which record is not established at the beginning of the fiscal year?
answer
Document summary record (DSR)
question
Each combination of element of expense/investment code (EEIC) and responsibility center/cost center (RC/CC) codes requires a separate......
answer
Program summary record (PSR)
question
Which system was designed to automate the accounts payable process?
answer
Integrated Accounts Payable System (IAPS)
question
What is the link between the Integrated Accounts Payable System (IAPS) and the General Accounting and Finance System (GAFS)?
answer
ICI
question
What system is used to approve upward adjustments to expired and cancelled appropriations?
answer
Obligation Adjustment Reporting System (OARS)
question
What is the next step after an Automated Business Services System (ABSS) user selects the form type?
answer
Add the administrative data
question
Who is the final financial individual in the Automated Business Services System (ABSS) routing process?
answer
The certifying official
question
What are the steps of processing a document in the Automated Business Services System (ABSS)?
answer
Approver; resource advisor; certifying official
question
Who appoints the certifying official in writing?
answer
Comptroller
question
Who is held pecuniary liable for erroneous payments?
answer
Certifying official
question
What type of codes will allow instant input of financial transactions?
answer
Override
question
What need should be met when commitments for annual appropriations are incurred?
answer
A bona fide need for goods or services in the fiscal year the funds are issued for
question
Which commitment document is used to designate the accounting classification for charges by the cardholders within the various organizations on base?
answer
AF Form 4009
question
When adding commitment documents in the Automated Business Services System (ABSS) and you want to add the unit of issue and quantity you can click on the......
answer
Line Items button
question
What document would you use for construction projects exceeding $100,000?
answer
SF 1442
question
Who determines the category for a Military Interdepartmental Purchase Request (MIPR)?
answer
Performing activity
question
With a direct cite category II Military Interdepartmental Purchase Request (MIPR), who funds the cost for material or services provided?
answer
Requesting activity
question
Who authorizes and approves the AF Form 150 for do-it-yourself (DITY) moves?
answer
Housing Management Officer
question
What document is considered evidence of financial liability?
answer
Receiving report
question
A receiving report represents what stage of accounting?
answer
AEU
question
What form is used to provide the vendor an opportunity to release the government from any obligation?
answer
AF Form 821
question
The Prompt Payment Act (PPA) requires federal agencies to make payments on time, if payments are late what should be done?
answer
Pay interest penalties
question
Cash management is a part of the Prompt Payment Act (PPA); what is a function of cash management?
answer
Electronic funds transfer
question
Although you must make payments within prescribed terms, payments must also be paid within what window?
answer
7 day window
question
When validating a Miscellaneous Obligation Reimbursement Document (MORD) from a funding activity, what do you do after you review the data for validity and accuracy?
answer
Check the description block
question
Should a resource advisor (RA) fail to submit supporting documentation to support a Miscellaneous Obligation Reimbursement Document (MORD) what step to you take?
answer
Request DFAS process reversal of MORD greater than 90 days
question
When using the Government Purchase Card (GPC), what is the first step you take after you've made a purchase?
answer
Update Access Online with each purchased
question
Which is the file created for the Tri-Annual Review (TAR) at the start of each review, requires validation by the bases, and is due at the mid-point of the review?
answer
Base file
question
As a resource advisor (RA), if you accepted a Military Interdepartmental Purchase Request (MIPR) as a Category 2, what actions do you take after you receive the obligation documents?
answer
Forward to the Financial Management Analysis (FMA)
question
Which general accounting and finance system listing identifies all open document summary records in the BQ system?
answer
ODL
question
When travelers do not file their travel vouchers in time, the order they traveled on will show up as outstanding on what report?
answer
GOO
question
What form is prepared after a vendor sends in a check for an overpayment?
answer
DD Form 1131
question
What two forms are commonly used for collections after customers send in their payment to the Defense Finance and Accounting Service (DFAS)?
answer
DD Form 1131 and SF 1080
question
What must be included in the collection voucher, Department of Defense (DD) Form 1131?
answer
Complete accounting classification being credited
question
If the US Treasury determines that collection is not possible when working delinquent accounts receivable, what does the debt collection do?
answer
Process a write-off
question
Financial accounting is concerned with......
answer
external reporting to parties outside the company
question
The left side of the ?T account is used to record......
answer
debits
question
What is used to ensure that debits equal credits?
answer
Trial balance
question
Budgetary accounts, control and properly manage budget authority provided and apply primarily to......
answer
the legal requirements
question
The proprietary accounting equation includes all of the following except......
answer
debits
question
If you are looking for information on the location you are deploying to which option would you choose from the four offered on the main page of the Combat Comptroller Community of Practice (CoP) website?
answer
Pre-deployment
question
Which section of the Combat Comptroller Community of Practice (CoP) contains unique and unusual situations as well as identified problems and proposed solutions?
answer
Post-deployment
question
Which section of the Combat Comptroller Community of Practice (CoP) includes great information on the Air and Space Expeditionary Force Unit Type Code Reporting Tool (ART) to include the checklist to assess unit type code (UTC) personnel?
answer
UDM/Warplanner
question
If you are looking to understand the overall picture of contingencies specifically our Financial Management (FM) wartime requirements you would search in what section of the Combat Comptroller Community of Practice (CoP) website?
answer
UDM/War Planner
question
What system is used as an internal management tool by the Chairman of the Joint Chiefs of Staff (CJCS) to access effectiveness meeting responsibilities to organize, train, and equip forces for combatant commanders?
answer
Status of Resources and Training System (SORTS).
question
Comptroller actions supporting a Joint Strategic Capabilities Plan (JSCP) and non-JSCP contingency operations are similar. The major difference between them is that the......
answer
comptroller personnel may not be required to be physically present at deployment locations to provide financial support under a non-JSCP contingency operation
question
What rates are normally used in preparing the budget submission?
answer
Budget
question
What account is used to charge losses or credit gains between amounts obligated, at specified budget rates, in the basic appropriation and the amount disbursed at the current rate of exchange for designated foreign currencies?
answer
Centrally Managed Allotment (CMA) account
question
Step 2 of using foreign currency has you......
answer
determine the type of funds
question
Which step in using foreign currency has you determine the impact the budget and foreign currency rate will have on programs?
answer
Step 4
question
An Air Force Form 616, Fund Cite Authorization, may be used to purchase......
answer
vehicle rentals in support of a contingency
question
When posting obligations in the General Accounting and Finance System (GAFS) the first step is to......
answer
get the commitment document summary record (DSR)
question
Vouchers are assembled after......
answer
all computations have been made
question
Which is not something the certifying official should check on a voucher before certifying it?
answer
Receiving report is attached and dictates the payment amount authorized
question
If BQ (Accounting and Finance System) is not available at a deployed location, then what form is issued to authorize use of funds?
answer
AF Form 616
question
What is the third step in updating the AF Form 616 when commitment documents are received?
answer
Calculate the new available balance by reducing the commitment amount by the amount of the newly posted commitment
question
When presenting a status of funds briefing, what information do you show for each unit's expenditures?
answer
Major categories
question
What is ITS.gov (International Treasury Service)?
answer
A system used for processing international direct deposit payments
question
Which is not a benefit of ITS.gov (International Treasury Service)?
answer
Increases the ability to process national electronic payments in emerging markets
question
Acquisitions Cross Service Agreement (ACSA) agreements document......
answer
legal authority to buy, sell, give, or loan support to another country
question
The Acquisitions Cross Service Agreement (ACSA) program allows logistical support with coordination from what three areas?
answer
Finance, Logistics, Legal
question
What is of top priority should you receive a joint tasking?
answer
Setting you up for success
question
Which category contains the financial publication that contains specific guidance regarding early resource manager involvement in planning to ensure mission success?
answer
1-0: Personnel Series