Identify the statement that is NOT a major advantage of placing a project within a functional element of the parent organization.
answer
The functional division tends to be oriented towards activities particular to its function.
question
Identify the statement that is NOT a major disadvantage of placing a project within a functional element of the parent organization.
answer
The functional division contains the normal path of advancement for individuals whose expertise is in the functional area.
question
Identify the statement that is NOT a major advantage of placing a project within the pure project organization.
answer
The functional manager retains full line authority over project team members.
question
Identify the statement that is NOT a major disadvantage of placing a project within the pure project organization.
answer
The project manager has full line authority over the project.
question
If the project manager controls when and what people do while the functional managers control who will be assigned to the project and what technology will be used, the __________ organizational form is probably being used.
answer
matrix
question
In the systems approach to design, one organization would have to take responsibility for __________.
answer
the integrity of the project design
question
Identify the statement that is NOT a major advantage of placing a project in the matrix approach.
answer
The division of authority between the project manager and the functional managers is complex.
question
Identify the statement that is NOT a major disadvantage of placing the project in the matrix approach.
answer
The project manager takes responsibility for managing the project.
question
When a project requires the integration of inputs from several functional areas and involves sophisticated technology, but does not require all the technical specialists for the project on a full-time basis, the ___ organizational form should be used
answer
matrix
question
The process of dealing with uncertainties in projects has come to be known as __________.
answer
risk management
question
The project management office is often created by organizations to __________.
answer
establish consistent project management standards and methods
question
A major purpose of the project management office should be to serve as __________.
answer
a link between strategic management and project management
question
This member of the project team is in charge of product design and development and is responsible for functional analysis, specifications, drawings, cost estimates, quality/reliability, engineering changes, and documentation.
answer
system architect
question
This member of the project team is responsible for the efficient production of the product of the process, including the manufacturing engineering, design and production of tooling, production scheduling, and other production tasks.
answer
development engineer
question
This behavior in a project manager would be highly correlated with unsuccessful project management.
answer
conflict avoidance
question
This person is responsible for the installation, testing, and support of the product (process) once its engineering is complete.
answer
test engineer
question
One of the main technical problems faced by the project manager is meeting __________ without compromising performance.
answer
schedule and cost goals
question
An organization structure that is based on the Financial, Human Resources and Operational departments rather than by project is termed as a(n) __________.
answer
functional organization
question
The key to conflict resolution is to turn a __________ into a __________.
answer
win-lose situation, win-win situation
question
A major advantage of using a __________ placement for a project is that individual experts can be utilized by many different projects.
answer
functional
question
A characteristic of __________ projects is that the work these projects can cross time, space, organizational, and cultural boundaries.
answer
virtual
question
Virtual teams, when composed, should consist of “boundary spanners” who number about one in every __________ team members.
answer
6-7
question
A major contribution of ____ is to establish project administration procedures for selecting, initializing and planning, budgeting, and scheduling projects as well as to serve as a repository for reports.
answer
PMOs
question
Project priorities are more of a concern in the __________ stages of the project life cycle.
answer
earlier
question
Subletting tasks out to smaller contractors is known as
answer
subcontracting
question
The __________ organizational form is a pure project organization overlaid on the functional divisions of the parent firm
answer
matrix
question
The ________ matrix is most similar to the resembles the projectized organizational form.
answer
strong
question
The ______ matrix is least similar to the pure project organizational form.
answer
weak
question
The firm or organization within which the project is being conducted is known as the _____________
answer
parent organization
question
The __________ manager is typically responsible for a number of related projects, each with its own project manager.
answer
program
question
The ________ structure is a basic project document that describes all the work that must be done to complete the project and forms the basis for costing, scheduling, and work responsibility.
answer
work break down
question
It is the responsibility of the _______ to ensure that the project is structured in such a way as to allow for motivational factors to be used
answer
project manager