a storage location is a key organizational level associated with inventory management
answer
true
question
the most relevant category of master data in inventory management is the plant
answer
false
question
a goods receipt cannot be posted without a reference to an order
answer
false
question
planned receipts occur when a reference document, such as a purchase order or a production order, does not exist
answer
false
question
a goods issue results in the creation of appropriate material, FI and CO documents
answer
true
question
a goods issue, unlike a goods receipt, can be posted without reference to an order
answer
false
question
a goods issue, unlike a goods receipt, results in a decrease in inventory
answer
true
question
a transfer posting always involves an actual movement of materials
answer
false
question
to change a material number you need to create a change request
answer
false
question
in a consignment scenario, when raw materials are consumed in the production process, the status of the materials is changed from warehouse stock to consignment
answer
false
question
a stock transfer involves physically moving materials
answer
true
question
one-step procedure, two-step procedure, and stock transport order are strategies for moving materials
answer
true
question
a material document is created during both the one-step and two-step procedures
answer
true
question
during the one-step procedure, two materials documents are created
answer
false
question
moving materials between two storage locations within the same plant or different plants is known a storage location to storage location transfer
answer
false
question
one-step procedure is possible only when the materials are in unrestricted use at the supplying location
answer
false
question
when transferring materials between storage locations in the same plant, if quantities are valued in the same way, then no FI document is created
answer
true
question
in plant to plant transfer in the two-step method, the FI document is created at the time of receipt
answer
false
question
a movement of materials between two plants in different company codes is called a company code to company code transfer
answer
true
question
stock transport orders with delivery include the invoice verification step
answer
false
question
in stock transport orders with delivery and billing, valuation is based on the purchase price in the STO
answer
true
question
inventory management keeps track of the quantity of materials in storage location, but it cannot determine their exact location
answer
true
question
a storage location can be linked to only one warehouse
answer
true
question
a storage type is a division of a storage section that is based on the characteristics of the space, materials, or activity
answer
false
question
storage sections represent the physical links between IM and WM
answer
false
question
shelf storage is an example of a storage type
answer
true
question
lightweight materials are designated as fast moving materials
answer
false
question
a picking area groups materials with the same material type
answer
false
question
storage bins are the smallest unit of space in a warehouse
answer
true
question
transfer requirements can be created manually as well as automatically
answer
true
question
transfer orders are used to execute warehouse movements
answer
true
question
transfer orders can only be created automatically
answer
false
question
target quantities, destination storage type, bin, and quant are examples of line item data in a transfer order
answer
true
question
transfer orders in the execute warehouse management step can be created with or without a reference document
answer
true
question
one of the steps of the inventory management process related to procurement is post goods issue
answer
false
question
inventory management in the production process involves a goods issue and a goods receipt
answer
true
question
a stock transfer from a storage bin in one warehouse to a storage bin in another warehouse is a possible scenario under which warehouse movements can occur
answer
false
question
lack of overall planning may result in excess inventory and lost sales
answer
true
question
when a company transfers part of the materials in stock from one distribution center to another this scenario is known as stock out
answer
false
question
material planning is one of the most complex processes within an organization
answer
true
question
planned orders are requests to produce materials
answer
true
question
MRP uses requirements to generate the final procurement proposals
answer
true
question
storage area is one of the organizational data elements in material planning
answer
false
question
product routings is one of the master data elements in material planning
answer
true
question
work scheduling data are defined at the client level
answer
false
question
MRP is defined at the plant level
answer
true
question
MRP data are specific to each plant
answer
true
question
in house production is the most common procurement type for raw materials
answer
false
question
semifinished goods are typically purchased from vendors
answer
false
question
MRP type specifies the production control technique used in planning
answer
true
question
consumption based planning calculates the requirements for a material based on current consumption data
answer
false
question
in time phased planning materials are ordered when the stock level reaches a predetermined level known as the reorder point
answer
false
question
consumption based planning assumes that future consumption will follow the same patterns as current consumption
answer
false
question
in a scenario when the need for brakes depends on the need to produce cars, consumption based planning will be an appropriate strategy to use
answer
false
question
typically semifinished goods and raw materials have dependent requirements
answer
true
question
the input to MRP is the independent requirement for the finished goods
answer
true
question
MPS is a mandatory step in the planning process and is usually followed by MRP
answer
false
question
period lot sizing procedures combine the requirement from multiple time periods such as days or weeks, into one lot
answer
true
question
for externally procured materials, the planned delivery time and the GR processing time are used to determine procurement time
answer
true
question
lot size dependent times remain the same regardless of the amount of the material being procured
answer
false
question
the BOM selection method in the material master identifies the criteria the system should use to select the BOM
answer
true
question
a BOM is used only in the materials planning process
answer
false
question
planning with final assembly takes into consideration current sales orders
answer
true
question
when using planning without final assembly components are made to order, and the finished product is made to stock
answer
false
question
the strategy group defines the strategy the systems uses to determine whether a quantity of material will be available on a specific day
answer
false
question
A BOM always identifies the components needed to make one unit of the finished products
answer
false
question
in make to stock strategy the production of the finished foods and any needed semifinished goods is triggered by a sales order
answer
false
question
consumption based planning derives dependent demand based on independent requirements and exploding the BOM
answer
false
question
a product group groups products with similar planning characteristics such as similar types
answer
true
question
whether SOP is required depends on the production planning strategy used for the material
answer
true
question
the MRP controller is a program in the SOP process that is responsible for creating procurement proposals and monitoring material availability
answer
false
question
SOP can be either flexible or standard
answer
true
question
the operations plan is an outcome of SOP
answer
true
question
after planning the master schedule items, MRP creates dependent requirements for the components of those items
answer
true
question
MPS is generally appropriate for high value items only
answer
True
question
MPS creates planned orders for the MPS items and dependent requirements for all items in the BOM
answer
false
question
net requirements calculation is one of the steps in MRP
answer
true
question
the lot size calculation step in MRP is used to determine whether there is a need to procure the material
answer
false
question
the ERP system initially uses forward scheduling and employs backward scheduling only if forward scheduling is unsuccessful
answer
false
question
a processing key is a control parameter that determines how the materials in the mRP list will be organized
answer
false
question
the schedule lines control parameter applies to scheduling agreements
answer
true
question
the MRP list, unlike the stock/requirements list, highlights changes to MRP elements that have occurred since MRP was executed
answer
false
question
the planning result report aggregates quantities for MRP elements to make it easier to view the overall picture
answer
true
question
sell from stock strategy uses inventory as a buffer between processes to decouple them of to make them less dependent on each other
answer
true