Project Management – Closing – Flashcards

Unlock all answers in this set

Unlock answers
question
At the end of a project, what documents will the project manager need for closure of the project?
answer
Scope definition and acceptance documentation and project closure guidelines Source: PMBOK® Guide p. 101
question
What phase is a project in when all the work specified in the contract scope of work are complete and the final product has been sent to the client?
answer
Closure Source: PMBOK®, Page 99
question
Performance reporting is important during closure of a particular project phase in order to:
answer
Close out the portion of the project scope and the associated activities. Source: PMBOK® Guide, Page 99
question
All the deliverables have been sent to the client and were formally accepted. The closure activities have been completed when a procurement audit turns up a problem. The project is considered to be:
answer
Complete Source: PMBOK® Guide p. 341
question
Your cost reimbursable contract project has finally entered closure. What must the buyer do?
answer
Audit seller's costs Source: World Class Contracting — Garrett, Page 93
question
The project team has completed all the project deliverables. The client has formally accepted the deliverables. Today you schedule the lessons learned meeting with the stakeholders as required by your organization. What is the status of the project?
answer
Incomplete until all deliverables are complete and accepted Source: PMBOK® Guide, Page 102
question
During administrative closure, you discover that formal performance reporting from one of your vendors has not been received. What should you do?
answer
Require the vendor to complete the work Source: PMBOK® Guide p. 341
question
A project is considered closed when:
answer
Archives are completed and filed Source: PMBOK® Guide, Page 102
question
The PMO has audited your last project and the audit report lists the term "Gold Plating." What is the issue being cited by the audit?
answer
The project was delivered with a positive variance in scope Source: Managing Project in Organizations — Frame, Page 129
question
Administrative closure is different than contract closure in that:
answer
Contract closure includes an audit of the terms and conditions while administrative closure does not Source: PMBOK® Guide, Pages 101, 341
question
You have assigned two team members to perform scope verification, reviewing the product documentation and conducting lessons learned reviews. What activity are the team members engaged in?
answer
Project or phase closure Source: PMBOK® Guide, Page 102
question
What is the purpose of the procurement audit?
answer
Identify the successes and failures that warrant transfer to other procurements or projects Source: PMBOK® Guide , Page 343
question
With a clear scope of work, a seller completes work as specified, but the buyer is not pleased with the results. The contract is:
answer
Complete Source: World Class Contracting—Garrett, Page 273
question
Due to force majeure, your project will be delayed by eight months. The customer has asked to end the contract citing problems with the location. What is the MOST appropriate thing to do in this situation?
answer
Complete contract closure Source: PMBOK® Guide p. 342
question
Contract and project closure both involve:
answer
Accepted deliverables Source: PMBOK® Guide, Pages 101, 344
question
You are managing a project and determine that the only way to resolve a vendor problem is to have it heard and resolved by a neutral party. To accomplish this, the project manager should use a(n):
answer
Arbitrator Source: World Class Contracting Garrett, Page 151
question
Documents that serve as historical records for future projects are archived:
answer
During closure Source: PMBOK® Guide, Page 102
question
Your seller has failed to deliver a major item for your project. What should you do?
answer
Notify the seller of the breach. Source: PMBOK® Guide, p. 337
question
In your last company, you were considered the "King of Metrics." You have worked for a new company for three months and you have recommended changes in the collection of project performance documents and creating historical records of past projects. What is the BEST way to accomplish this?
answer
Documenting lessons learned Source: PMBOK® Guide, Pages 102, 261, 344
question
In project closure what is the LAST thing to do?
answer
Release the team Source: Project Management Meredith & Mantel, Pages 554, 556
question
When is it BEST to perform administrative closure?
answer
At the end of each project phase Source: PMBOK® Guide, Page 99
question
In closing out a minor contract you discover that a deliverable has not been received. What should you do?
answer
Require that the deliverable be done Source: PMBOK® Guide, p. 341
question
An output of administrative closure is the creation of:
answer
Project archives Source: PMBOK® Guide, Page 102
question
The scope of work is completed on a project. The customer has asked for a change to provide service to the project product for 90 days. What should be done?
answer
Begin closure on the contract and sign a new one for the additional work Source: PMBOK® Guide, Page 100
question
Upon completion of administrative closure, you will have, formal acceptance documentation, project files, project closure documents and:
answer
Lessons learned Source: PMBOK® Guide, Page 102
question
When is the earliest time administrative closure should be completed?
answer
At the conclusion of each project phase Source: PMBOK® Guide, Page 99
question
Your project is nearing the end of the implementation phase. Before beginning the next phase, you should ensure that:
answer
The objectives of the prior phase have been obtained and accepted by the customer Source: PMBOK® Guide, Page 99
question
Your client terminates your contract for convenience. The project is now in:
answer
Closure Source: World Class Contracting —Garrett, Page 173
question
What is the BEST technique to ensure proper contract closure?
answer
Procurement audits Source: PMBOK® Guide, p. 343
question
Your PMO called this morning to ask why your lessons learned documentation has not been filed. You claim that last night your car hit a water buffalo and the service manager took a long time filling out the paperwork making you late. In addition, you tell them that as fate would have it, you had planned to do your lessons learned this very morning. Who do you invite to your office to assist in the creation of lessons learned?
answer
Stakeholders Source: Project Management Terms Ward, Page 115
question
The project management process includes several avenues of feedback and control. During the closure process, the most significant form of feed forward control is:
answer
Lessons learned Source: PMBOK® Guide, p. 261
question
Once a project is turned over and accepted:
answer
The client is now exposed to the risk of failure of the project to perform its intended function for its expected life Source: Wideman, Page IV-9
question
Your client terminates your contract for convenience. This means you are now implementing which process?
answer
Close Procurements Source: PMBOK, Section 12.4
question
The company PMO tells the project manager to create lessons learned. What do lessons learned include?
answer
Information on issues and risks Source: PMBOK, Section 4.6.3
question
In your last project to add street signs throughout Jay County, WI, the company procurement team was short-handed and particularly slow to respond to your requests for signs. What would be the MOST appropriate thing to do to ensure the issues are resolved for future projects?
answer
Conduct a procurement audit Source: PMBOK, Section 12.4.2
question
What is the process of documenting project successes and failures and recommendations to improve future performance on projects?
answer
Lessons learned Source: PMBOK, Section 4.6.3
question
As project manager, you have been called to a meeting with the contract administrator to conduct a procurement audit. The purpose of the audit is to:
answer
This review of successes and failures of the procurement Source: PMBOK, Section 12.4.3
question
Contract and administrative closure both involve what type of documentation?
answer
Archiving relevant documentation Source: PMBOK, Sections 12.4 and 4.6
question
The seller considers the contract closed when the following is complete:
answer
Formal written notice from the buyer Source: PMBOK, Sections 12.4.3
question
A structured review of the procurement process is called:
answer
A procurement audit Source: PMBOK, Sections 12.4.3
question
The causes of variances, the reasoning behind corrective action chosen should be documented in:
answer
Organizational process assets Source: PMBOK, Sections 4.6.3
question
There are outstanding issues, claims and disputes with one supplier for your project. A common method for addressing these is through:
answer
Negotiated settlements Source: PMBOK, Sections 12.4.2
Get an explanation on any task
Get unstuck with the help of our AI assistant in seconds
New