Project Management Flashcards Answers
Unlock all answers in this set
Unlock answersquestion
            Project management can be defined as planning, directing, and controlling resources to meet the technical, cost, and time constraints of the project
answer
        TRUE
question
            A project may be defined as a series of related jobs usually directed toward some major output and requiring a significant period of time to perform
answer
        TRUE
question
            The second step in managing a project is writing the Statement of Work
answer
        FALSE- a project starts out as a statement of work
question
            An event unit package is a subdivision of a project
answer
        FALSE- there is no such item as an event unit package
question
            Complex projects are often subdivided into a series of tasks that are typically configured to be not longer than several months in duration
answer
        TRUE- a task is a subdivision of a project. It is usually not longer than several months in duration and is performed by one group or organization
question
            A work breakdown structure is used in project management but it is not used when the critical path method is involved
answer
        FALSE- activities are identified as part of the work breakdown structure. Activities are also the essence of the critical path method. Hence, the work breakdown structure is used when the critical path method is involved
question
            The fact that organizations are flattening is one of the reasons that project management is important
answer
        TRUE
question
            The Gantt is an example of a project control chart
answer
        TRUE
question
            Upper level management must decide between pure, functional, and matrix structures as a way to organize projects
answer
        TRUE
question
            One of the disadvantages of a pure project organizational structure is that the project manager has full authority over the project
answer
        FALSE- this is an advantage
question
            One of the advantages of a functional project organizational structure is that a team member can work on several projects
answer
        TRUE
question
            A matrix project attempts to blend the properties of functional and pure project structures
answer
        TRUE
question
            A matrix project is often referred to as a "skunkworks"
answer
        FALSE- pure projects are referred to as "skunkworks"
question
            A disadvantage of a matrix project organizational structure is that a project manager is held responsible for successful completion of the project
answer
        FALSE- this is an advantage
question
            The critical path of activities in a project is the sequence of activities that form the shortest chain in a project network of activities
answer
        FALSE- longest chain
question
            CPM is an abbreviation for Critical Path Method
answer
        TRUE
question
            In CPM the late start time estimate is the latest time you can start an activity and still keep the entire project on schedule
answer
        TRUE
question
            The critical path in a project is that sequence of activities that consume the longest amount of time in a project network of activities
answer
        TRUE
question
            The critical path in a CPM analysis is always the shortest path through the network
answer
        FALSE- longest
question
            Slack activity time is the difference between the early start time and the late finish of a project activity time
answer
        FALSE- slack time is the difference between late start time and early start time
question
            In a CPM analysis if you subtract the late finish from the early finish the result is the activity's slack time
answer
        FALSE- slack time is the difference between the late start time and early start time
question
            In a CPM analysis, if you subtract the early start time from the late start the result is slack time
answer
        TRUE
question
            The critical path in a CPM analysis is found by locating the activities times with zero slack
answer
        TRUE
question
            Calculating the early start and early finish times for each activity in a CPM analysis does not provide any useful information
answer
        FALSE- savings
question
            The project indirect costs associated with a project include overhead, facilities, and resource opportunity costs
answer
        TRUE
question
            The activity direct costs associated with a project might include giving workers overtime to complete a project in less than the expected time
answer
        TRUE
question
            You are managing a project and need to cut the cost of the project. You decide to transfer workers to another job to cut the project's costs. Costs associated with transferring the workers are an example of project indirect costs.
answer
        FALSE- this is a cost for expediting activity and is therefore a direct cost
question
            Using the Time-Cost CPM model, the crash time is the shortest possible time allowed for each activity in the project
answer
        TRUE
question
            In the Time-Cost CPM model, cost is assumed to be a linear function of time
answer
        TRUE
question
            When reducing the planned duration of a project using the Time-Cost CPM model we select the activity to crash by determining the cost of each alternative and selecting the one whose cost is the greatest
answer
        FALSE- lowest cost
question
            One of the assumptions made when using CPM is that project activities can be identified with clear beginning and ending points
answer
        TRUE
question
            One of the assumptions made using CPM is that project activity sequence relationships can be specified and networked
answer
        TRUE
question
            Project management software available today combines CPM and other scheduling aids, like Gantt charting, to aid in tracking progress of project completion
answer
        TRUE
question
            A project milestone is a specific event to be reached by a particular point in time
answer
        TRUE
question
            Breakthrough projects are those that provide fundamental improvements to existing products
answer
        FALSE- breakthroughs involve major changes and entirely new markets. platform projects provide fundamental changes to existing products
question
            Derivative projects are those which address incremental changes to products
answer
        TRUE
question
            Earned Value Management EVM is a technique for measuring project progress in an objective manner
answer
        TRUE
question
            The valuations in an EVM analysis must be either profits or revenue
answer
        FALSE- profits or costs
question
            EVM has the capability to combine measurements of scope, schedule, and cost in a project
answer
        TRUE
question
            A project can be subdivided into which of the following?
answer
        Work Packages
question
            A project starts out as which of the following
answer
        Statement of Work
question
            What is a work breakdown structure?
answer
        definition of the hierarchy of project tasks, subtasks, and work packages
question
            In a Gantt chart the horizontal axis is usually which of the following?
answer
        Time
question
            Which of the following is a graphic project report used in project management?
answer
        Cost and performance tracking schedule
question
            An advantage of a pure project, where self contained teams work full time on a project is which of the following
answer
        Lines of communication are shortened
question
            Some of the advantages of a functional project where the project is housed in a functional division include which of the following
answer
        A team member can work on several projects
question
            A series of projects that are organized in such a way that each project uses people from different functional areas is using which of the following organizational structure
answer
        matrix project
question
            You are looking at a chart that has the terms BCWS, BCWP, and AC indicating lines on the chart. What kind of chart are you looking at
answer
        EVM chart
question
            PERT is an abbreviation for which of the following
answer
        Program Evaluation and Review Technique
question
            You have just been assigned to oversee a series of projects. Functional areas will loan you personnel for each project and separate project managers will be responsible for separate projects. These project managers will report to you. Which project management structure is being used?
answer
        Matrix project
question
            You have been placed in charge of a large project. Shortened communication lines are required to ensure quick resolution of problems as they arise. You recognize that the project is going to take a lot of time and require a lot of team pride, motivation, and commitment by all members. Which project management structure should you use?
answer
        Pure Project
question
            For an activity in a CPM analysis, the Early Start time is 8 and the Late Start time is 10. Which of the following statements is true?
answer
        The slack time for this activity is 2
question
            For an activity in a CPM analysis the Early Finish time is 20 and the late finish time is 20. which of the following is true?
answer
        The activity is on the critical path
question
            A listing of immediate predecessor activities is important information in a CPM analysis for which of the following reasons
answer
        It specifies the relationships in the CPM network of activities
question
            You have just performed a CPM analysis and have found that more than one path through the project network has zero slack variables. What can you conclude
answer
        You have more than one critical path
question
            You know when you have arrived at the optimal solution using the Time-Cost CPM Scheduling model analysis when what happens?
answer
        You have reached the minimum total cost
question
            In CPM analysis it is generally expected that the relationship between activity direct costs and project indirect costs will be which of the following
answer
        Negatively related
question
            What is that sequence of activities that consume the longest amount of time in a project network of activities called?
answer
        The Critical Path
question
            What are Project Milestones
answer
        Specific events to be accomplished by specific points in time
question
            What do the initials EVM stand for
answer
        Earned Value Management
question
            What is the most basic requirement of an EVM system
answer
        that is quantify progress using PV and EV