PMP 5th – Chapter 6 – Project Time Management – Flashcards

Unlock all answers in this set

Unlock answers
question
Project Time Management
answer
Includes the processes required to manage timely completion of the project.
question
Project Time Management Processes (7)
answer
1 Plan Schedule Management 2 Define Activities 3 Sequence Activities 4 Estimate Activity Resources 5 Estimate Activity Durations 6 Develop Schedule 7 Control Schedule
question
Schedule Model
answer
Representation of the plan for executing the project's activities including durations, dependencies, and other planning information, used to produce project schedules along with other scheduling artifacts.
question
Schedule Management Plan
answer
- A subsidiary plan of, and component of the project management plan through the Develop Project Management Plan process; - Identifies a scheduling method and scheduling tool; - Sets the format and establishes criteria for developing and controlling the project schedule; - May be formal or informal, highly detailed or broadly framed, based upon the needs of the project, and includes appropriate control thresholds; - Defines how schedule contingencies will be reported and assessed; - may be updated to reflect a change in the way the schedule is managed;
question
Scheduling Methodology
answer
Defines the rules and approaches for the scheduling process. Some of the better known methodologies include: - Critical path method (CPM) - Critical chain
question
The majority of effort in the Project Time Management Knowledge Area will occur in...
answer
The Control Schedule process to ensure completion of project work in a timely manner.
question
Process: Plan Schedule Management
answer
- The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule. - The benefit of this process is that it provides guidance and direction on how the project schedule will be managed throughout the project.
question
Input (4) of the Plan Schedule Management process
answer
1 Project management plan 2 Project charter 3 Enterprise environmental factors 4 Organizational process assets
question
Project management plan
answer
- Contains information used to develop the schedule management plan which includes: - scope baseline => includes the project scope statement and the work breakdown structure (WBS) details used for defining activities, duration estimation, and schedule management; - Other information => Other scheduling related cost, risk, and communications decisions from the project management plan are used to develop the schedule.
question
Project charter
answer
Defines the summary milestone schedule and project approval requirements that will influence the management of the project schedule.
question
Enterprise environmental factors
answer
Influence the Plan Schedule Management process include: - Organizational culture and structure can all influence schedule management; - Resource availability and skills that may influence schedule planning; - Project management software provides the scheduling tool and alternative possibilities for managing the schedule; - Published commercial information, such as resource productivity information, is often available from commercial databases that track; - Organizational work authorization systems.
question
Organizational process assets
answer
Factors can influence: - Monitoring and reporting tools to be used; - Historical information; - Schedule control tools; - formal and informal schedule control related policies, procedures, and guidelines; - Templates; - Project closure guidelines; - Change control procedures; - Risk control procedures including risk categories, probability definition and impact, and probability and impact matrix.
question
Tools & Techniques (3) of the Plan Schedule Management process
answer
1 Expert judgment 2 Analytical techniques 3 Meetings
question
Expert judgment
answer
- Guided by historical information, provides valuable insight about the environment and information from prior similar projects.
question
Analytical techniques
answer
- The process involve strategic options to estimate and schedule the project such as: scheduling methodology, scheduling tools and techniques, estimating approaches, formats, and project management software. Examples: - rolling wave planning - leads and lags - alternatives analysis - methods for reviewing schedule performance
question
Meetings
answer
Project teams may hold planning meetings to develop the schedule management plan. Participants: project manager, the project sponsor, selected project team members, selected stakeholders, anyone with responsibility for schedule planning or execution, and others as needed.
question
Output (1) of the Plan Schedule Management process
answer
1 Schedule management plan
question
Schedule management plan
answer
A component of the project management plan that establishes the criteria and the activities for developing, monitoring, and controlling the schedule. The schedule management plan may be formal or informal, highly detailed or broadly framed, based upon the needs of the project, and includes appropriate control thresholds.
question
The schedule management plan can establish the following
answer
• Project schedule model development • Level of accuracy • Units of measure • Organizational procedures links • Project schedule model maintenance • Control thresholds • Rules of performance measurement • Reporting formats • Process descriptions
question
Project schedule model development
answer
The scheduling methodology and the scheduling tool to be used in the development of the project schedule model are specified.
question
Level of accuracy
answer
The acceptable range used in determining realistic activity duration estimates is specified and may include an amount for contingencies.
question
Units of measure
answer
Each unit used in measurements (such as staff hours, staff days, or weeks for time measures, or meters, liters, tons, kilometers, or cubic yards for quantity measures) is defined for each of the resources.
question
Organizational procedures links
answer
The WBS provides the framework for the schedule management plan, allowing for consistency with the estimates and resulting schedules.
question
Project schedule model maintenance
answer
The process used to update the status and record progress of the project in the schedule model during the execution of the project is defined.
question
Control thresholds
answer
Variance thresholds for monitoring schedule performance may be specified to indicate an agreed-upon amount of variation to be allowed before some action needs to be taken. Thresholds are typically expressed as percentage deviations from the parameters established in the baseline plan.
question
Rules of performance measurement
answer
Earned value management (EVM) rules or other physical measurement rules of performance measurement are set. For example, the schedule management plan may specify: ○○ Rules for establishing percent complete, ○○ Control accounts at which management of progress and schedule will be measured, ○○ Earned value measurement techniques (e.g., baselines, fixed-formula, percent complete, etc.) to be employed (for more specific information, refer to the Practice Standard for Earned Value Management) [9], ○○ Schedule performance measurements such as schedule variance (SV) and schedule performance index (SPI) used to assess the magnitude of variation to the original schedule baseline.
question
Reporting formats
answer
The formats and frequency for the various schedule reports are defined.
question
Process descriptions
answer
Descriptions of each of the schedule management processes are documented.
question
Process: Define Activities
answer
- The process of identifying the specific actions to be performed to produce the project deliverables. - The key benefit of this process is to break down work packages into activities that provide a basis for estimating, scheduling, executing, monitoring, and controlling the project work.
question
Inputs (4) of the Define Activities process
answer
1 Schedule management plan 2 Scope baseline 3 Enterprise environmental factors 4 Organizational process assets
question
Schedule management plan
answer
A key input from the schedule management plan is the prescribed level of detail necessary to manage the work.
question
Scope Baseline
answer
The project deliverables, constraints, and assumptions documented in the project scope baseline are considered explicitly while defining activities.
question
Enterprise Environmental Factors
answer
Influence the Define Activities process include: - Organizational cultures and structure, - Published commercial information from commercial databases - The project management information system (PMIS)
question
Organizational Process Assets
answer
- Existing formal and informal activity planning-related policies, procedures, and guidelines, such as the scheduling methodology, that are considered in developing the activity definitions. - Lessons-learned knowledge base containing historical information regarding activities lists used by previous similar projects.
question
Tools & Techniques (3) Define Activities process
answer
1 Decomposition 2 Rolling wave planning 3 Expert judgment
question
Decomposition
answer
- Involves subdividing the project work packages into smaller, more manageable components called activities. - Activities represent the effort needed to complete a work package. - The Define Activities process defines the final outputs as activities rather than deliverables, as done in the Create WBS process. - The activity list, WBS, and WBS dictionary can be developed either sequentially or concurrently, with the WBS and WBS dictionary as the basis for development of the final activity list. - Each work package within the WBS is decomposed into the activities required to produce the work package deliverables. - Involving team members in the decomposition can lead to better and more accurate results.
question
Rolling Wave Planning
answer
A form of progressive elaboration (iterative) planning where the work to be accomplished in the near term is planned in detail and future work is planned at a higher level of the WBS.
question
Expert Judgement
answer
Project team members or other experts, who are experienced and skilled in developing detailed project scope statements, the WBS, and project schedules, can provide expertise in defining activities.
question
Outputs (3) of the Define Activities process
answer
1 Activity list 2 Activity attributes 3 Milestone list
question
Activity List
answer
A comprehensive list including all schedule activities required on the project. The activity list includes the activity identifier and a scope of work description for each activity in sufficient detail to ensure that project team members understand what work is required to be completed.
question
Activity Attributes
answer
Activity attributes extend the description of the activity by identifying the multiple components associated with each activity.
question
Components of Activity Attributes
answer
-The components for each activity evolve over time. - During the initial stages of the project they include the Activity ID, WBS ID, and Activity Name, and when completed may include activity codes, activity description, predecessor activities, successor activities, logical relationships, leads and lags, resource requirements, imposed dates, constraints, and assumptions.
question
Activity attributes can be used to
answer
- Identify the person responsible for executing the work, - geographic area, or - place where the work has to be performed, and - activity type such as level of effort (LOE), discrete effort, and apportioned effort (AE).
question
Activity attributes are used for
answer
Schedule development and for selecting, ordering, and sorting the planned schedule activities in various ways within reports.
question
Milestone List
answer
Identifies all milestones and indicates whether the milestone is mandatory, such as those required by contract, or optional, such as those based upon historical information.
question
Milestone
answer
- A significant point or event in the project. -They have zero duration because milestones represent a moment in time.
question
Process: Sequence Activities
answer
- The process of identifying and documenting relationships among the project activities - The key benefit of this process is that it defines the logical sequence of work to obtain the greatest efficiency given all project constraints.
question
Characteristics of Sequence Activities
answer
- Every activity and milestone except the first and last are connected to at least one predecessor and one successor. - It may be necessary to use lead or lag time between activities to support a realistic and achievable project schedule. - Sequencing can be performed by using project management software or by using manual or automated techniques.
question
Inputs (7) of the Sequence Activities process
answer
1 Schedule management plan 2 Activity list 3 Activity attributes 4 Milestone list 5 Project scope statement 6 Enterprise environmental factors 7 Organizational process assets
question
Schedule management plan
answer
Identifies the scheduling method and tool to be used for the project, which will guide how the activities may be sequenced.
question
Activity list
answer
Contains all schedule activities required on the project, which are to be sequenced. Dependencies and other constraints for these activities can influence the sequencing of the activities.
question
Activity attributes
answer
Describe a necessary sequence of events or defined predecessor or successor relationships.
question
Milestone list
answer
The milestone list may have scheduled dates for specific milestones, which may influence the way activities are sequenced.
question
Project Scope Statement
answer
Contains the product scope description, which includes product characteristics that may affect activity sequencing, such as the physical layout of a plant to be constructed or subsystem interfaces on a software project. While these effects are often apparent in the activity list, the product scope description is generally reviewed to ensure accuracy.
question
Enterprise environmental factors
answer
• Government or industry standards, • Project management information system (PMIS), • Scheduling tool, • Company work authorization systems.
question
Organizational process assets
answer
Factors can be influence: project files from the corporate knowledge base used for scheduling methodology, existing formal and informal activity planning-related policies, procedures, and guidelines, such as the scheduling methodology that are considered in developing logical relationships, and templates that can be used to expedite the preparation of networks of project activities. Related activity attributes information in templates can also contain additional descriptive information useful in sequencing activities.
question
Tools & Techniques (3) Sequence Activities process
answer
1 Precedence diagramming method (PDM) 2 Dependency determination 3 Leads and lags
question
Precedence Diagramming Method (PDM)
answer
- Also referred to as Activity-On-Node (AON) - A method used in Critical Path Methodology (CPM) for constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activities, and connects them with arrows that show the logical relationships that exist between them. - The method used by most project management software packages.
question
PDM
answer
Precedence Diagramming Method
question
CPM
answer
Critical Path Methodology
question
AON
answer
Activity-On-Node.
question
Precedence Diagramming Method (PDM) Relationship Types
answer
- Finish-to-start (FS). - Finish-to-finish (FF). - Start-to-start (SS). - Start-to-finish (SF).
question
FS
answer
Finish-to-start. The initiation of the successor activity depends upon the completion of the predecessor activity. The most commonly used type of precedence relationship
question
FF
answer
Finish-to-finish. The completion of the successor activity depends upon the completion of the predecessor activity.
question
SS
answer
Start-to-start. The initiation of the successor activity depends upon the initiation of the predecessor activity.
question
SF
answer
Start-to-finish. The completion of the successor activity depends upon the initiation of the predecessor activity.
question
Dependency Determination
answer
- Mandatory dependencies - Discretionary dependencies - External dependencies - Internal dependencies
question
Mandatory Dependencies
answer
- Mandatory dependencies are those that are contractually required or inherent in the nature of the work. - Also sometimes referred to as hard logic or hard dependencies.
question
Examples of Mandatory Dependencies
answer
Mandatory dependencies often involve physical limitations: - construction project where it is impossible to erect the superstructure until after the foundation has been built; - an electronics project, where a prototype must be built before it can be tested.
question
Discretionary Dependencies
answer
- Discretionary dependencies are established based on knowledge of best practices within a particular application area or some unusual aspect of the project where a specific sequence is desired, even though there may be other acceptable sequences. - Also sometimes referred to as preferred logic, preferential logic, or soft logic.
question
Fast Tracking and Discretionary Dependencies
answer
- Discretionary dependencies should be fully documented since they can create arbitrary total float values and can limit later scheduling options. - When fast tracking techniques are employed, these discretionary dependencies should be reviewed and considered for modification or removal.
question
External Dependencies
answer
External dependencies involve a relationship between project activities and non-project activities. These dependencies are usually outside the project team's control.
question
Internal Dependencies
answer
Internal dependencies involve a precedence relationship between project activities and are generally inside the project team's control.
question
Leads and Lags
answer
- The project management team determines the dependencies that may require a lead or a lag to accurately define the logical relationship. - The use of leads and lags should not replace schedule logic. - Activities and their related assumptions should be documented.
question
Lead
answer
Allows an acceleration of the successor activity
question
Lag
answer
Directs a delay in the successor activity
question
Outputs (2) of the Sequence Activities process
answer
1 Project schedule network diagrams 2 Project documents updates
question
Project Schedule Network Diagram
answer
- It is a graphical representation of the logical relationships, also referred to as dependencies, among the project schedule activities. - The project schedule network diagram can be produced manually or by using project management software.
question
Components of a Project Schedule Network Diagram
answer
- It can include full project details, or have one or more summary activities. - A summary narrative can accompany the diagram and describe the basic approach used to sequence the activities. - Any unusual activity sequences within the network should be fully described within the narrative.
question
Project Document Updates
answer
Project documents that may be updated include: - Activity lists - Activity attributes - Milestone list - Risk register
question
Process: Estimate Activity Resources
answer
- The process of estimating the type and quantities of material, people, equipment, or supplies required to perform each activity. - The key benefit of this process is that it identifies the type, quantity, and characteristics of resources required to complete the activity which allows more accurate cost and duration estimates.
question
Inputs (8) of the Estimate Activity Resources process
answer
1 Schedule management plan 2 Activity list 3 Activity attributes 4 Resource calendars 5 Risk register 6 Activity cost estimates 7 Enterprise environmental factors 8 Organizational process assets
question
Schedule management plan
answer
Identifies the level of accuracy and the units of measure for the resources to be estimated.
question
Activity list
answer
Identifies the activities which will need resources.
question
Activity Attributes
answer
Provides the primary data input for use in estimating those resources required for each activity.
question
Resource Calendars
answer
Information on which resources (such as people, equipment, and material) are potentially available during planned activity period.
question
Characteristics of Resource Calendars
answer
- Used for estimating resource utilization. - Resource calendars specify when and how long identified project resources will be available during the project. - This information may be at the activity or project level. - This knowledge includes consideration of attributes such as resource experience and/or skill level, as well as various geographical locations from which the resources originate and when they may be available.
question
Composite Resource Calendar
answer
Includes the availability, capabilities, and skills of human resources
question
Risk Register
answer
- Events may impact resource selection and availability. - Updates to the risk register are included with project documents updates.
question
Activity Cost Estimates
answer
The cost of resources may impact resource selection.
question
Enterprise Environmental Factors
answer
Factors can influence: resource location, availability, and skills.
question
Organizational Process Assets
answer
Factors can influence: - Policies and procedures regarding staffing. - Policies and procedures relating to rental and purchase of supplies and equipment. - Historical information regarding types of resources used for similar work on previous project.
question
Tools & Techniques (5) Estimate Activity Resources process
answer
1 Expert judgment 2 Alternative analysis 3 Published estimating data 4 Bottom-up estimating 5 Project management software
question
Expert Judgement
answer
Often required to assess the resource-related inputs to this process. Any group or person with specialized knowledge in resource planning and estimating can provide such expertise.
question
Alternative Analysis
answer
Many schedule activities have alternative methods of accomplishment. They include using various levels of resource capability or skills, different size or type of machines, different tools (hand versus automated), and makerent-or-buy decisions regarding the resource.
question
Published Estimating Data
answer
Several companies routinely publish updated production rates and unit costs of resources for an extensive array of labor trades, material, and equipment for different countries and geographical locations within countries.
question
Bottom Up Estimating
answer
- It is a method of estimating project duration or cost by aggregating the estimates of the lower-level components of the WBS. - When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail. - The resource needs are estimated. - These estimates are then aggregated into a total quantity for each of the activity's resources.
question
Bottom Up Estimating Activity Dependencies
answer
- Activities may or may not have dependencies between them that can affect the application and use of resources. - If there are dependencies, this pattern of resource usage is reflected and documented in the estimated requirements of the activity.
question
Project management software
answer
Has the capability to help plan, organize, and manage resource pools and develop resource estimates. Depending on the sophistication of the software, resource breakdown structures, resource availability, resource rates and various resource calendars can be defined to assist in optimizing resource utilization.
question
Outputs (3) of the Estimate Activity Resources process
answer
1 Activity resource requirements 2 Resource breakdown structure 3 Project documents updates
question
Activity Resource Requirements
answer
- Identifies the types and quantities of resources required for each activity in a work package. - These requirements can then be aggregated to determine the estimated resources for each work package and work period. - The amount of detail and the level of specificity of the resource requirement descriptions can vary by application area.
question
Resource Requirements Documentation
answer
For each activity, can include the basis of estimate for each resource, as well as the assumptions that were made in determining which types of resources are applied, their availability, and what quantities are used.
question
Resource Breakdown Structure
answer
A hierarchical structure of the identified resources by resource category and resource type.
question
Examples of Resource Categories
answer
labor, material, equipment, and supplies
question
Examples of Resource Types
answer
skill level, grade level or other information as appropriate to the project
question
Purpose of Resource Breakdown Structure
answer
Useful for organizing and reporting project schedule data with resource utilization information.
question
Project Document Updates
answer
- Activity list - Activity attributes - Resource calendars
question
Process: Estimate Activity Durations
answer
- The process of approximating the number of work periods needed to complete individual activities with estimated resources. - The key benefit of this process is that it provides the amount of time each activity will take to complete.
question
Characteristics of Estimate Activity Durations
answer
- Uses information on activity scope of work, required resource types, estimated resource quantities, and resource calendars. - The inputs for the estimates of activity duration originate from the person or group on the project team who is most familiar with the nature of the work in the specific activity. - The duration estimate is progressively elaborated, and the process considers the quality and availability of the input data. - Requires that the amount of work effort required to complete the activity is estimated and the amount of resources to be applied to complete the activity is estimated; these are used to approximate the number of work periods (activity duration) needed to complete the activity. - All data and assumptions that support duration estimating are documented for each estimate of activity duration.
question
Inputs (10) of the Estimate Activity Durations process
answer
1 Schedule management plan 2 Activity list 3 Activity attributes 4 Activity resource requirements 5 Resource calendars 6 Project scope statement 7 Risk register 8 Resource breakdown structure 9 Enterprise environmental factors 10 Organizational process assets
question
Schedule Management Plan
answer
Defines the method used and the level of accuracy along with other criteria required to estimate activity duration including the project update cycle.
question
Activity list
answer
Identifies the activities that will need duration estimates.
question
Activity attributes
answer
Provide the primary data input for use in estimating durations required for each activity in the activity list.
question
Activity Resource Requirements
answer
Will have an effect on the duration of the activity, since the resources assigned to the activity and the availability of those resources will significantly influence the duration of most activities.
question
Resource Calendars
answer
The resource calendars influence the duration of schedule activities due to the availability of specific resources, type of resources, and resources with specific attributes.
question
Project Scope Statement
answer
- The constraints and assumptions from the project scope statement are considered when estimating the activity duration. -Examples of the Assumptions: - Existing conditions, - Availability of information, and - Length of the reporting periods Examples of the Constraints: - Available skilled resources, and - Contract terms and requirements
question
Risk Register
answer
- Provides the list of risks, along with the results of risk analysis and risk response planning. - Updates to the risk register are included with project document updates.
question
Resource Breakdown Structure
answer
Provides a hierarchical structure of the identified resources by resource category and resource type.
question
Enterprise Environmental Factors
answer
Factors can influence: - Duration estimating databases and other reference data - Productivity metrics - Published commercial information - Location of team members.
question
Organizational Process Assets
answer
Factors can influence: - Historical duration information - Project calendars - Scheduling methodology - Lessons learned
question
Tools & Techniques (6) for Estimate Activity Durations process
answer
1 Expert judgment 2 Analogous estimating 3 Parametric estimating 4 Three-point estimating 5 Group decision-making techniques 6 Reserve analysis
question
Expert Judgement
answer
- Guided by historical information, can provide duration estimate information or recommended maximum activity durations from prior similar projects. - Can also be used to determine whether to combine methods of estimating and how to reconcile differences between them.
question
Analogous Estimating
answer
- Technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project. - Uses parameters such as duration, budget, size, weight, and complexity, from a previous, similar project, as the basis for estimating the same parameter or measure for a future project.
question
Characteristics of Analogous Estimating
answer
- When estimating duration, this technique relies on the actual duration of previous, similar projects as the basis for estimating the duration of the current project. - It is a gross value estimating approach, sometimes adjusted for known differences in project complexity. - Frequently used to estimate project duration when there is a limited amount of detailed information about the project. - Uses historical information and expert judgment. - Generally less costly and time consuming than other techniques, but it is also generally less accurate. - Can be applied to a total project or to segments of a project and may be used in conjunction with other estimating methods. - Is most reliable when the previous activities are similar in fact and not just in appearance, and the project team members preparing the estimates have the needed expertise.
question
Parametric Estimating
answer
Uses a statistical relationship between historical data and other variables (e.g., square footage in construction) to calculate an estimate for activity parameters, such as cost, budget, and duration. Activity durations can be quantitatively determined by multiplying the quantity of work to be performed by labor hours per unit of work.
question
Characteristics of Parametric Estimating
answer
- Can produce higher levels of accuracy depending upon the sophistication and underlying data built into the model. - Can be applied to a total project or to segments of a project, in conjunction with other estimating methods.
question
Three-Point Estimates
answer
The accuracy of activity duration estimates can be improved by considering estimation uncertainty and risk.
question
PERT
answer
Program Evaluation and Review Technique. Uses three estimates to define an approximate range for an activity's duration. PERT analysis calculates an Expected (tE) activity duration using a weighted average of these three estimates.
question
PERT Estimate Types
answer
- Most Likely - Optimistic - Pessimistic
question
PERT: Most Likely Estimate
answer
The duration of the activity, given the resources likely to be assigned, their productivity, realistic expectations of availability for the activity, dependencies on other participants, and interruptions.
question
PERT: Optimistic Estimate
answer
The activity duration is based on analysis of the best-case scenario for the activity.
question
PERT: Pessimistic Estimate
answer
The activity duration is based on analysis of the worst-case scenario for the activity.
question
Benefit of PERT
answer
Duration estimates based on the PERT equation, or even on a simple average of the three points, may provide more accuracy, and the three points clarify the range of uncertainty of the duration estimates.
question
Group decision-making techniques
answer
- Team-based approaches: - brainstorming - the Delphi or nominal group techniques, are useful for engaging team members to improve estimate accuracy and commitment to the emerging estimates. - Involving a structured group of people who are close to the technical execution of work in the estimation process, additional information is gained and more accurate estimates obtained. - People are involved in the estimation process, their commitment towards meeting the resulting estimates increases.
question
Reserve Analysis
answer
Duration estimates may include contingency reserves, (sometimes referred to as time reserves or buffers) into the overall project schedule to account for schedule uncertainty.
question
Contingency Reserves
answer
Time reserves or buffers. May be a percentage of the estimated activity duration, a fixed number of work periods, or may be developed by using quantitative analysis methods.
question
Characteristics of Contingency Reserves
answer
- As more precise information about the project becomes available, the contingency reserve may be used, reduced, or eliminated. - Contingency should be clearly identified in schedule documentation.
question
Outputs (2) of the Estimate Activity Durations process
answer
1 Activity duration estimates 2 Project documents updates
question
Activity Duration Estimates
answer
Are quantitative assessments of the likely number of work periods that will be required to complete an activity. Duration estimates do not include any lags. May include some indication of the range of possible results. For example: - 2 weeks ± 2 days to indicate that the activity will take at least eight days and no more than twelve (assuming a five-day workweek). - 15% probability of exceeding three weeks to indicate a high probability—85% percent—that the activity will take three weeks or less.
question
Project Document Updates
answer
- Activity attributes - Assumptions made in developing the activity duration estimate such as skill levels and availability
question
Process: Develop Schedule
answer
- The process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model. - The key benefit of this process is that by entering schedule activities, durations, resources, resource availabilities, and logical relationships into the scheduling tool, it generates a schedule model with planned dates for completing project activities.
question
Characteristics of Develop Schedule
answer
- Entering the activities, durations, and resources into the scheduling tool generates a schedule with planned dates for completing project activities. - It determines the planned start and finish dates for project activities and milestones. - Developing an acceptable project schedule is often an iterative process. - Schedule development can require the review and revision of duration estimates and resource estimates to create an approved project schedule that can serve as a baseline to track progress. - Revising and maintaining a realistic schedule continues throughout the project as work progresses, the project management plan changes, and the nature of risk events evolves.
question
Inputs (13) of the Develop Schedule process
answer
1 Schedule management plan 2 Activity list 3 Activity attributes 4 Project schedule network diagrams 5 Activity resource requirements 6 Resource calendars 7 Activity duration estimates 8 Project scope statement 9 Risk register 10 Project staff assignments 11 Resource breakdown structure 12 Enterprise environmental factors 13 Organizational process assets
question
Schedule management plan
answer
Identifies the scheduling method and tool used to create the schedule, and how the schedule is to be calculated.
question
Activity List
answer
Identifies the activities that will be included in the schedule model.
question
Activity Attributes
answer
Provide the details used to build the schedule model.
question
Project Schedule Network Diagrams
answer
Contain the logical relationships of predecessors and successors that will be used to calculate the schedule.
question
Activity Resource Requirements
answer
Identify the types and quantities of resources required for each activity used to create the schedule model.
question
Resource calendars
answer
Contain information on the availability of resources during the project.
question
Activity duration estimates
answer
Contain the quantitative assessments of the likely number of work periods that will be required to complete an activity that will be used to calculate the schedule.
question
Project Scope Statement
answer
Contains assumptions and constraints that can impact the development of the project schedule.
question
Risk Register
answer
Provides the details of all identified risks and their characteristics that affect the schedule model.
question
Project Staff Assignments
answer
Specify which resources are assigned to each activity.
question
Resource Breakdown Structure
answer
Provides the details by which resource analysis and organizational reporting can be done.
question
Entperise Environmental Factors
answer
Factors can be include: - Standards - Communication channels - Scheduling tool to be used in developing the schedule model.
question
Organizational Process Assets
answer
Factors can be include: - Scheduling methodology - Project calendar
question
Tools & Techniques (8) for Develop Schedule process
answer
1 Schedule network analysis 2 Critical path method 3 Critical chain method 4 Resource optimization techniques 5 Modeling techniques 6 Leads and lags 7 Schedule compression 8 Scheduling tool
question
Scheduling Network Analysis
answer
A technique that generates the project schedule model. It employs various analytical techniques, such as critical path method, critical chain method, what-if analysis, and resource leveling to calculate the early and late start and finish dates for the uncompleted portions of project activities. Some network paths may have points of path convergence or path divergence that can be identified and used in schedule compression analysis or other analyses.
question
Critical Path Method (CPM)
answer
- A method used to estimate the minimum project duration and determine the amount of scheduling flexibility on the logical network paths within the schedule model. - Calculates the theoretical early start and finish dates, and late start and finish dates, for all activities without regard for any resource limitations, by performing a forward and backward pass analysis through the schedule network. - The resulting early and late start and finish dates are not necessarily the project schedule; rather, they indicate the time periods within which the activity could be scheduled, given activity durations, logical relationships, leads, lags, and other known constraints.
question
Activity Total Float
answer
Calculated early start and finish dates, and late start and finish dates, may be affected by activity total float, which provides schedule flexibility and, may be positive, negative, or zero.
question
Critical Path
answer
Have either a zero or negative Total Float
question
Total Float
answer
On any network path, the schedule flexibility is measured by the positive difference between early and late dates.
question
Critical Activities
answer
Schedule activities on a critical path.
question
Zero Total Float
answer
Critical Path
question
Networks are going to have multiple...
answer
Near critical paths
question
produce network paths with a zero or positive total float
answer
Adjustments to activity durations, logical relationships, leads and lags, or other schedule constraints.
question
Free Float
answer
The amount of time that an activity can be delayed without delaying the early start date of any immediate successor activity within the network path. Can be determined after the total float of network path has been calculated.
question
Critical Chain Method (CCM)
answer
Is a schedule network analysis technique that modifies the project schedule to account for limited resources. Adds duration buffers that are non-work schedule activities to manage uncertainty.
question
Duration of a Project
answer
- Should be calculated after drawing a network diagram and determining the critical path. - The length of the critical path and not the sum of the duration of all the tasks in the project.
question
Slack for tasks on the critical path
answer
is equal to zero
question
The more critical paths
answer
the more project risk
question
Negative Critical Path
answer
The project float compares the critical path with an externally imposed date and may be negative. You may be forced to fast track or perform crashing to ensure that the project is completed on time as required by the management. There will be no change to the critical path.
question
Determining the Critical Chain
answer
- Initially, the project schedule network diagram is built using duration estimates with required dependencies and defined constraints as inputs. - The critical path is then calculated. - After the critical path is identified, resource availability is entered and the resource-limited schedule result is determined. - The resulting schedule often has an altered critical path.
question
Critical Chain
answer
The resource-constrained critical path
question
Project Buffer
answer
One buffer, placed at the end of the critical chain, protects the target finish date from slippage along the critical chain.
question
Feeding Buffer
answer
Additional buffers are placed at each point that a chain of dependent tasks not on the critical chain feeds into the critical chain. Feeding buffers thus protect the critical chain from slippage along the feeding chains.
question
Duration Buffers
answer
- Non-work schedule activities to manage uncertainty. - The size of each buffer should account for the uncertainty in the duration of the chain of dependent tasks leading up to that buffer. - Once the buffer schedule activities are determined, the planned activities are scheduled to their latest possible planned start and finish dates.
question
The Critical Chain Method focuses on
answer
Consequently, instead of managing the total float of network paths, the critical chain method focuses on managing remaining buffer durations against the remaining durations of task chains.
question
Resource optimization techniques
answer
Example of resource optimization techniques that can be used to adjust the schedule model due to demand and supply of resources. Can be: - Resource Leveling - Resource Smoothing
question
Resource Leveling
answer
It is a schedule network analysis technique applied to a schedule that has already been analyzed by the critical path.
question
Characteristics of Resource Leveling
answer
- Can be used when shared or critical required resources are only available at certain times, are only available in limited quantities, or to keep resource usage at a constant level. - Is necessary when resources have been over-allocated, when shared or critical required resources are only available at certain times or are only available in limited quantities. - Can often cause the original critical path to change.
question
Resource Smoothing
answer
- A technique that adjusts the activities of a schedule model such that the requirements for resources on the project do not exceed certain predefined resource limits. - Opposite the technique resource leveling. - The project's critical path is not changed and the completion date may not be delayed. In other words, activities may only be delayed within their free and total float. - May not be able to optimize all resources.
question
Modeling techniques
answer
Examples of modeling techniques: - What-If Scenario Analysis - Simulation - Monte Carlo analysis
question
What-If Scenario Analysis
answer
An analysis of the question "What if the situation represented by scenario 'X' happens?". A schedule network analysis is performed using the schedule to compute the different scenarios.
question
Characteristics of What-If Analysis
answer
The outcome of the whatif scenario analysis can be used to assess the feasibility of the project schedule under adverse conditions, and in preparing contingency and response plans to overcome or mitigate the impact of unexpected situations.
question
Simulation
answer
Involves calculating multiple project durations with different sets of activity assumptions.
question
Monte Carlo Analysis
answer
The most common Simulation technique. A distribution of possible activity durations is defined for each activity and used to calculate a distribution of possible outcomes for the total project.
question
Leads and Lags
answer
- Refinements applied during network analysis to develop a valid schedule. - Leads are used in limited circumstances to advance a successor activity with respect to the predecessor activity. - Lags are used in limited circumstances where processes require a set period of time to elapse between the predecessors and successors without work or resource impact..
question
Schedule Compression
answer
Shortens the project schedule without changing the project scope, to meet schedule constraints, imposed dates, or other schedule objectives.
question
Schedule Compression Techniques
answer
- Crashing - Fast-tracking
question
Crashing
answer
A schedule compression technique in which cost and schedule trade offs are analyzed to determine how to obtain the greatest amount of compression for the least incremental cost.
question
Characteristics of Crashing
answer
• Only works for activities where additional resources will shorten the duration. • Doesn't not always produce a viable alternative and may result in increased risk and/or cost. Examples: • approving overtime, • bringing in additional resources, or • paying to expedite delivery to activities on the critical path
question
Fast Tracking
answer
A schedule compression technique in which phases or activities normally performed in sequence are performed in parallel.
question
Characteristics of Fast Tracking
answer
• May result in rework and increased risk. • Only works if activities can be overlapped to shorten the duration.
question
How to deal with a project with a negative float
answer
The project manager will have to either fast-track or crash the project schedule.
question
Scheduling Tool
answer
Automated scheduling tools expedite the scheduling process by generating start and finish dates based on the inputs of activities, network diagrams, resources and activity durations. A scheduling tool can be used in conjunction with other project management software applications as well as manual methods.
question
Outputs (6) of the Develop Schedule process
answer
1 Schedule baseline 2 Project schedule 3 Schedule data 4 Project calendars 5 Project management plan updates 6 Project documents updates
question
Schedule Baseline
answer
Is a specific version of the project schedule developed from the schedule network analysis. It is accepted and approved by the project management team as the schedule baseline with baseline start dates and baseline finish dates. It is a component of the project management plan.
question
Project Schedule
answer
Includes a planned start date and planned finish date for each activity.
question
Characteristics of Project Schedule
answer
- If resource planning is done at an early stage, then the project schedule would remain preliminary until resource assignments have been confirmed and scheduled start and finish dates are established. - This process usually happens no later than completion of the project management plan. - A project target schedule may also be developed with a defined target start and target finish for each activity. - The project schedule may be presented in summary form, sometimes referred to as the master schedule or milestone schedule, or presented in detail. - Although a project schedule can be presented in tabular form, it is more often presented graphically.
question
Graphical Formats of the Project Schedule
answer
- Bar charts - Milestone charts - Project schedule network diagrams
question
Bar Charts
answer
These charts, with bars representing activities, show activity start and end dates, as well as expected durations. Bar charts are relatively easy to read, and are frequently used in management presentations.
question
Hammock Activity
answer
For control and management communication, the broader, more comprehensive summary activity, is used between milestones or across multiple interdependent work packages, and is displayed in barchart reports.
question
Milestone Charts
answer
These charts are similar to bar charts, but only identify the scheduled start or completion of major deliverables and key external interfaces.
question
Project Schedule Network Diagrams
answer
These diagrams, with activity date information, usually show both the project network logic and the project's critical path schedule activities. These diagrams can be presented in the activity-on-node diagram format, or presented in a time-scaled schedule network diagram format that is sometimes called a logic bar chart.
question
Schedule Data
answer
Includes at least the schedule milestones, schedule activities, activity attributes, and documentation of all identified assumptions and constraints.
question
Schedule Data Supporting Detail
answer
• Resource requirements by time period, often in the form of a resource histogram. • Alternative schedules, such as best-case or worst-case, not resource-leveled, or resource leveled, with or without imposed dates. • Scheduling of contingency reserves. • could include such items as resource histograms, cash-flow projections, and order and delivery schedules.
question
Project calendars
answer
- Identifies working days and shifts that are available for scheduled activities - It distinguishes time periods in days or parts of days that are available to complete scheduled activities from time periods that are not available. A schedule model may require more than one project calendar to allow for different work periods for some activities to calculate the project schedule. -The project calendars may be updated.
question
Project Management Plan Updates
answer
Elements of the project management plan that may be updated: - Schedule baseline - Schedule management plan
question
Project Document Updates
answer
Project documents that may be updated include: - Activity resource requirements - Activity attributes - Calendar - Risk register
question
Activity Resource Requirements
answer
Resource leveling can have a significant effect on preliminary estimates of the types and quantities of resources required. If the resource-leveling analysis changes the project resource requirements, then the project resource requirements are updated.
question
Activity Attributes
answer
Updated to include any revised resource requirements and any other revisions generated by the Develop Schedule process.
question
Calendar
answer
For each project may use different calendar units as the basis for scheduling the project.
question
Risk Register
answer
May need to be updated to reflect opportunities or threats perceived through scheduling assumptions.
question
Process: Control Schedule
answer
- The process of monitoring the status of project activities to update project progress and manage changes to the schedule baseline to achieve the plan. - The key benefit of this process is that it provides the means to recognize deviation from the plan and take corrective and preventive actions and thus minimize risk.
question
Purpose of Control Schedule
answer
- Determining the current status of the project schedule. - Influencing the factors that create schedule changes. - Determining that the project schedule has changed. - Managing the actual changes as they occur.
question
Inputs (6) of the Control Schedule process
answer
1 Project management plan 2 Project schedule 3 Work performance data 4 Project calendars 5 Schedule data 6 Organizational process assets
question
Project Management Plan
answer
- Contains the schedule management plan and the schedule baseline. - The schedule management plan describes how the schedule will be managed and controlled. - The schedule baseline is used to compare with actual results to determine if a chance, corrective action, or preventative action is necessary.
question
Project Schedule
answer
- The most recent version of the project schedule with notations to indicate updates, completed activities, and started activities as of the indicated data date.
question
Work performance data
answer
- Information about project progress, such as which activities have started, their progress, and which activities have finished.
question
Project calendars
answer
A schedule model may require more than one project calendar to allow for different work periods for some activities to calculate the schedule forecasts.
question
Schedule data
answer
Will be reviewed and updated in the Control Schedule process.
question
Organizational Process Assets
answer
- Existing formal and informal schedule control-related policies, procedures and guidelines - Schedule control tools - Monitoring and reporting methods to be used
question
Tools & Techniques (7) for Control Schedule process
answer
1 Performance reviews 2 Project management software 3 Resource optimization techniques 4 Modeling techniques 5 Leads and lags 6 Schedule compression 7 Scheduling tool
question
Performance Reviews
answer
Measure, compare, and analyze schedule performance such as actual start and finish dates, percent complete, and remaining duration for work in progress.
question
Techniques of Performance Reviews
answer
- Trend analysis - Critical path method - Critical Chain method - Earned Value Management (EVM)
question
Trend analysis
answer
Examines project performance over time to determine whether performance is improving or deteriorating. Graphical analysis techniques are valuable for understanding performance to date and for comparison to future performance goals in the form of completion dates.
question
Critical path method
answer
Comparing the progress along the critical path can help determine schedule status. The variance on the critical path will have a direct impact on the project end date. Evaluating the progress of activities on near critical paths can identify schedule risk.
question
Critical Chain method
answer
Comparing the amount of buffer remaining to the amount of buffer needed to protect the delivery date can help determine schedule status. The difference between the buffer needed and the buffer remaining can determine whether corrective action is appropriate.
question
Earned Value Management (EVM)
answer
- Earned Value Management utilized the schedule variance(SV) and schedule performance index (SPI). - An important part of schedule control is to decide if the schedule variation requires corrective action.
question
Variance Analysis
answer
- Schedule performance measurements (SV - schedule variance, SPI - schedule performance inde) are used to assess the magnitude of variation to the original schedule baseline. - The total float variance is also an essential planning component to evaluate project time performance. - Important aspects of project schedule control include determining the cause and degree of variance relative to the schedule Baseline and deciding whether corrective or preventive action is required.
question
EVM
answer
Earned Value Management
question
SV
answer
Schedule Variance
question
SPI
answer
Schedule Performance Index
question
Project Management Software
answer
Project management software for scheduling provides the ability to track planned dates versus actual dates, and to forecast the effects of changes to the project schedule.
question
Resource optimization techniques
answer
Involve the scheduling of activities and the resources required by those activities while taking into consideration both the resource availability and the project time.
question
Modeling Techniques
answer
Used to review various scenarios guided by risk monitoring to bring the schedule model into alignment with the project management plan and approved baseline.
question
Leads and Lags
answer
Used to find ways to bring project activities that are behind into alignment with the plan.
question
Schedule Compression
answer
Used to find ways to bring project activities that are behind into alignment with the plan.
question
Scheduling Tool
answer
- Schedule data is updated and compiled into the schedule to reflect actual progress of the project and remaining work to be completed. - The scheduling tool and the supporting schedule data are used in conjunction with manual methods or other project management software to perform schedule network analysis to generate an updated project schedule.
question
Outputs (6) of the Control Schedule process
answer
1 Work performance information 2 Schedule forecasts 3 Change requests 4 Project management plan updates 5 Project documents updates 6 Organizational process assets updates
question
Work performance information
answer
The calculated SV and SPI values for WBS components, in particular the work packages and control accounts, are documented and communicated to stakeholders.
question
Schedule forecasts
answer
- They are estimates or predictions of conditions and events in the project's future based on information and knowledge available at the time of the forecast. - Forecasts are updated and reissued based on work performance information provided as the project is executed. - The information is based on the project's past performance and expected future performance, and includes earned value performance indicators that could impact the project in the future.
question
Change Requests
answer
- Schedule variance analysis, along with review of progress reports, results of performance measures, and modifications to the project schedule can result in change requests to the schedule baseline and/or to other components of the project management plan. - Change requests are processed for review and disposition through the Perform Integrated Change Control process. - Preventive actions may include recommended changes to reduce the probability of negative schedule variances.
question
Project Management Plan Updates
answer
Elements can be updated: - Schedule baseline - Schedule management plan - Cost baseline
question
Schedule Baseline
answer
Changes to the schedule baseline are incorporated in response to approved change requests related to project scope changes, activity resources, or activity duration estimates.
question
Schedule Management Plan
answer
May be updated to reflect a change in the way the schedule is managed.
question
Cost Baseline
answer
May be updated to reflect changes caused by compression or crashing techniques.
question
Project Document Updates
answer
Project documents can be uptaded: - Schedule data - Project schedule - Risk Register
question
Schedule Data
answer
New project schedule network diagrams may be developed to display approved remaining durations and modifications to the work plan. In some cases, project schedule delays can be so severe that development of a new target schedule with forecasted start and finish dates is needed to provide realistic data for directing the work, and for measuring performance and progress.
question
Project Schedule
answer
An updated project schedule will be generated from the updated schedule data to reflect the schedule changes and manage the project.
question
Risk Register
answer
The risk register, and risk response plans within it, may also be updated based on the risks that may arise due to schedule compression techniques.
question
Organizational Process Assets Updates
answer
Factors can be: - Causes of variances, - Corrective action chosen and the reasons, and - Other types of lessons learned from project schedule control
question
All baselines and plans are a part of
answer
the project management plan
question
Plan Schedule Management Define Activities Sequence Activities Estimate Activity Resources Estimate Activity Durations Develop Schedule
answer
Planning Process Group
question
Control Schedule
answer
Monitoring and Controlling Process Group