Supply Chain management Chapter 3 – Flashcards

Unlock all answers in this set

Unlock answers
question
A simple CPM network has five activities, A, B, C, D, and E. A is an immediate predecessor of C and of D. B is also an immediate predecessor of C and of D. C and D are both immediate predecessors of E. Given the above scenario, which of the following is correct?
answer
There are four paths in this network.
question
Which of these statements regarding time-cost tradeoffs in CPM networks is true?
answer
Crashing shortens the project duration by assigning more resources to one or more of the critical tasks.
question
With respect to PERT and CPM, slack__________
answer
is the amount of time a task may be delayed without changing the overall project completion time.
question
The critical path for the network activities shown below is _______ with duration _______. Activity Duration Immediate Predecessors A 4 B 2 A C 7 D 4 A E 5 B,C,D
answer
A-D-E; 13
question
The three phases involved in the management of large projects are:
answer
Planning, scheduling, and controlling
question
An activity on a PERT network has these time estimates: optimistic = 1, most likely = 2, and pessimistic = 5. Its expected time is:
answer
2.33
question
The critical path of a network is the__________
answer
longest time path through the network.
question
Dummy activities__________
answer
are used when two activities have identical starting and ending events.
question
With respect to PERT and CPM, slack is the amount of time a task may be delayed without changing the overall project completion time.
answer
Latest start is the term used to describe the latest time an activity can be started without delaying the entire project. Latest finish is the term used to describe the latest time an activity can be completed and not delay the completion time of the entire project. previous
question
Which of the following is a basic assumption of PERT?
answer
No activity in the network must be repeated.
question
The critical path for the network activities shown below is A-D-E with duration 13. Critical path activities are those activities that will delay the entire project if they are not completed on time. In this case, activity A is an immediate predecessor for A and D and the final activity is E. The sum of the duration for this network is 13 (4+4+5 = 13).
answer
2.33
question
Expected time (t) is calculated using the following formula: t = (a + 4m + b)/6, where a = optimistic time estimate (in this case 1); m = most likely time estimate (in this case 2); and b = pessimistic time estimate (in this case 5). Therefore;
answer
An activity on a PERT network has these time estimates: optimistic = 1, most likely = 2, and pessimistic = 5. Its expected time is: t = (1 + 4*2 + 5)/6 t = 14/6 t = 2.33
question
An activity has an optimistic time of 15 days, a most likely time of 18 days, and a pessimistic time of 27 days. What is the expected time?
answer
19 days
question
Which of the following is determined during the forward pass?
answer
Early start
question
An activity on a PERT network has these time estimates: optimistic = 2, most likely = 5, and pessimistic = 10. Its expected time is:
answer
5.33
question
An activity on a PERT network has these time estimates: optimistic =2, most likely = 3, and pessimistic 8. Its expected time and variance (if it is a critical activity) are:
answer
3.67 and 1
question
Which of the following statements regarding PERT analysis is true?
answer
Only critical activities contribute to the project variances.
question
PERT analysis computes the variance of the total project completion time as:
answer
The sum of all variances of all activities on the critical path
question
Expected time (t) is calculated using the following formula: t = (a + 4m + b) / 6, where a = optimistic time estimate (in this case 2); m = most likely time estimate (in this case 3); and b = pessimistic time estimate (in this case 8). Therefore; t = (2 + 4*3 + 8) / 6 t = 22 / 6 t = 3.67
answer
Variance (v) is calculated using the following formula: v = [(b-a) / 6]2, where b= pessimistic time estimate (in this case 8) and a = optimistic time estimate (in this case 2). Therefore; v = [(b-a) / 6]2 v = [(8-2) / 6]2 v = [6/6]2 v = [1]2 v = 1
question
Which of these statements regarding time-cost tradeoffs in CPM networks is true?
answer
Crashing shortens the project duration by assigning more resources to one or more of the critical tasks.
question
Which of the following statements regarding Gantt charts is true?
answer
Gantt charts are visual devices that show the duration of activities in a project.
question
__________ is the amount of time an individual activity in a network can be delayed without delaying the entire project.
answer
Slack time
question
The critical path for the network activities shown below is _______ with duration _______. Activity Duration Immediate Predecessors A 2 B 4 C 6 A,B D 1 A,B E 2 B,C,D
answer
B-C-E; 12
question
A project's critical path is composed of activities A (variance .33), B (variance .67), C (variance .33), and D (variance .17). What is the standard deviation on the critical path?
answer
1.22
question
An activity has an optimistic time of 11 days, a most likely time of 15 days, and a pessimistic time of 23 days. What is its variance?
answer
4
question
The true statement is that gantt charts are visual devices that show the duration of activities in a project.
answer
Gantt charts are not a precedence diagraming activity or method (such as AON or AOA networks) that create timelines and present the sequence in which activities should be performed. Instead, Gantt charts graphically specify all of the tasks involved in a project and how much time should be spent doing each activity. The four standard spines of Methods, Materials, Manpower, and Machinery are part of cause and effect diagrams and are typically used in the quality control process. previous
question
The standard deviation on the critical path is 1.22. To calculate the standard deviation you take the square root (?) of the sum of the critical path activity variances. In this case,
answer
Standard deviation = ?.33+.67+.33+.17 Standard deviation = ?1.5 Standard deviation = 1.22
question
The variance for this activity is 4. Variance (v) is calculated by using the following formula: v = [(b-a) / 6]2, where b = pessimistic time estimate (in this case 23) and a = optimistic time estimate (in this case 11). Therefore:
answer
v = [(b-a) / 6]2 v = [(23-11) / 6]2 v = [12 / 6]2 v = [2]2 v = 4 previous
question
In a PERT network, non-critical activities that have little slack need to be monitored closely__________
answer
because near-critical paths could become critical paths with small delays in these activities
question
WBS stands for which of the following project management tools?
answer
Work Breakdown Structure
question
The Beta distribution is used in project management to
answer
Calculate expected activity times
question
The EF of an activity is the:
answer
ES + Activity time
Get an explanation on any task
Get unstuck with the help of our AI assistant in seconds
New