Which of the following is a difference between project management and portfolio management? a. Project management involves making wise investment decisions whereas portfolio management does not. b. Portfolio management is an easy task whereas project management is a more difficult task. c. Portfolio management asks questions like, "Are we carrying out projects efficiently?" whereas project management asks questions such as "Are we investing in the right areas?" d. Project management addresses specific, short-term goals whereas portfolio management focuses on long-term goals.
answer
d. Project management addresses specific, short-term goals whereas portfolio management focuses on long-term goals. Feedback: Individual projects often address tactical goals, whereas portfolio management addresses strategic goals. Tactical goals are generally more specific and short-term than strategic goals.
question
A _____ is an organizational group responsible for coordinating the project management function throughout an organization. a. Project Management Office b. Project Management Professional c. Project Management Center d. Portfolio Group
answer
a. Project Management Office Feedback: In the 1990s, many companies began creating Project Management Offices to help them handle the increasing number and complexity of projects. A Project Management Office (PMO) is an organizational group responsible for coordinating the project management function throughout an organization.
question
In which of the following areas of management is payback analysis most likely to be used? a. Human resource b. Communication c. Cost d. Quality
answer
c. Cost Feedback: Tools used in cost management include payback analysis, earned value management, project portfolio management, and cost estimates among others.
question
Which of the following tools can best help in efficient communication management? a. Kick-off meetings b. Impact matrices c. Requests for quotes d. Fast tracking
answer
a. Kick-off meetings Feedback: Kick-off meetings are an important tool in project communication management. Other tools in project communication management are communications management plans, conflict management, communications media selection, and progress reports.
question
Fast tracking is an example of a tool used in _____ management. a. time b. quality c. communication d. risk
answer
a. time Feedback: Time management tools include Gantt charts, project network diagrams, critical path analysis, crashing, fast tracking, and schedule performance measurements.
question
A Gantt chart is a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a ____ format. a. calendar b. line graph c. bar graph d. pie chart
answer
a. calendar Feedback: A Gantt chart was developed by Henry Gantt for scheduling work in factories. A Gantt chart is a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in calendar form.
question
An important tool for project scope management is a. fast tracking b. crashing c. a Gantt chart d. a work breakdown structure
answer
d. a work breakdown structure Feedback: Scope management uses scope statements, work breakdown structures, statements of work, requirements analyses, scope management plans, scope verification techniques, and scope change controls.
question
Which of the following provides certification as a Project Management Professional? a. PMS b. PMC c. PMI d. PMP
answer
d. PMP Feedback: PMI or the Project Management Institute provides certification as a Project Management Professional (PMP). A Project Management Professional (PMP) is someone who has documented sufficient project experience and education, agreed to follow the PMI code of professional conduct, and demonstrated knowledge of project management by passing a comprehensive examination.
question
Team building exercises and motivation techniques are tools used in _____ management. a. procurement b. scope c. human resource d. cost
answer
c. human resource Feedback: Motivation techniques, empathic listening, resource histograms, and team building exercises are tools used in human resource management.
question
Galaxy, a construction company, buys a particular brand of tiles manufactured by Tiles and Floors, an eco-friendly tile manufacturing company. However, Tiles and Floors has declared bankruptcy and closed down. At present, Galaxy is facing a crisis because there are no other manufacturers in the market that supplies eco-friendly tiles. Which of the following constraints is Galaxy currently facing? a. Resources b. Time c. Scope d. Cost
answer
a. Resources Feedback: Every project is constrained in different ways. For some projects, resources are the main concern.
question
The project time management knowledge area maps to the _____ process group through the activity of schedule control. a. initiating b. planning c. executing d. monitoring and controlling
answer
d. monitoring and controlling Feedback: The project time management knowledge area maps to the monitoring and controlling process group through the activity of schedule control.
question
_____ includes measuring progress toward project objectives and taking corrective action to match progress with the plan. a. Planning b. Montioring and controlling c. Executing d. Initiating
answer
b. Montioring and controlling Feedback: Monitoring and controlling is done throughout the life of a project and involves 9 of the 10 project management areas.
question
The project management plan is the output of the planning process of project _____. a. integration management b. quality management c. scope management d. procurement management
answer
a. integration management Feedback: The project management plan,which is part of the planning process, is the output of project integration management.
question
The _____ process involves gaining stakeholder and customer acceptance of the final products and services and bringing the project, or project phase, to an orderly end. a. executing b. closing c. planning d. monitoring
answer
b. closing Feedback: The closing process involves gaining stakeholder and customer acceptance of the final products and services and then bringing the project or project phase to an orderly end. It includes verifying that all of the deliverables are complete, and it often includes a final project report and presentation.
question
_____ are an output of the executing process of project integration management. a. Deliverables b. Issue logs c. Resource calendars d. Enterprise environmental factor updates
answer
a. Deliverables Feedback: Deliverables are an output of the executing process of project integration management.
question
_____ processes include defining and authorizing a project or project phase. a. Initiating b. Planning c. Executing d. Monitoring and controlling
answer
a. Initiating Feedback: Initiating processes include defining and authorizing a project or project phase. Initiating processes take place during each phase of a project.
question
One of the main outputs of the initiation process is _____. a. creating the work breakdown structure b. selecting the project manager c. developing the project charter d. identifying the project sponsor
answer
c. developing the project charter Feedback: The main outputs of the initiation process are a project charter and a stakeholder register.
question
Organizational process assets update is the output of the closing process of _____ a. project integration management b. project quality management c. project procurement management d. project time management
answer
a. project integration management Feedback: The closing process involves gaining stakeholder and customer acceptance of the final products and services and then bringing the project or project phase to an orderly end. It includes verifying that all of the deliverables are complete, and it often includes a final project report and presentation.
question
The _____ provides a basis for creating the project schedule and performing earned value management for measuring and forecasting project performance. a. scope statement b. cost management plan c. work breakdown structure d. project charter
answer
c. work breakdown structure Feedback: The WBS is a very important tool in project management because it provides the basis for deciding how to do the work. The WBS also provides a basis for creating the project schedule and performing earned value management for measuring and forecasting project performance.
question
Which of the following project parameters would be compatible with the use of the agile approach? a. Projects with inexperienced and dispersed teams b. Projects that have a fairly rigid completion date c. Projects with clear-up front requirements d. Projects that have more flexible scheduling
answer
d. Projects that have more flexible scheduling Feedback: Projects with heavy constraints, inexperienced and dispersed teams, large risks, generally clear up-front requirements, and a fairly rigid completion date are best done using a predictive approach. In contrast, projects with less rigid constraints, experienced and preferably co-located teams, smaller risks, unclear requirements, and more flexible scheduling would be more compatible with an agile approach.
question
The project cost management knowledge area maps to the _____ process group through the activities of estimating costs and budget determination. a. initiating b. planning c. executing d. monitoring and controlling
answer
b. planning Feedback: The project cost management knowledge area maps to the planning process group through the activities of estimating costs and budget determination.
question
The improvement of the product and process in the Scrum method is discussed at the _____. a. sprint reflection meeting b. sprint review meeting c. kick-off meeting d. daily Scrum meeting
answer
a. sprint reflection meeting Feedback: The improvement of the product and process in the Scrum method is discussed at the sprint reflection meeting.
question
During _____ processes for a new project, the organization recognizes that a new project exists, and completes a project charter as part of this recognition. a. initiating b. planning c. opening d. controlling
answer
a. initiating Feedback: While initiating processes for a new project, the organization recognizes that a new project exists, and completes a project charter as part of this recognition.
question
A _____ is an important Scrum artifact used to graphically display progress on each sprint during the monitoring and controlling process. a. WBS b. sprint backlog c. burndown chart d. product backlog
answer
c. burndown chart Feedback: A burndown chart is an important artifact used to graphically display progress on each sprint.
question
Which of the following activities is a part of the planning process of the Scrum? a. Determining how many sprints will compose each release b. Demonstrating the product during a sprint review meeting c. Completing tasks each day during sprints d. Creating sprint backlog
answer
d. Creating sprint backlog Feedback: Creating product backlogs, sprint backlogs and release backlogs are all part of the planning process of the scrum.
question
A _____ is usually not necessary to the Scrum method. a. team contract b. velocity estimate c. Gantt chart d. product backlog
answer
a. team contract Feedback: Because Scrum implies that team members work as a self-directed group, coached by the ScrumMaster, a team contract should not be necessary.
question
_____ is a planning process that is within the Project Scope Management knowledge area. a. chedule development b. Developing a project management plan c. Creation of a WBS d. Quality planning
answer
c. Creation of a WBS Feedback: Creation of a WBS is a planning process falling under the Project Scope Management knowledge area.
question
A common _____ process is reporting performance, where project stakeholders can identify any necessary changes that may be required to keep the project on track. a. executing b. closing c. monitoring and controlling d. planning
answer
c. monitoring and controlling Feedback: Monitoring and controlling processes include regularly measuring and monitoring progress to ensure that the project team meets the project objectives. A common monitoring and controlling process is reporting performance, where project stakeholders can identify any necessary changes that may be required to keep the project on track.
question
Developing a _____ is a planning process that occurs in the Project Integration Management knowledge area. a. schedule management plan b. project management plan c. WBS d. quality management
answer
b. project management plan Feedback: Developing a project management plan is a planning process falling under the Project Integration Management knowledge area.
question
The main purpose of project plans is to a. schedule management plans b. define project scope c. estimate activity resources d. guide project execution
answer
d. guide project execution Feedback: Developing a project management plan is a planning process falling under the Project Integration Management knowledge area.