12 – Project Procurement Management – Flashcards

Unlock all answers in this set

Unlock answers
question
PM's focus when reviewing contract?
answer
Checking that price is right. Confirming that product, service or output description is adequate (while legal team focuses on ensuring contract language is legally adequate.. E.g. Limits legal risk Also, PM should provide an understanding of project risks and make sure provisions are included in the contract to address these risks.
question
If project is an internal project between two departments in same company where one is the customer and other is supplier, should a formal contract Be created and agreed?
answer
Yes (in perfect world or PMP world)
question
Which of the following is not an acceptable approach for termination of a procurement contact? A.) Termination by the buyer after the delivery of the contracted work. B.) Termination by bypassing the terminations clause of the contract. C.) Termination by either party anytime for any cause or convenience. D.) Termination by a party due to the default of other party.
answer
B- Any reason or approach for termination of a contract is legal and acceptable if it is in accordance with the agreed terminations clause of the contract. Bypassing the terminations clause is not only an unacceptable approach for terminating a contract, it is also illegal.
question
Is a formal written contract the only form of a binding contract?
answer
No, binding contract can be written, verbal, a handshake, an email,etc.. All contracts are subject to remedy in the courts.
question
Does buyer have the right to ask for anything not in contract?
answer
No, Seller only has to deliver what is in contract.
question
What is in Procurement Management Plan
answer
Processes to be followed by Procurement Management process, Make or buy decision, sourcing strategy, types of contracts to be used, metrics used to measure sellers, procurement document formats, risks, constraints,assumptions
question
Which technique is mandatory in Procurement Management?
answer
Make or Buy decisioning - determining which products or services will be bought, leased, rented or made in-house. This drives which outputs need to flow through rest of Procurement Management (Conduct Procurement, Control Procurement and close procurement).
question
What are the types of contracts?
answer
Fixed Price - Scope must be well known. Requires more work from buyer to set up and write procurement SOW. But, less work for buyer to manage. Big advantage is cost risk reduction for buyer. But, changes in scope must be carefully observed, otherwise the cost of the project may be elevated significantly because it is seen that the contractors get the contract by bidding the lower price and then try to cover the cost with any opportunity, such as added scope. Cost Reimbursable - Higher cost risk for buyer. Used when scope is less understood, and you need expert resources. MUST AUDIT seller invoices. More management from buyer required than fixed. This contract is also known as a Cost Disbursable Contract. In this type of contract, the seller is reimbursed for completed work plus a fee representing his profit. Sometimes this fee will be paid if the seller meets or exceeds the selected project objectives; for example, completing the task before time or completing the task with less cost, etc. Time and Materials (T)- done when you need resources quick but for SHORT DURATION. Needs lot's of day to day mgmt by buyer. A Time and Materials type of contract is generally used when a precise SOW can not be quickly created. In this type of contract, the project manager or the organization will provide the qualification or experience to the contractor to provide the staff.
question
What are the contract modifiers?
answer
Fixed Fee- Incentive Fee Award Fee Economic Adjusted Fee
question
Typical Contracts
answer
Firm Fixed Price (FFP) Fixed Price Incentive Fee (FPIF) Fixed Price Economic Price Adjust (FP-EPA) Cost Plus Fixed Fee (CPFF) Cost Plus Incentive Fee (CPIF) Cost Plus Award Fee (CPAF) Time &Materials (T&M)
question
Firm Fixed Price (FFP)
answer
This is the simplest type of procurement contract. In this type of contract, the fee is fixed. The seller has to complete the job within an agreed amount of money and time. Any cost increase due to bad performance of the seller will be the responsibility of the seller, who is legally bound to complete the job within the agreed amount. Since the risk is borne by the seller, the cost tends to be higher. Another drawback of a Firm Fixed Price Contract is that, if the scope is not clear, there can be disputes between the buyer and the seller. Moreover, any deviation from the original scope can cost you a lot. Example: The seller has to complete the job for $100,000 USD within 18 months.
question
Fixed Price Incentive Fee (FPIF)
answer
In this type of contract, although the price is fixed, the seller is given an additional incentive based on his performance. This incentive lowers the risk borne by the seller. The incentive can be tied to any project metrics such as cost, time, or technical performance. Example: 10,000 USD will be paid to contractor as an incentive if he completes the work before two months.
question
Fixed Price Economic Price Adjust (FP-EPA)
answer
If the contract is multi-year long, a Fixed Price with Economic Price Adjustment Contract is used. Here you include a special provision in a clause which protects the seller from inflation. Example: About 3% of the cost of the project will be increased after a certain time duration based on the Consumer Price Index.
question
Cost Plus Fixed Fee (CPFF)
answer
In this type of contract, the seller is paid for all his cost incurred plus a fixed fee (which will not change), regardless of his performance. Here, the buyer bears the risk. This type of contract is used in projects where risk is high, and no one is interested in bidding. Therefore, this type of contract is selected to keep the seller safe from risks. Example: Total cost plus $25,000 USD as a fee.
question
Cost Plus Incentive Fee (CPIF)
answer
In a Cost Plus Incentive Fee Contract, the seller will be reimbursed for all costs plus an incentive fee based upon achieving certain performance objectives mentioned in the contract. This incentive will be calculated by using an agreed predetermined formula. Here the risk also lies with the buyer; however, this risk is lower than the Cost Plus Fixed Fee where the buyer has to pay a fixed fee along with the cost incurred. In a Cost Plus Incentive Fee Contract, the incentive is a motivating factor for the seller. If the seller is able to complete the work with less cost or able to complete it before time, he may get some incentive. Most of the time incentive is a percentage of the savings, which is shared by the buyer and the seller. Example: If the project is completed with lesser cost, 25% of remaining fund will be given to the seller.
question
Cost Plus Award Fee (CPAF)
answer
Here, the seller is paid for all his legitimate costs plus some award fee. This award fee will be based on achieving satisfaction on the certain performance objectives described in the contract. The evaluation of performance is a subjective matter, and you cannot appeal it. There is a difference between the incentive fee and the award fee. An incentive fee is calculated based on a formula defined in the contract, and is an objective evaluation. An award fee is dependent on the satisfaction of the client and is evaluated subjectively. Award fee is not subjected to an appeal. Example: If the seller completes the task meeting or exceeding all quality standards, based on his performance he may be given an award of up to $10,000 USD.
question
Time & Materials (T&M)
answer
This is a hybrid contract of Fixed Price and Cost Reimbursable Contracts. A Time and Materials type of contract is generally used when a precise SOW can not be created quickly. In this type of contract, the project manager or the organization will provide the qualification or experience to the contractor to provide the staff. This type of contract is used to hire some experts or any outside support. Here the buyer can specify the hourly rate for the labor with a "not-to-exceed" limit. Example: Technician will be paid $20 USD per hour.
question
What's in the Procurement Statement of Work?
answer
An output of Plan Procurement Management process. Based on the scope statement, WBS, WBS Dictionary , all related products and services required, for one or multiple items to be procured, not final until contract signed, specifications, delivery details, schedule, location requirements. Usually one Procurement SOW is created for each procured item. However, one procurement SOW can be created for more than on procured item intended to be supplied by one vendor.
question
Procurement Documents
answer
An output of Plan Procurement Management process Docs used in bids and proposal activities. E.g. RFI, IFB, RFP, RFQ, format for collection and evaluation of vendor responses,
question
When is fixed price contract right or wrong?
answer
The main advantage of Fixed Price Contract is that both parties know the scope of the work, and the total cost of the task before the work is started. This type of contract is very useful if the scope of work is defined accurately. If done right, risk is with seller. Fixed price contracts are good for controlling the cost. However, changes in scope must be carefully observed, otherwise the cost of the project may be elevated significantly because it is seen that the contractors get the contract by bidding the lower price and then try to cover the cost with any opportunity, such as added scope.
question
RFI
answer
Type of procurement document whereby Buyer requests various information around potential Seller's products, services or capabilities. For finding potential vendors for consolidation of proposals or quotes.
question
RFQ
answer
Type of procurement document used to request price quotations from potential Sellers of common or standard products or services. Sometimes used in place of RFPs, and in some application areas may have a narrower or more specific meaning. Usually request a price quote per item, hour, meter, or other unit of measure. Getting prices from a company for goods or services. Contract type- T & M Procurement SOW- Any
question
RFP
answer
Type of procurement document used to proposals from potential Sellers of. In some application areas may have a narrower or more specific meaning. A very detailed and specific approach to a customized solution and a total price. Contract type- CR Procurement SOW- Performance or Functional
question
IFB
answer
Invitation for bid- generally this term is equivalent to RFP, but in some application areas may have a narrower or more specific meaning. But, Usually request for just a total price to do all the work. Is usually a sealed bidding processes used by Govt. contracting Contract type- FP Procurement SOW- Design
question
Which of the following usually do not get updated in the Organizational Process Assets during the Control Procurements process? A.) Correspondence B.) Payment schedules C.) The Project Management Plan D.) Performance evaluations
answer
C- All of the given choices are updated in the Organizational Process Assets during some stage of the project. However, the Project Management Plan does not get updated in the Organizational Process Assets during the Control Procurements process.
question
Monica is managing a software system implementation project. The technical work has been outsourced to a technology provider. Monica wants to change the contracted Scope of Work. Where can she find documentation on the process that needs to be followed in order to modify the contracted Scope of Work? A.) Contract Change Control System B.) Project Management Plan C.) Organizational Process Assets D.) Enterprise Environmental Factors
answer
A- The Organizational Process Assets often do contain documentation on generic organizational change control systems. However, the specific details regarding contract changes are documented in every Contract Change Control System.
question
Who is responsible for the negotiations of the procurement contract clauses in any organization?
answer
This varies from organization to organization. The responsibility for project Procurement Management varies from organization to organization. The project manager and the project team may not be the lead negotiators on every project. Some organizations have dedicated Legal and Procurement departments that perform these activities.
question
A leading telecom network operator has signed a procurement contract with an international telecom equipment vendor company to extend their network infrastructure nationally by 50%. Network planning, civil works and equipment installation are all included as a part of the procurement contract. From the equipment vendor's point of view, which of the following needs to be applied efficiently to effectively manage this procurement contract?
answer
This question is asking about the approach of the vendor towards an awarded contract. For the vendor, the awarded work needs to be treated as a project. However, for the buyer, the contract needs to be managed as a procurement.
question
Which of these is not an input to the Control Procurements process? A. Agreements B. Change requests C. Work performance data D. Work performance reports
answer
B - Change requests are not inputs to the Control Procurements process. The other choices are valid inputs to this process. [PMBOK 5th edition, Page 379] [Project Procurement Management] Approved Change requests are an input to Control Procurements process.
question
Which of the following is not a tool or technique of the Control Procurements process? A. Payment system B. Configuration management system C. Contract change control system D. Records management system
answer
B - The configuration management system is not a tool and technique of the Control Procurements process. The other choices are valid tools and techniques of this process. [PMBOK 5th edition, Page 379] [Project Procurement Management]
question
You have received a proposal for an RFP that was sent to vendors. One of the vendors has proposed doing the project for $12,500. The cost for the project is $10,000 and their profit will be $2,500. Which type of contract is most suitable for this situation? A. Cost Plus Fixed Fee B. Cost Plus Percentage of Cost C. Fixed price D. Cost Plus Incentive Fee
answer
C - It looks as if the vendor is asking for a cost-plus-fixed-fee contract. However, by asking for a fixed $12,500, the vendor is actually asking for a fixed-price contract. The cost and fee are just the components the vendor has estimated to come up with a final price. [PMBOK 5th edition, Pages 362, 363] [Project Procurement Management]
question
Your company requires that before you purchase any routers or switches for the data center you are building, you need to solicit quotes from three separate suppliers prior to submitting the purchase request to the finance department. This policy belongs to: A. Organizational Process Assets B. Enterprise Environmental Factors C. Procurement Management Knowledge Area D. Make-or-Buy Decision
answer
A - Any type of corporate policy or formal procurement procedure is an organizational process asset. [PMBOK 5th edition, Page 27] [Project Procurement Management]
question
Which of the following is accurate regarding agreements in Project Procurement Management? A. Agreements can never be terminated. B. Terms and conditions never include the seller's proposal C. Agreements are informal documents. D. Agreements are legal documents between a buyer and a seller.
answer
D - Agreements are legal and formal documents between buyers and sellers. [PMBOK 5th edition, Page 357] [Project Procurement Management]
question
Type procurement where seller organization is preferred seller?
answer
Single Source
question
Type procurement where seller organization is only seller?
answer
Sole Source (e.g. Has patent)
question
Sharing Ratio?
answer
Incentives are usually expressed as a ratio such as 90/10 sharing of savings. The buyer portion is always the first number. So, in this example, buyer gets 90% of the savings while the seller gets 10%.
question
Point of total assumption (PTA)?
answer
The amount above which the seller bears all the loss of cost overrun. PTA = ((Ceiling Price - Target Price) / Buyer's Share Ratio) + Target Cost
question
Final Price & Final Fee in Cost plus Incentive Fee?
answer
Final Price = Actual Cost + Final Fee Final Fee = Target Fee + or - sellers portion of savings or cost overrun
question
Target price?
answer
Used to compare the end result (final price) with what was expected (target price). Target price is a measure of success. Target Cost + Target Fee = Target Price. (this is thinking about procurements from the buyers point of view)
question
On fixed price contracts, what are some key areas to focus upon:
answer
- Watch for the seller cutting scope - Watch for the seller cutting quality - When the contract requires the seller's costs to be transparent, make sure they are real costs that have been incurred, not just future costs (unless there is an agreement stating otherwise) - Watch for overpriced change orders - Check for scope misunderstandings
question
On Cost Reimbursable contracts, what are some key areas to focus upon:
answer
- Audit every invoice - Make sure all the costs are applicable and chargeable to your project - Make sure the seller's work is progressing efficiently - Watch for the seller adding resources to your project that do not add value or perform real work. - Watch for resources being shifted from what was said in the original proposal (e.g. more experienced people proposed and less experienced people used) - Watch for seller charges that were not part of the original plan - Reestimate the cost of the project
question
A routine audit of a cost reimbursable (CR) contract determines that overcharges are being made. If the contract does not specify corrective action, the buyer should: A. Continue to make project payments B. Halt payments until the problem is corrected C. Void the contract and start legal action to recover overpayments D. Change the contract to require more frequent audits
answer
A. Continue to make project payments. Halting all payments would be a breach of contract on the buyer's part. Voiding the contract and beginning legal action is too severe and connot be done unilaterally. Changing the contract to require more frequent audits does not solve the problem presented. A choice that said, "Halt payments on the disputed amount" would probably be the best answer. But, this choice isn't there, so best answer is to continue to make project payments.
question
The primary objective of the contract negotiations is to: A. Get the most from the other side B. Protect the relationship C. Get the highest monetary return. D. Devine the objectives and stick to them
answer
B. Protect the relationship. As PM you want to develop good relationship during negotiations that will last throughout the project. That doesn't mean the buyer sacrifices doing what is best for the organization.
question
All of the following must be present to have a contract except: A. A procurement statement of work B. Acceptance C. The address of the seller D. Buyer's signatures
answer
C. The address of the seller. Don't forget a contract INCLUDES a procurement statement of work.
question
If worried about seller increasing profit in cost plus incentive fee (CPIF), what should you do?
answer
Cutting scope actually decreases profit on this type of contract. But, seller might invoice for items not chargeable to the project. Therefore, all invoiced costs should be audited.
question
A project performed under a cost reimbursable contract has finally entered the Close Procurements process. What must the buyer remember to do? A. Decrease the risk rating of the project B. Audit seller's cost submittals C. Evaluate the fee she is paying D. Make sure the seller is not adding resources.
answer
B. Audit seller's cost submittals. Evaluation of fee should have been done during Conduct Procurements process. Making sure the seller does not add resources may be a concern during the Control Procurements process, but it is not common during Close Procurements. Auditing the seller's cost submittals is a required aspect of the Close Procurements process.
question
An advantage of a fixed-price contract for the buyer is: A. Cost risk is lower B. Cost risk is higher C. There is little risk D. Risk is shared by all parties
answer
A. Cost risk is lower. YES, FIXED PRICE IS LOWER RISK FOR BUYER, BUT WE ARE TALKING ABOUT COST RISK (NOT ANY RISK).
question
Some procurement related items that would be tracked in the records management system:
answer
The proposal, procurement statement of work, contract terms and conditions, etc.
question
During which procurement processes does procurement negotiation occur? A. Plan Procurement Management and Close Procurements B. Control Procurements and Close Procurements C. Conduct Procurements and Control Procurements D. Conduct Procurements and Close Procurements
answer
D. Conduct Procurements and Close Procurements. Negotiation occurs during the Conduct Procurements process of course. Negotiation also occurs in the Close Procurements to settle any outstanding disputes.
question
You want to protect your company from financial risk associated with a large project that has limited scope definition. What is the best type of contract to choose? A. Fixed Price B. Cost plus percentage of cost C. Time and Material D. Cost plus fixed fee
answer
D. Cost plus fixed fee. Of the options given, the only contract that limits fees for large projects with limited scope definition is cost plus fixed fee.
question
If Party A and B signed off notes during contract negotiations, if item in the signed off notes was not in the contract, and buyer identifies that the seller didn't complete that item, is the seller obligated to complete the item.
answer
No, the seller is only obligated to complete what is in the contract (generally).
question
Contract terms and conditions require a work plan to be issued for the buyer's approval prior to commencing work, but the seller fails to provide one. Which of the following is the best thing for the buyer's project manager to do A. File a letter of intent B. Develop the work plan and issue it to the seller to move things along C. Issue a default letter D. Issue a stop work order to the seller until a work plan is prepared
answer
C. Issue a default letter. When a seller does not perform accourding to the contract terms and conditions, they have defaulted and the PM must take action. You might prefer a choice to ask vendor what is going on and investigate first.... But, this choice is not available. You must send formal written notice as soon as you become aware of the default so that you do not give up any right to receive the work plan in the future. You contact the seller for a discussion is the second thing you do. [Breach of contract and in default are generally the same thing]
question
Close Procurements is different from Close Project or Phase in that Close Procurements: A. Occurs before Close Project or Phase B. Is the only one to involve the customer C. Includes the return of property D. May be done more than once for each contract
answer
A. Occurs before Close Project or Phase. Close Procurements is done once for each procurement, at the end of the contract (not charter. We're talking about contract. There's typically one contract per seller on a project.). ALL PROCUREMENTS ARE CLOSED BEFORE THE PROJECT IS CLOSED.
question
Buyer refuses a deliverable because one requirement is missed. You agree with the buyer. What is the best thing to do? A. Explain that the contract is wrong and should be changed B. Issue a change order C. Review the requirements and meet with the responsible team member to review the WBS dictionary D. Call a meeting of the team to review the missed requirement
answer
C. Review the requirements and meet with the responsible team member to review the WBS dictionary. This is from seller's perspective. A seller cannot issue a change order (although they could request one). If requirement missed, should review the WBS to understand if cause was missing Work Package or work package failing to deliver. You should meet with responsible person to understand why (the cause). ?
question
Benefits of having a contract change control system and what is in this system?
answer
Having a contract change control system will allow you to establish the processes and procedures should you need to modify a contract. It contains paperwork, tracking systems, dispute resolution procedures, and approval levels necessary for authorizing changes. [PMBOK 5th edition, Page 383] [Project Procurement Also contains an extensive procurement changes approval process?
question
A buyer has just received a final set of deliverables from the seller and finds that they do not conform to the specifications that were originally planned. Where should the buyer expect to find documentation on how to handle non-conforming deliverables? A. Communication Plan B. The contract C. Quality Plan D. Scope Statement
answer
B. The contract. Requirements for formal deliverable acceptance and procedures for addressing non-conforming deliverables are usually defined in the contract. [PMBOK 5th edition, Pages 377, 378] [Project Procurement Management]
question
You are managing a software development project. The project will involve working with a remote team. One of the requirements is to set up a secure communication link. The lead time to set up the link is 45 days. Since the initial phase of the project involves requirements gathering, you believe that the link is only required after 3 months and you are planning accordingly. You would typically do this planning activity in: A. The Conduct Procurements process B. The Define Activities process C. The Plan Procurement Management process D. The Control Procurements process
answer
C - Determining what, when and how to purchase or acquire is done during the Plan Procurement Management process. [PMBOK 5th edition, Page 358] [Project Procurement Management]
question
_______________ - acquiring goods and services from an outside source
answer
procurement
question
Suppliers, vendors, contractors, subcontractors, and sellers are all examples of what?
answer
organizations/individuals who provide procurement services
question
Name at least 2 reasons to turn to outsourcing.
answer
access skills and technologies, reduce both fixed and recurrent costs, allow the client organization to focus on its core business, provide flexibility, increase accountability
question
_______________ - mutually binding agreement that obligates the seller to provide specified products or services and obligates the buyer to pay for them
answer
contract
question
What involves processes required to acquire goods and services for a project from outside the performing organization.
answer
project procurement management
question
Name the 4 main processes of project procurement management.
answer
planning procurement management, conducting procurements, controlling procurements, closing procurements
question
Which of the 4 main processes of project procurement management is the following? Determining what to procure and when and how to do it; decide what to outsource, type of contract, and the work for potential sellers
answer
planning procurement management
question
Which of the 4 main processes of project procurement management do the following outputs belong to? procurement management plan, procurement statements of work, procurement documents, source selection criteria, make-or-buy decisions, change requests, project document updates
answer
planning procurement management
question
_______________ - providers, contractors, suppliers who provide goods and services to other organizations
answer
sellers
question
Which of the 4 main processes of project procurement management is the following? Obtaining seller responses, selecting sellers, and awarding contracts
answer
conducting procurements
question
Which of the 4 main processes of project procurement management do the following outputs belong to? Selected sellers, agreements, resource calendars, change requests, updates to project management plan and other project documents
answer
conducting procurements
question
Which of the 4 main processes of project procurement management is the following? Managing relationships with sellers, monitoring contract performance, making changes as needed.
answer
controlling procurements
question
Which of the 4 main processes of project procurement management do the following outputs belong to? Work performance info, change requests, updates to project management plan, project documents, organizational process assets
answer
controlling procurements
question
Which of the 4 main processes of project procurement management is the following? Completion and settlement of each contract or agreement, including resolution of any open items.
answer
closing procurements
question
Which of the 4 main processes of project procurement management do the following outputs belong to? Closed procurements, organizational process assets updates
answer
closing procurements
question
__________________ - organization decides whether it should make certain products and perform certain services inside the organization, or if it's better to buy those products and services from an outside organization
answer
make-or-buy decisions
question
What are the 3 broad categories of contracts?
answer
fixed-price/lump-sum, cost reimbursable, time and material
question
What type of contract involves a fixed total price for a well-defined product or service.
answer
Fixed-price/lump-sum
question
What is the cost at which contractor assumes total responsibility for each additional dollar of contract cost?
answer
Point of Total Assumption (PTA)
question
What type of contract involves a payment to the supplier for direct and indirect actual costs.
answer
cost-reimbursable contract
question
What are the 4 types of cost-reimbursable contracts?
answer
cost plus: incentive fee, fixed fee, award fee, percentage of costs
question
What type of contract involves the buyer pays supplier for allowable performance costs along with predetermined fee and incentive bonus.
answer
cost plus incentive fee contract
question
What type of contract involves the buyer pays supplier for allowable performance costs and fixed fee payment that's usually based on a percentage of estimated costs.
answer
cost plus fixed fee contract
question
What type of contract involves the buyer pays supplier for allowable performance costs plus award fee based on satisfaction of subjective performance criteria.
answer
cost plus award fee contract
question
What type of contract involves the buyer pays supplier allowable performance costs with predetermined percentage based on total costs.
answer
cost plus percentage of costs contract
question
What type of contract is a hybrid of fixed-price and cost-reimbursable contracts?
answer
time and material contracts
question
What requires the buyer to pay the supplier a predetermined amount per unit of product or service?
answer
unit pricing
question
What's the name of the contract clause that allows the buyer or supplier to end the contract?
answer
termination clause
question
What are the 3 main tools/techniques to help in planning procurement management?
answer
make-or-buy analysis, expert judgement, market research
question
What is a general management technique used to determine whether an organization should make a product or perform a service inside the organization or buy it from someone else?
answer
make-or-buy analysis
question
What can be identified as a document that describes how the procurement processes will be managed, from developing documentation for making outside purchases or acquisitions to contract closures?
answer
procurement management plan
question
What can be identified as the description of the work required for the procurement?
answer
statement of work (SOW)
question
If SOW is used to describe only the work required for a particular contract, it's called a __________________________.
answer
contract statement of work
question
What are 2 common examples of procurement documents?
answer
request for proposal (RFP), request for quote (RFQ)
question
What can be identified as a document used to solicit proposals from prospective suppliers?
answer
request for proposal (RFP)
question
What can be identified as a document used to solicit quotes/bids from prospective suppliers?
answer
request for quote (RFQ)
question
_________________ - document prepared by seller when there are different approaches to meeting buyer needs
answer
proposal
question
_________________ - document prepared by sellers to provide pricing for standard items that buyer has clearly defined
answer
bid
question
What can be identified as a meeting with prospective sellers prior to preparation of their proposals/bids; helps ensure that everyone has a clear, common understanding of buyer's desired products or services
answer
bidders' conference
question
_________________ - oral or written acts or omissions by someone with actual or apparent authority that can be construed to have the same effect as a written change order
answer
constructive change orders
question
Name 3 tools to assist in closing procurements.
answer
procurement audits, negotiated settlements, records management system
question
_________________ - various procurement functions that are now done electronically
answer
e-procurement
question
Name the 7 types of e-procurement.
answer
web-based ERP, e-MRO, e-sourcing, e-tendering, e-reverse auctioning, e-informing, e-marketsites
question
Which of the following is an output of the contract closure process? A. Resource calendar B. Work performance info C. Procurement statements of work D. Updates to organizational process assets
answer
D. Updates to organizational process assets
question
The _____ is a description of the work required for a procurement. A. RFQ B. SOW C. RFP D. WBS
answer
B. SOW
question
True or false? While outsourcing, organizations should protect strategic information because it can become vulnerable in the hands of suppliers.
answer
True
question
In project procurement management, which of the following processes involve completion and settlement of each contract, including resolution of any open items? A. Planning procurement management B. Closing procurements C. Conducting procurements D. Controlling procurements
answer
B. Closing procurements
question
In project procurement management, the process of conducting procurements is part of the _____ process. A. closing B. executing C. planning D. monitoring and controlling
answer
B. executing
question
True or false? Make-or-buy analysis involves comparing the internal costs of providing a product with the cost of outsourcing.
answer
True
question
True or false? Procurement audits are often done during contract closure to identify lessons learned in the entire procurement process.
answer
True
question
True or false? Indirect costs are those costs can be traced back to a project in a cost-effective way.
answer
False
question
True or false? Contents of the procurement management plan vary with project needs.
answer
True
question
True or false? Suppliers are those organizations or individuals who provide procurement services.
answer
True
question
True or false? In project procurement management, a main output of the controlling process is a source selection criteria.
answer
False
question
A drawback of outsourcing is that: A. it cannot increase accountability of suppliers through a written contract. B. it can make an organization become overly dependent on particular suppliers. C. it invariably results in an increase in both fixed and recurrent costs. D. it does not provide access to specific skills or technologies.
answer
B. it can make an organization become overly dependent on particular suppliers
question
A document used to solicit quotes or bids from prospective suppliers is known as a(n) _____. A. RFQ B. WBS C. SOW D. RFP
answer
A. RFQ
question
True or false? Buyers absorb lesser risk with cost-reimbursable contracts than they do with fixed-price contracts.
answer
False
question
In project procurement management, an output of the _____ monitoring and controlling process. A. Change requests B. Make-or-buy decisions C. Selected sellers D. Resource calendars
answer
A. Change requests
question
True or false? Reviewing performance records reduces the risk of selecting a supplier with a poor track record.
answer
True
question
Which of the following is true of lump-sum contracts? A. They incur a high degree of risk for the buyer. B. They consist of a fee based on the satisfaction of subjective performance criteria. C. They involve a fixed total price for a well-defined product or service. D. They are also known as cost-reimbursable contracts.
answer
C. They involve a fixed total price for a well-defined product or service
question
The first step in project procurement management is: A. conducting procurements B. controlling procurements C. closing procurement management D. planning procurement management
answer
D. planning procurement management
question
After planning for procurement management, which of the following does the next process involve? A. Sending appropriate documentation to potential sellers B. Developing procurement statements of work C. Using expert judgement in planning purchases and acquisitions D. Determining the evaluation criteria for the contract award
answer
A. Sending appropriate documentation to potential sellers
question
True or false? A single contract can include all three categories of contracts.
answer
True
question
True or false? If an organization has no need to buy any products or services from outside the organization, then it has no need to perform any of the procurement management processes.
answer
True
question
True or false? Project procurement management consists primarily of two processes: assessing procurements and controlling procurements.
answer
False
question
True or false? Risk registers and stakeholder registers are outputs of the planning procurement process.
answer
False
question
True or false? A key factor in evaluating bids, particularly for projects involving information technology, is the past performance record of the bidder.
answer
True